🇿🇦 South AfricaRegulatory Guide10 min read

Certificate of Compliance for Solar in South Africa

A Certificate of Compliance (CoC) is mandatory for every solar PV installation in South Africa.

Nimesh Katariya

Written by

Nimesh Katariya

Solar-industry contributor

Rainer Neumann

Reviewed by

Rainer Neumann

Editorial contributor · SurgePV

Published ·Last reviewed ·Regulator: Department of Labour (DoL)

A Certificate of Compliance is not an optional document in South African solar. It is a legal requirement under the Occupational Health and Safety Act — and without it, your Eskom or municipality SSEG registration will not be completed. More practically, it is the document that protects the homeowner’s insurance, enables property sale, and provides evidence that the installation is safe. See South Africa Load Shedding Solar Design for more. See South Africa Section 12B Solar Tax Incentive for more.

This guide covers every aspect of the CoC process for solar installations: who issues it, what it covers, when you need a new one, and how to handle tricky situations.

Legal Basis
OHS Act 85 of 1993 — Electrical Installations Regulations
Registration Verification
Department of Labour — provincial offices can verify contractor registration
Standard Referenced
SANS 10142-1:2020 — Wiring of premises
Required For
All electrical installations including solar PV, battery storage, and associated wiring
Last Updated
April 2026

Always Get the CoC from the Installing Contractor

The contractor who installs the system is best positioned to issue the CoC — they know what they installed and can stand behind the work. Getting a second contractor to issue a CoC for someone else’s installation requires a full independent inspection and means the second contractor takes on liability for work they did not do. Always agree upfront that the installing contractor will provide the CoC.

What the CoC Certifies

The CoC is a legal declaration by a registered electrical contractor that the electrical installation complies with SANS 10142-1 at the time of inspection. For solar, this means:

Element What the Contractor Verifies
DC cabling Correct type (UV-rated), correct size, correct routing
DC protection String fuses (where required), DC circuit breaker ratings
DC isolators Present, labelled, lockable, correctly rated
Earthing/bonding Array structure bonded and connected to earth system
Surge protection SPDs installed where required by design
AC wiring Correct cable size, protection, connection to distribution board
AC isolator Present, labelled, lockable
Distribution board Solar connection clearly labelled, protective devices present
Inverter settings Protection settings match NRS 097-2-1 requirements (commissioning report)
Labels All required DC and AC labels installed and legible
Documentation As-built drawing matches physical installation

When You Need a New CoC

Trigger Action Required
New solar installation CoC required — cannot connect to grid without it
Adding more solar panels New or amended CoC required
Replacing the inverter New CoC required (different model, different settings)
Installing battery storage New CoC required for the battery addition
Property sale Buyer’s conveyancer will request current CoC
Insurance claim involving electrical installation Insurer may require valid CoC to process claim
Significant rewiring New CoC required for the rewired portion

Verifying a CoC Is Valid

Before accepting a CoC from a contractor, verify:

  1. DoL registration number is visible on the CoC and matches the contractor
  2. Contractor’s details — business name, address, registration number
  3. Installation address — matches the property
  4. Date of inspection — recent enough to reflect the current installation
  5. Contractor’s signature and stamp — both required
  6. Description of work — covers solar PV installation, not just “general electrical”

To verify a contractor’s DoL registration, contact the Department of Labour’s provincial office for the area where the installation took place, or request the contractor’s registration certificate directly.

CoC Failures: Common Causes

Failure Why It Happens
Non-UV-rated cable on roof Installer used building cable to save cost
Missing DC isolation DC isolator omitted or not installed near inverter
No earth continuity in array structure Mounting clips assumed to provide continuity without testing
Incorrect inverter protection settings Factory defaults not reconfigured to NRS 097
Labels missing Installer did not install labels before inspection
As-built drawing not matching installation String count changed during installation without updating drawings

Generate CoC-Ready Solar Documentation Before Installation

SurgePV produces the as-built single-line diagram, cable schedule, and commissioning record that your DoL-registered contractor needs to complete the CoC inspection efficiently.

See the Documentation Tool

No commitment required · 20 minutes · Live project walkthrough

Frequently Asked Questions

Can the homeowner request a CoC for their own installation? The homeowner cannot issue a CoC. Only a DoL-registered electrical contractor can issue a CoC. The homeowner can, however, request a CoC inspection from any registered electrical contractor — they do not have to use the original installer. A second-party CoC inspection is common when purchasing a property with an existing solar system.

My solar installer offered to issue the CoC without visiting the site. Is this legal? No. A CoC cannot be issued without a physical inspection of the installation. A CoC issued without an on-site inspection is fraudulent and legally invalid. Do not accept a CoC that was not preceded by a documented site inspection. The issuance of a false CoC is a criminal offence under the OHS Act.

What if the inspector finds non-compliances? The contractor lists the non-compliances and the CoC is not issued until they are rectified. The installer should then carry out the rectification work. After rectification, the contractor re-inspects the relevant portions and issues the CoC if satisfied. Keep a record of what was found and what was done to rectify it — this documents the installation history.

See the SANS 10142-1 guide, the DoL vs ECSA sign-off guide, and the Eskom SSEG registration guide for related topics. Use solar software to generate installation documentation that supports fast CoC inspections.

About the Contributors

Author
Nimesh Katariya
Nimesh Katariya

Solar-industry contributor

Nimesh Katariya contributes to SurgePV content concerning solar project workflows. This profile intentionally does not assert certifications, project totals, seminar counts, or technical-review authority without retained verification evidence.

Editor
Rainer Neumann
Rainer Neumann

Editorial contributor · SurgePV

Rainer Neumann is credited as an editorial contributor on SurgePV content. This profile does not assert engineering credentials, project totals, software-testing experience, education, speaking engagements, or media citations because independent verification evidence is not retained in the publication record.

certificate of compliance solar South AfricaCoC solar installation South Africaelectrical CoC solar South AfricaDoL CoC solar South Africasolar installation sign off South Africa

Solar Compliance Updates in Your Inbox

Join 2,000+ solar professionals. Regulatory changes, code updates, and design tips — weekly.

No spam · Unsubscribe anytime

Choose which optional technologies SurgePV may use. Essential storage remains active for security and requested features.