🇺🇸 United StatesTechnical Guide11 min read

NEC 690.8 Circuit Sizing: Conductor Ampacity Rules for Solar PV Systems

NEC 690.8 requires solar conductors to be rated at 125% of the module short-circuit current, plus additional derating for temperature and conduit fill.

Rainer Neumann

Written by

Rainer Neumann

Editorial contributor · SurgePV

Keyur Rakholiya

Edited by

Keyur Rakholiya

CEO & Co-Founder · SurgePV

Published ·Last updated ·Regulator: NFPA / National Electrical Code (NEC)

Every solar conductor must be sized to carry current safely under the worst-case conditions the installation will ever experience. NEC 690.8 defines how to do that calculation for PV source and output circuits — and the answer is almost never the same as a standard building wiring calculation.

The key difference: solar is treated as a continuous load, which means the 125% rule applies before any other derating. Then ambient temperature correction and conduit fill derating stack on top. Miss any one of these and the permit fails plan review.

SurgePV’s PV design software helps automate compliance documentation.

The 690.8 Calculation Framework

NEC 690.8 establishes a three-step minimum sizing requirement:

  1. Step 1: Start with the module rated Isc
  2. Step 2: Multiply by 1.25 (continuous load factor)
  3. Step 3: Apply standard NEC derating factors (temperature, conduit fill)

The conductor must carry the result of Step 3 under all conditions. This is the minimum required ampacity — you then select the smallest standard conductor from NEC Table 310.16 that meets or exceeds it.

Source Circuit vs. Output Circuit

A PV source circuit connects modules within a string to the combiner box or inverter input. A PV output circuit connects the combiner box output to the inverter. Source circuit current = single string Isc. Output circuit current = sum of all parallel string Isc values feeding that circuit.

Step 1: Identify Circuit Isc

Series Strings (Source Circuit)

Current does not add in series. A string of 20 modules in series has the same current as a single module:

Source circuit Isc = Module Isc (regardless of string length)

Parallel Strings (Output Circuit)

Current adds in parallel. If 4 strings (each with Isc = 10A) feed a combiner, the output circuit Isc is:

Output circuit Isc = N_strings × Module Isc = 4 × 10A = 40A

Step 2: Apply the 125% Continuous Load Factor

NEC 690.8(A) requires that the minimum conductor ampacity equal at least 125% of the maximum circuit current:

Minimum ampacity (before derating) = Isc × 1.25
Module Isc ×1.25 Minimum Ampacity
8.0 A 10.0 A
9.5 A 11.9 A
10.0 A 12.5 A
11.0 A 13.75 A
12.5 A 15.6 A
14.0 A 17.5 A

This is the floor. Everything after this point only makes the required ampacity larger.

Step 3A: Ambient Temperature Derating

Conductor ampacity decreases as ambient temperature increases. The NEC tables are based on a 30°C (86°F) reference temperature for THWN-2 conductors. In hotter environments, you must derate.

Rooftop Conduit: The 22°C Adder

NEC 310.15(B)(3)(c) requires adding 22°C (40°F) to the local design maximum ambient air temperature when conductors are in conduit installed on or above a rooftop and within 7 inches of the roof surface.

Example: Phoenix, AZ has a design maximum air temperature of 43°C (109°F). Conduit on roof: 43°C + 22°C = 65°C effective ambient

At 65°C, the temperature correction factor for 90°C-rated conductors (THWN-2) from NEC Table 310.15(B)(1)(1) is 0.58.

Phoenix Example Is Not an Edge Case

In Phoenix, the rooftop conduit temperature correction factor of 0.58 means you need a conductor rated for nearly twice the current at table ampacity compared to what the conductor would need at standard conditions. A 10 AWG THWN-2 rated at 40A (table) is only allowed to carry 40A × 0.58 = 23.2A in a Phoenix rooftop conduit — before conduit fill derating.

Temperature Correction Factors for 90°C Conductors (NEC Table 310.15(B)(1)(1))

Effective Ambient Temperature Correction Factor
21–25°C (70–77°F) 1.04
26–30°C (78–86°F) 1.00
31–35°C (87–95°F) 0.96
36–40°C (97–104°F) 0.91
41–45°C (105–113°F) 0.87
46–50°C (113–122°F) 0.82
51–55°C (123–131°F) 0.76
56–60°C (132–140°F) 0.71
61–65°C (141–149°F) 0.65
66–70°C (150–158°F) 0.58
71–75°C (159–167°F) 0.50

Step 3B: Conduit Fill Derating

When more than 3 current-carrying conductors share a conduit, NEC Table 310.15(C)(1) requires derating:

Number of Conductors Derating Factor
1–3 1.00 (no derating)
4–6 0.80
7–9 0.70
10–20 0.50
21–30 0.45
31–40 0.40
41+ 0.35

Both positive and negative conductors count as current-carrying. A conduit carrying 3 source circuits has 6 current-carrying conductors (3 positive, 3 negative) → 0.80 derating factor.

Keep Conduit Runs Short and Separate

The single most effective way to manage ampacity derating is to limit source circuit conductors per conduit. Two conduits with 3 circuits each (factor: 1.00) always allows smaller conductors than one conduit with 6 circuits (factor: 0.80), because neither conduit requires conduit fill derating.

Complete Worked Example

Project: 8.64 kW residential, Dallas, TX Module: 360W, Isc = 9.58A, 90°C THWN-2 in conduit String configuration: 2 strings × 12 modules, both strings in same conduit Local maximum air temperature: 40°C (104°F), rooftop conduit

Step 1 — Source circuit Isc:

Isc = 9.58A (single string)

Step 2 — Apply 125% factor:

Minimum ampacity = 9.58 × 1.25 = 11.98A

Step 3A — Temperature correction:

Effective ambient = 40°C + 22°C (rooftop adder) = 62°C
Correction factor at 62°C for 90°C conductor = 0.65
Required ampacity after temp derating = 11.98 / 0.65 = 18.43A

Step 3B — Conduit fill:

Conductors in conduit = 4 (2 positive + 2 negative for 2 source circuits)
Derating factor = 0.80
Required ampacity after fill derating = 18.43 / 0.80 = 23.04A

Step 4 — Select wire size:

From NEC Table 310.16 (90°C column):

  • 12 AWG THWN-2: 30A → sufficient (23.04A required)
  • 10 AWG THWN-2: 40A → provides more margin

With terminal temperature limitations, if the inverter terminals are only rated for 75°C, use the 75°C ampacity column: 12 AWG = 25A. This still covers the 23.04A requirement.

Result: 12 AWG THWN-2 is the minimum for this installation’s source circuits.

Common 690.8 Mistakes

Mistake Consequence Fix
Skipping temperature derating for “mild climate” installations Undersized conductors that overheat — AHJ reject + fire risk Always calculate — even San Diego rooftops add 22°C
Forgetting the 22°C rooftop adder Underestimated conductor temperature Add 22°C when conduit is within 7 inches of roof surface
Counting only one conductor per circuit Underestimates fill, misses conduit derating Count both positive and negative conductors
Using 60°C terminal limitation for 75°C-rated equipment Undersizes conductor Check inverter terminal temperature rating from spec sheet
Using wire ampacity from Table 310.17 (free air) instead of 310.16 (conduit) Overstates allowable ampacity for conduit installations Confirm wiring method before selecting table

Documentation for Permit Packages

AHJ plan reviewers checking 690.8 compliance look for:

  • Source circuit Isc clearly labeled on one-line diagram
  • 125% calculation shown explicitly
  • Ambient temperature documented with source (ASHRAE or local weather data)
  • 22°C rooftop adder applied (if applicable) with rooftop conduit noted
  • Conductor fill count with total current-carrying conductors per conduit
  • Final required ampacity and selected wire size
  • Wire size consistent between calculation, one-line diagram, and wire schedule

Automate NEC 690.8 Conductor Sizing

SurgePV calculates source and output circuit ampacity automatically — 125% factor, temperature derating, and conduit fill — and exports the full calculation table in your AHJ-ready permit package.

Try It Free

No commitment required · 20 minutes · Live project walkthrough

Frequently Asked Questions

What does NEC 690.8 require for conductor sizing?

Conductors in PV source and output circuits must be rated at a minimum of 125% of the module rated short-circuit current (Isc), then derated for ambient temperature and conduit fill per standard NEC ampacity tables.

Why 125% and not 100% of Isc?

Solar PV is classified as a continuous load — it can output near-maximum current for 3 or more hours. The NEC requires continuous loads to be served by conductors (and overcurrent devices) sized at 125% of the actual load.

What’s the biggest factor affecting conductor size on rooftop installations?

Ambient temperature derating, particularly the mandatory 22°C adder for conduit within 7 inches of a rooftop surface. This single factor can reduce allowable conductor ampacity by 30–40% and force upsizing from 12 AWG to 10 AWG or larger.

About the Contributors

Author
Rainer Neumann
Rainer Neumann

Editorial contributor · SurgePV

Rainer Neumann is credited as an editorial contributor on SurgePV content. This profile does not assert engineering credentials, project totals, software-testing experience, education, speaking engagements, or media citations because independent verification evidence is not retained in the publication record.

Editor
Keyur Rakholiya
Keyur Rakholiya

CEO & Co-Founder · SurgePV

Keyur Rakholiya is identified by SurgePV as its CEO and a company co-founder. His SurgePV author page lists only role information that can be tied to the public profile below; credentials, project totals, testing claims, media appearances, and speaking engagements are not asserted without retained evidence.

NEC 690.8conductor sizingampacitysolar permitsUSA

Solar Compliance Updates in Your Inbox

Join 2,000+ solar professionals. Regulatory changes, code updates, and design tips — weekly.

No spam · Unsubscribe anytime

Choose which optional technologies SurgePV may use. Essential storage remains active for security and requested features.