🇿🇦 South AfricaMunicipality Page12 min read

City of Tshwane SSEG Solar Registration Guide 2026

Register a Tshwane-supplied solar or storage system: the City SSEG application, written approval, commissioning documents, bidirectional metering and the 2026/27 embedded-generation tariff.

Nimesh Katariya

Written by

Nimesh Katariya

Solar-industry contributor

Rainer Neumann

Edited by

Rainer Neumann

Editorial contributor · SurgePV

Published ·Last updated ·Regulator: City of Tshwane Energy and Electricity Department

Tshwane solar registration starts with the electricity connection, not the suburb name. A Pretoria or Centurion address does not establish who supplies its meter. Check the account and network connection, then use the municipality’s process if Tshwane is the supplier. Eskom-supplied sites have a different route.

Tshwane SSEG rules at a glance

Item Position in the City documents Source
Contact for registration and applications sseg@tshwane.gov.za 2017 requirements, 19 March 2024 notice, electricity FAQ
Approval before installing Written approval required before installation starts 2017 requirements, April 2024 policy revision
Inverter evidence NRS 097-2-1 type test certificate from an accredited third-party test house 2017 requirements, April 2024 policy revision
Size limit on a shared LV feeder 25% of notified maximum demand, up to 20 kVA 2017 requirements (from NRS 097-2-3)
Export metering Bidirectional meter installed by the City at the customer’s cost 2017 requirements, April 2024 policy revision
Export credit, 2026/27 94,13 c/kWh, excluding VAT, after City approval 2026/27 tariff schedule
Monthly fixed charge, domestic, 2026/27 R324,00 per metering point, excluding VAT 2026/27 tariff schedule
Processing time Not set in any of the documents checked All documents listed below

Figures are quoted as the City publishes them, with a decimal comma.

Which City documents govern

The City’s embedded-generation process rests on a Council decision of 30 March 2017 (Ref. 26516/1). Council took note of the Embedded Generation Policy and its application procedure and approved grid-tied embedded generation for private and commercial use. The item’s annexures include the policy, the Requirements for Embedded Generation (final draft v8, October 2016), the application form and the commissioning report. The City publishes this pack on its website as “Proposed Embedded Generation Policy to support and formalise procedure”. Despite the file name, it contains the resolved Council item and its stamped resolution.

In April 2024 the City revised the policy (revision 01). The Policy on Small Scale Embedded Generation (SSEG) for the City of Tshwane was published on the City’s site in September 2024. It adds metering options, rules for changes to approved systems and exemptions for solar water heaters and unwired plug-in inverters.

The minutes of the Council meeting of 29 May 2025 (item 11, Ref. 87515/1) record that Council approved the embedded generation policy and its implementation after public consultation. Council also noted the change of name from “small scale embedded generation policy” to “embedded generation policy”. The City’s document library holds the 2017 pack and the April 2024 revision but no separate copy of the text adopted in 2025. This guide therefore names the document behind each rule.

The City’s media statement of 19 March 2024 says registration on the City database is mandatory for customers who want to feed electricity into the grid. It also says export is allowed only for registered embedded-generation customers with bidirectional meters, and directs registration queries to sseg@tshwane.gov.za. The City’s electricity FAQ gives the same address for embedded-generation enquiries and applications.

Prepare the Tshwane application package

The City’s application form is titled “Application for inverter-based grid-tied solar PV installation” (Annexure C to the 2017 Council item). It covers inverter-based PV systems up to 350 kVA. Request the current version from sseg@tshwane.gov.za before you complete it.

Record What the City documents ask for
Applicant Property owner details and signature, plus the applicant if different. A body corporate that resells electricity applies as the property owner (2017 requirements). Tenants of a reseller cannot apply directly (April 2024 revision)
Property Erf number, electricity account number, meter number, current tariff and connection capacity (circuit breaker size, or notified maximum demand for non-residential customers)
System Total PV DC capacity (kW), total inverter AC capacity (kVA), grid connection mode, storage capacity (kWh), earthing arrangement, inverter and panel make and model, and monthly estimates of production, consumption and export
Inverter evidence NRS 097-2-1 type test certificate and test report from a third-party test house that is SANAS accredited or recognised by ILAC or IAF under ISO/IEC 17025
Drawings Preliminary circuit diagram showing the major components, point of common coupling, isolating and interface devices, protection and earthing. Commercial and industrial sites also attach a site plan
Installer Installer company and contact details and the installer’s signature
Other departments Building and emergency services clearance fields. The form notes that no building plans are needed if the installation projects no more than 1,5 m (measured perpendicularly) above the roof and/or no more than 600 mm above the highest point of the roof
New connections The SSEG form does not cover a new supply. A separate new-connection application must accompany it

The April 2024 revision adds that the test certificate must generally be for the current version of NRS 097-2-1, and the City may refuse certificates for old versions. Fitting reverse-feed blocking does not remove the certificate requirement. A storage inverter that can feed power into the customer’s wiring also needs NRS 097-2-1 certification. The revision recommends installers accredited under PV GreenCard or the P4 quality assurance programme and says the City intends to make such accreditation a requirement.

A type test certificate covers the inverter. An electrical Certificate of Compliance covers the installation. Neither one grants network connection or export approval. The NRS interface guide explains that distinction.

Size limits Tshwane applies

The 2017 Requirements for Embedded Generation apply the NRS 097-2-3 simplified connection criteria to low-voltage systems up to 350 kVA. Generator size means the maximum output at the point of connection, which for PV is the inverter output, not the panel kWp.

Supply (shared LV feeder) Service circuit breaker Notified maximum demand Maximum individual generation
Single phase 20 A 4,6 kVA 1,2 kVA
Single phase 60 A 13,8 kVA 3,45 kVA
Single phase 80 A 18,4 kVA 4,6 kVA
Three phase 60 A and 80 A 41,4 kVA 13,8 kVA (4,6 kVA per phase)

On a shared low-voltage feeder, individual generation may not exceed 25% of the notified maximum demand, up to 20 kVA. On a dedicated low-voltage feeder the limit is 75% of the notified maximum demand. Systems above 4,6 kVA must be balanced across the phases. The City may use billing data where the notified maximum demand is under-used. Systems outside these criteria, or above 350 kVA, are likely to need a grid impact study at the applicant’s cost. The City may also refuse further connections where the combined generation on a network section would harm it. The limit stated in your written approval is the one that applies to your project.

Approval, commissioning and final connection

The 2017 requirements set out five steps, and the April 2024 revision repeats the same flow.

  1. Complete the application form.
  2. Submit the form and attachments. The requirements say to email them to sseg@tshwane.gov.za, and the process chart also allows the customer care office of your region. The City acknowledges receipt.
  3. The Energy and Electricity Department evaluates the application, inspects the site if needed, and tells you in writing whether it is approved. Installation may start only after that notice, and the City recommends not paying for equipment before it.
  4. After installation, the system may connect to the grid only for commissioning and must then stay disconnected until the City approves it in writing. Notify the City of the commissioning date. The City inspects larger systems at commissioning and may skip the inspection for systems of 4,6 kVA or less.
  5. The City gives written approval to connect, with any operating conditions, and records the system in its database, including any tariff change.

The commissioning submission listed in the 2017 requirements is:

  • the SSEG commissioning report, signed off by an ECSA-registered professional engineer or technologist
  • a signed contract for embedded generation with the City
  • as-built electrical drawings
  • the NRS 097-2-1 inverter type test certificate and test report
  • an electrical installation Certificate of Compliance under SANS 10142-1
  • operation and maintenance procedures, also kept on site.

The April 2024 revision keeps professional sign-off on commissioning until SANS 10142-1-2 is implemented and refers to the Requirements document for who signs.

Changes after approval need City review. Under the April 2024 revision, a capacity expansion or a configuration change such as adding storage that can run in parallel needs a new application. Replacing significant components such as the inverter or protection equipment, or moving the system, needs a new commissioning report. A decommissioned system must be physically disconnected at the owner’s cost, with a decommissioning report and a Certificate of Compliance. When the property or electricity account changes hands, the City requires a change-of-ownership declaration, or the system must be decommissioned. This is not an instruction to adjust electrical or protection settings yourself.

Metering, tariffs and the first bill

Both the 2017 requirements and the April 2024 revision say exporting customers need a bidirectional meter, installed by the City at the customer’s cost. The City’s electricity FAQ adds that after approval the customer receives a bidirectional meter with separate import and export registers. The April 2024 revision also sets these rules:

  • Grid-tied customers choose export or non-export and may switch only once per financial year.
  • Exporting customers provide a meter box to the City’s specification on the street-front boundary, at their own cost.
  • Non-exporting customers must install reverse power flow blocking.
  • A non-exporting customer on a credit meter drawing under 100 A has the meter replaced with a split prepaid meter at the City’s cost.

The embedded-generation charges sit in Schedule 2 (Supply of Electricity) of the City’s annual tariff determination. Both schedules call these tariffs “interim or pilot”. They apply to customers who remain net consumers, and imports are charged at the customer’s normal tariff.

Charge (excluding VAT) 2025/26: 1 July 2025 to 30 June 2026 2026/27: 1 July 2026 to 30 June 2027
Monthly fixed charge, domestic single or three phase, per metering point R297,80 R324,00
Monthly fixed charge, agricultural holdings and farmlands R1 157,20 R1 259,03
Credit (reverse) tariff for excess energy exported, after City approval 86,52 c/kWh 94,13 c/kWh
Wheeling through the City network 102,12 c/kWh 111,11 c/kWh
Bidirectional metering device, low voltage, single phase up to 80 A R11 281,23 R2 820,31
Bidirectional metering device, low voltage, three phase R12 785,39 (up to 100 A) R4 474,89 (up to 80 A)
Bidirectional metering device, medium voltage R13 838,30 R6 365,62

Sources: 2025/26 tariff determination, Local Authority Notice 648 of 2025, Gauteng Provincial Gazette 217, 18 June 2025; 2026/27 tariff determination, Part 1, published by the City as Notice 214, Gauteng Provincial Gazette 186, 17 June 2026. Other customer categories pay the fixed charges of their normal tariff. The schedules list the metering-device charges under metered connection fees, so confirm with the City which charge applies to your connection.

For context, the 2026/27 domestic import energy charge runs from 324,12 c/kWh for the first 100 kWh to 445,51 c/kWh above 650 kWh, excluding VAT. The City’s July 2026 tariff notice reports an 8,8% increase in municipal electricity tariffs from 1 July 2026. The export credit is therefore well below the import rate, so self-consumption is worth more per kWh than export.

Two points need care. First, the City’s electricity FAQ still quotes an export credit of 11,99 c/kWh. That conflicts with the gazetted schedules, and the schedule for the current financial year governs. Second, the 2016 requirements say reverse feed would not be compensated. The 2025/26 and 2026/27 schedules now include a credit tariff, so that statement no longer reflects the tariff.

The schedules set the credit rate but do not say how a credit balance is carried forward, expires or is paid out. Before estimating savings, get the account category, fixed charges and settlement terms in writing. Reconcile the first bill with the meter readings.

Registration workflow

Confirm the actual electricity supplier

Check the meter and account. Eskom-supplied customers inside Tshwane apply to Eskom. Where a body corporate or landlord resells electricity, the application comes from the City’s account holder, not the tenant.

Get the current form and prepare the attachments

Request the current application form from sseg@tshwane.gov.za. Complete it with property owner and installer signatures, inverter and panel details, the NRS 097-2-1 inverter type test certificate, a preliminary circuit diagram and, for commercial or industrial sites, a site plan. Add a separate new-connection application if the property has no supply yet.

Submit and obtain written approval

Email the form and attachments to sseg@tshwane.gov.za, or hand them in at the customer care office of your region. Wait for the City’s written approval before buying or installing equipment.

Install, commission and submit the documents

Commission the system and submit the signed commissioning report, the signed embedded-generation contract, as-built drawings, the inverter certificate and test report, the SANS 10142-1 Certificate of Compliance and the operation and maintenance procedures. The City may inspect at commissioning.

Obtain final connection, metering and tariff confirmation

Connect permanently only after the City’s written approval. Exporting customers need a bidirectional meter, installed by the City at the customer’s cost, and move onto the embedded-generation tariff. Ask for a new application before expanding or reconfiguring the system.

A practical status record

Stage Retain Stronger claim to avoid
Application Form version, attachments, receipt and open questions “Approved” because sent
Installation decision City’s written approval and its conditions Unconditional network or export permission
Commissioning Signed commissioning report, CoC, inverter certificate and as-built drawings CoC replaces municipal approval
Final connection Written approval to connect, operating conditions and meter details Export permitted because the system works
Billing Current tariff schedule, eligibility and the actual bill Automatic credit carry-forward or cash payment

None of the City documents checked sets a processing time for SSEG applications. Ask for the next review step and any missing information rather than building a customer installation date around an assumed target.

Use the South Africa compliance overview and Eskom registration guide to confirm the correct network path. Solar design software can be evaluated for the project documentation workflow; it does not certify municipal compliance or grant approval.

Review your solar documentation workflow

Bring a sanitized project and current municipal checklist to a SurgePV demo. Confirm the available outputs and retain qualified technical review and municipal approval.

Request a demo

Official sources checked

All documents below were retrieved from tshwane.gov.za and checked on 9 November 2026.

  • City of Tshwane, Council item “Proposed Embedded Generation Policy to support and formalise procedure for installations within the City”, Ref. 26516/1, resolved 30 March 2017, with Annexure A (Policy on Embedded Generation, November 2016), Annexure B (Requirements for Embedded Generation, final draft v8, October 2016) and Annexure C (application form and SSEG commissioning report). PDF
  • City of Tshwane, Policy on Small Scale Embedded Generation (SSEG), revision 01, April 2024, published September 2024. PDF
  • City of Tshwane, minutes of the Ordinary Council Meeting of 29 May 2025, item 11 (Ref. 87515/1), report on public consultation outcomes for the energy wheeling and embedded generation policies. PDF
  • City of Tshwane, determination of fees, charges and tariffs for 1 July 2025 to 30 June 2026, Local Authority Notice 648 of 2025, Gauteng Provincial Gazette 217, 18 June 2025, Schedule 2 Part III. PDF
  • City of Tshwane, various fees, charges and tariffs for 1 July 2026 to 30 June 2027, Part 1, Notice 214, Gauteng Provincial Gazette 186, 17 June 2026, Schedule 2 section 22 and Part II item B1.8.5. PDF, listed on the City’s promulgated tariffs page
  • City of Tshwane, media statement “Tshwane calls on residents who want to feed excess energy on the City’s grid to come forward and register”, 19 March 2024. Page
  • City of Tshwane, electricity prepaid meter FAQ (undated). Page
  • City of Tshwane, “It’s hike time: Tariff increases to hit Tshwane residents”, 2 July 2026. Page

Frequently Asked Questions

How do I register a solar system with the City of Tshwane?

If the City of Tshwane supplies your meter, request the current application form from sseg@tshwane.gov.za, the SSEG address the City publishes. The City form (“Application for inverter-based grid-tied solar PV installation”) is signed by the property owner and the installer and needs the NRS 097-2-1 inverter type test certificate and a preliminary circuit diagram. The City evaluates the application and replies in writing. Install only after written approval, then submit the commissioning documents and wait for written approval to connect. Eskom-supplied customers inside Tshwane apply to Eskom instead.

What is the solar export limit for Tshwane customers?

The City Requirements for Embedded Generation apply the NRS 097-2-3 size limits. On a shared low-voltage feeder a generator may not exceed 25% of the notified maximum demand, up to 20 kVA: 3,45 kVA on a 60 A single-phase supply, 4,6 kVA on 80 A single-phase and 13,8 kVA on a 60 A or 80 A three-phase supply. On a dedicated low-voltage feeder the limit is 75% of the notified maximum demand. Generator size means inverter output, not panel kWp. Systems outside those limits are likely to need a grid impact study at the applicant’s cost, and the limit in your written approval governs.

Does the City of Tshwane offer net metering for solar customers?

Not one-for-one. Imports are billed at your normal tariff and approved exports earn a separate credit (reverse) tariff of 94,13 c/kWh from 1 July 2026 to 30 June 2027 (86,52 c/kWh in 2025/26), excluding VAT. Embedded-generation customers also pay a monthly fixed charge per metering point, R324,00 for domestic supplies in 2026/27. The credit applies only after City approval with a bidirectional meter. The tariff schedule does not set out carry-forward or cash payment of credits, so get those terms in writing.

Does Tshwane require pre-approval before installing solar?

Yes. The City requirements say installation may start only after the City confirms in writing that the application succeeded, and recommend not paying for equipment before then. After installation the system may connect to the grid only for commissioning tests and must stay disconnected until the City gives written approval to connect.

How long does Tshwane SSEG registration take?

None of the City documents checked for this guide (the 2017 policy and requirements, the April 2024 policy revision and the 2025/26 and 2026/27 tariff schedules) sets a processing time for SSEG applications. Ask sseg@tshwane.gov.za for the status of your application and any missing information, and do not promise a customer a fixed completion date.

About the Contributors

Author
Nimesh Katariya
Nimesh Katariya

Solar-industry contributor

Nimesh Katariya contributes to SurgePV content concerning solar project workflows. This profile intentionally does not assert certifications, project totals, seminar counts, or technical-review authority without retained verification evidence.

Editor
Rainer Neumann
Rainer Neumann

Editorial contributor · SurgePV

Rainer Neumann is credited as an editorial contributor on SurgePV content. This profile does not assert engineering credentials, project totals, software-testing experience, education, speaking engagements, or media citations because independent verification evidence is not retained in the publication record.

Tshwane SSEG solar registration Pretoria 2026City of Tshwane solar approvalPretoria solar SSEG applicationTshwane net metering solarTshwane electricity solar registration

Solar Compliance Updates in Your Inbox

Join 2,000+ solar professionals. Regulatory changes, code updates, and design tips — weekly.

No spam · Unsubscribe anytime

Choose which optional technologies SurgePV may use. Essential storage remains active for security and requested features.