Answer
A modeled 50 kW solar plus 100 kWh battery system cuts a UK warehouse peak from 142 kW to 75 kW, a 47% reduction. Under the example assumptions it costs £95,000, saves £15,900 in year one and pays back in about six years. These are illustrative modeled figures, not a measured project.
Last updated: November 2026
Peak demand charges can make up a meaningful slice of a UK commercial electricity bill. They are fees linked to the highest power a site draws from the grid, so a warehouse that spikes to 150 kW for half an hour can pay for that spike all year. Peak shaving attacks that cost by using solar and a battery to cover the spike instead of the grid.
This guide walks through a modeled design example: a 50 kW solar PV plus 100 kWh battery storage system for a warehouse in the East Midlands. The site, load data, costs and results are illustrative assumptions built for this guide. They are not a measured installation, and no customer data is behind them. Use the structure and the arithmetic as a template, then swap in your own bills and load data.
Related reading: battery solar system design in the UK and adding battery storage services to a solar company. For UK grid and certification rules, see the MCS vs non-MCS comparison.
TL;DR: 50 kW + 100 kWh Peak Shaving Design Example
Modeled system: 50 kW solar plus 100 kWh LFP battery at a UK commercial warehouse. Assumed cost: £95,000 all-in. Modeled first-year savings: £15,900 (36% of the £43,800 baseline bill). Peak demand falls from 142 kW to 75 kW (47%). Simple payback: 6.0 years, or about 7.4 years with a Year-12 battery replacement added. Design lesson: match battery discharge timing to the site’s real peak window, not a generic forecast.
Model your own peak-shaving numbers
Swap this example’s assumptions for your site’s load data and tariff in the generation and financial tool, and see payback before you quote.
Book a DemoChecking cost first? See the SurgePV pricing page · 20 minutes · Live project walkthrough
In this design example:
- Site profile and load analysis: why this site was a strong candidate
- System design decisions: panel selection, inverter sizing, battery configuration
- Financial analysis: full cost breakdown, savings calculation, and sensitivity
- Battery sizing and control strategy: how the system decides when to charge and discharge
- Installation timeline: from survey to commissioning
- Modeled first-year performance: generation, consumption, and peak reduction
- Design risks and how to handle them
- UK regulatory framework: MCS, DNO, grid codes, and tax treatment
- Design lessons for future projects
- Three modeled size variants
- FAQ
Project Overview: The Site and the Problem
The modeled site is a 12,000 sq ft commercial warehouse and distribution facility in the East Midlands. The building houses a small manufacturing operation, packing lines, and office space. The site operates Monday to Friday, 07:00–18:00, with reduced weekend activity.
Site Characteristics
| Parameter | Value |
|---|---|
| Building type | Warehouse / light industrial |
| Floor area | 12,000 sq ft (1,115 m²) |
| Roof type | Steel portal frame, pitched south-facing |
| Available roof area | ~850 m² (unshaded) |
| Grid connection | Three-phase, 200 A supply |
| Annual electricity consumption | 118,000 kWh |
| Baseline annual electricity cost | £43,800 |
| Operating hours | 07:00–18:00 weekdays, limited weekends |
| Staff count | 28 full-time |
Before finalising any layout, run a shadow analysis to catch shading problems early.
The Electricity Bill Breakdown
The example assumes a baseline annual electricity bill of £43,800 before the solar + storage system. The split below is illustrative. Your own bill will use different rates and labels.
| Charge Component | Annual Cost | Share of Total |
|---|---|---|
| Energy charges (118,000 kWh at £0.295/kWh) | £34,810 | 79.5% |
| DUoS capacity charge | £3,620 | 8.3% |
| TNUoS demand-based charge | £2,840 | 6.5% |
| Standing charge and metering | £1,530 | 3.5% |
| Red-band unit rates and other levies | £1,000 | 2.3% |
| Total | £43,800 | 100% |
The example treats the DUoS capacity charge and the TNUoS charge as linked to peak demand. It assumes £25.50 per kW per year for DUoS capacity and £20.00 per kW per year for TNUoS, or £45.50 per kW of peak demand combined. These rates are assumptions for the arithmetic. How DUoS and TNUoS are actually charged depends on your tariff and network area, so read your own bill before copying them.
The assumed peak demand over the previous 12 months is 142 kW. At £45.50/kW, demand-based charges total £6,460 per year, about 15% of the bill.
Why This Site Suits Peak Shaving
Three factors make this site a good fit for a solar + storage peak-shaving system:
1. High daytime load with clear peaks. The assumed consumption profile shows a sharp morning ramp from 07:30 to 09:00 as machinery started up, a sustained midday plateau of 80–110 kW during full operation, and a second smaller peak around 14:00 when the packing line runs. The peaks are predictable and occur during daylight hours.
2. Unshaded, near-south-facing roof. The pitched steel roof faces 15° east of south with a 22° tilt, and the example assumes no shading from neighbouring buildings or trees. Check the exact figure for your roof in a shadow analysis and yield model or in PVGIS.
3. Three-phase grid connection with headroom. The existing 200 A three-phase supply is assumed to have capacity for a 50 kW solar system without a grid upgrade, which a pre-application enquiry to the DNO would test.
Pro Tip, Pre-Application DNO Enquiry
Before designing any commercial solar system of this size, submit a pre-application enquiry to your DNO. This informal check flags available grid capacity and early red flags. Ask your DNO about its fee and turnaround, which vary. The DNO can indicate whether the full application is likely to proceed smoothly or whether a grid impact study is needed. The G98 vs G99 guide explains which route applies. For this example site, the assumption is that the 200 A supply can accept 50 kW of generation without an upgrade.
Site and Load Profile Analysis
Accurate load profiling is the foundation of any peak-shaving design. The example assumes the installer fits a three-phase power meter with 15-minute logging for six weeks before finalising the design.
Daily Load Profile (Weekday Average, Assumed)
| Time Period | Average Power (kW) | Peak Seen (kW) | Activity |
|---|---|---|---|
| 00:00–06:00 | 4.2 | 8.5 | Security, refrigeration, standby |
| 06:00–07:00 | 12.5 | 22.0 | Pre-opening preparation |
| 07:00–08:00 | 68.0 | 95.0 | Morning startup ramp |
| 08:00–09:00 | 105.0 | 142.0 | Morning peak, full production |
| 09:00–12:00 | 92.0 | 118.0 | Steady operation |
| 12:00–13:00 | 78.0 | 95.0 | Lunch reduction |
| 13:00–15:00 | 98.0 | 128.0 | Afternoon peak, packing line |
| 15:00–17:00 | 85.0 | 105.0 | Winding down |
| 17:00–18:00 | 45.0 | 68.0 | Shutdown sequence |
| 18:00–24:00 | 6.0 | 12.0 | Night standby |
The data revealed two distinct peak windows: 08:00–09:00 (morning startup) and 13:00–15:00 (afternoon production). The assumed annual maximum of 142 kW occurs in the morning window on three separate days.
Seasonal Variation
Load profiles are assumed to vary modestly by season:
| Season | Average Weekday Peak (kW) | Annual Share of Consumption |
|---|---|---|
| Winter (Dec–Feb) | 138 | 28% |
| Spring (Mar–May) | 128 | 23% |
| Summer (Jun–Aug) | 118 | 22% |
| Autumn (Sep–Nov) | 135 | 27% |
Winter peaks are higher because of electric heating in the office area. Summer peaks are lower because the manufacturing floor needs less heating, though air conditioning adds a small afternoon load.
Solar Generation Profile vs. Load Profile
The critical design question was whether solar generation would coincide with peak demand. Solar output in the UK is strongest around midday, so the site’s afternoon peak at 13:00–15:00 lines up reasonably well with it. The morning peak at 08:00–09:00 did not, solar generation at 08:30 in midwinter is minimal.
This mismatch meant solar alone could not address the morning peak. Battery storage was essential to shift energy from the midday solar peak to the morning demand peak.
System Design
The example system is designed around a clear objective: reduce the site’s monthly peak demand below 80 kW, cutting demand-based charges by at least 40%.
Design Targets
| Target | Value | Rationale |
|---|---|---|
| Peak demand reduction | 45–55% | Cut DUoS + TNUoS charges materially |
| Annual bill reduction | 35–45% | Achieve sub-7-year payback |
| Solar self-consumption | >85% | Minimise low-value export |
| Battery daily cycles | 1.0–1.5 | Balance wear and savings |
| System design life | 25 years (PV), 15 years (battery) | Match commercial depreciation |
Solar Array Specification
| Component | Specification |
|---|---|
| Total capacity | 49.92 kWp |
| Module type | 156 × 320 W monocrystalline PERC |
| Module efficiency | About 20% (assumed) |
| Inverter | 50 kW three-phase hybrid inverter |
| Inverter efficiency | About 98% (assumed) |
| Array configuration | 12 strings of 13 modules |
| Tilt angle | 22° (roof-mounted, no tilt adjustment) |
| Azimuth | 195° (15° east of south) |
| Estimated annual generation | 47,800 kWh (modeled) |
| Specific yield | 958 kWh/kWp/year |
The 958 kWh/kWp/year specific yield is an assumption for the East Midlands at this orientation, not a measured value. Cross-check it for your own address and orientation in the European Commission’s PVGIS tool before using it in a quote.
Battery Storage Specification
| Component | Specification |
|---|---|
| Battery chemistry | Lithium iron phosphate (LFP) |
| Usable capacity | 100 kWh |
| Nominal capacity | 106 kWh (5% buffer for cell protection) |
| Maximum continuous discharge | 50 kW |
| Maximum continuous charge | 50 kW |
| Round-trip efficiency | 92% (assumed) |
| Warranty terms assumed | 10 years / 6,000 cycles at 80% retained capacity (check the datasheet of the model you choose) |
| Operating temperature | Per manufacturer datasheet |
| Enclosure | Outdoor cabinet, wall-mounted |
For a deeper comparison of chemistries, see LFP vs NMC batteries for solar storage.
The example specifies LFP over NMC for three reasons: it is commonly chosen for longer cycle life, it has better thermal stability for an industrial setting, and the model assumes a lower cost per kWh (£380/kWh for LFP). Cycle life and price vary by product, so use the figures on the datasheet and quote for the battery you actually specify.
Inverter and Control Architecture
The 50 kW hybrid inverter manages both solar DC input and battery charge/discharge. A dedicated energy management system (EMS) runs the peak-shaving control logic. The EMS receives:
- Real-time site power consumption from the grid meter
- Solar generation data from the inverter
- Battery state of charge from the battery management system
- Time-of-use tariff signals from the supplier’s API
In the example, the EMS decides every 30 seconds whether to charge the battery, discharge the battery, or pass solar generation directly to loads.
Single-Line Diagram Summary
Grid (200 A, 3-phase) ←→ Grid Meter ←→ Hybrid Inverter (50 kW)
↑
Solar Array (49.92 kWp)
↑
Battery (100 kWh LFP)
↑
Site Loads (0–142 kW)
Solar generation flows first to site loads. Excess solar charges the battery. When site demand exceeds solar generation, the battery discharges to cover the gap. If both solar and battery are insufficient, the grid supplies the remainder.
Key Design Decision, Why 100 kWh, Not 50 kWh or 150 kWh
A 50 kWh battery could discharge at 50 kW for one hour, enough to cover short peaks but not sustained morning demand. A 150 kWh battery would provide more buffer but adds about £28,000 to capex in this model, with diminishing returns on peak reduction. The 100 kWh size is selected because it can discharge at 50 kW for two hours, covering both the morning startup ramp and the afternoon packing peak on most days, while keeping simple payback near six years.
Financial Analysis
The modeled case rests on three savings streams: energy bought less often from the grid, lower demand-based charges, and a small export income. All figures below are assumptions for the example, in pounds sterling, before VAT and before tax.
Capital Cost Breakdown
| Cost Item | Amount (£) | Share |
|---|---|---|
| Solar modules (156 × 320 W) | £14,040 | 14.8% |
| Hybrid inverter (50 kW) | £6,800 | 7.2% |
| Battery system (100 kWh LFP) | £38,000 | 40.0% |
| Mounting system and rails | £4,200 | 4.4% |
| DC/AC cabling and switchgear | £5,600 | 5.9% |
| Installation labour (5 days, 3 electricians) | £8,500 | 8.9% |
| Scaffolding and access | £2,800 | 2.9% |
| DNO application and grid connection | £1,200 | 1.3% |
| Monitoring and EMS | £2,400 | 2.5% |
| Project management and design | £3,200 | 3.4% |
| Testing, commissioning, MCS paperwork | £2,260 | 2.4% |
| Contingency and sundries | £6,000 | 6.3% |
| Total project cost | £95,000 | 100% |
The battery is 40% of project cost in this model. That is plausible when storage is sized for peak shaving rather than only for solar self-consumption, but your own quotes decide the real split.
First-Year Savings Breakdown
| Savings Category | Modeled Annual Savings (£) | Share |
|---|---|---|
| Energy savings (solar used on site, net of battery losses) | £11,960 | 75.2% |
| Peak demand charge reduction (DUoS capacity + TNUoS) | £3,100 | 19.5% |
| Red-band unit rate and levy savings | £500 | 3.1% |
| SEG export income (surplus only) | £340 | 2.1% |
| Total first-year savings | £15,900 | 100% |
£15,900 is 36% of the £43,800 baseline bill.
- Energy savings£11,960
- Peak demand charges£3,100
- Red-band and levies£500
- SEG export income£340
Source: SurgePV worked design example using the assumptions in this guide (illustrative, not a measured project), checked November 2026.
Energy Savings Detail
The array generates 47,800 kWh in its first modeled year. Of this:
- 41,200 kWh is used on site (86.2%), including 8,400 kWh that passes through the battery
- 6,600 kWh is exported to the grid (13.8%)
At the blended energy rate of £0.295/kWh, 41,200 kWh is worth £12,154. The battery path loses about 8% of the 8,400 kWh it handles (about 670 kWh, or roughly £198), which leaves £11,960 of effective energy savings.
The 6,600 kWh exported earns £340 at an assumed Smart Export Guarantee (SEG) rate of £0.0515/kWh. SEG rates are set by each supplier and change, so this is a small, uncertain line. The design aims for self-consumption instead.
Peak Demand Charge Reduction
Peak shaving is the main design objective. The modeled demand-based charges move as follows:
| Metric | Before | After | Change |
|---|---|---|---|
| Annual maximum peak demand | 142 kW | 75 kW | -47% |
| Annual DUoS capacity charge | £3,620 | £1,860 | -49% |
| Annual TNUoS charge | £2,840 | £1,500 | -47% |
| Total demand-based charges | £6,460 | £3,360 | -48% |
| Annual demand charge savings | £3,100 |
Demand charges are only about a fifth of the total savings here. That surprises people who expect peak shaving to carry the whole case. In this model, most of the money still comes from solar energy that the site would otherwise buy.
Payback and Return Metrics
| Metric | Value |
|---|---|
| Total project cost | £95,000 |
| First-year savings | £15,900 |
| Simple payback | 6.0 years |
| Payback with 3% annual savings growth | 5.6 years |
| Simple payback with £22,000 battery replacement added | 7.4 years |
| 15-year NPV (6% discount rate, flat savings, replacement in Year 12) | £48,500 |
| 15-year IRR (same assumptions) | 13.6% |
The 7.4-year figure is the more cautious one to quote. A battery warranty of about ten years means a replacement or major refresh is plausible before Year 15, and the £22,000 replacement cost is itself an assumption. The NPV and IRR use flat savings with no price growth, no degradation and no tax. Treat them as a rough screen, not a financing model. Read more about battery storage and payback modeling.
Sensitivity Analysis
Simple payback (cost divided by first-year savings) when one input moves 20% and the rest stay at base values:
| Variable | Base Case | Input -20% | Input +20% | Payback at -20% / +20% |
|---|---|---|---|---|
| Electricity price | £0.295/kWh | £0.236/kWh | £0.354/kWh | 7.0 yr / 5.2 yr |
| Peak demand charge | £45.50/kW/yr | £36.40/kW/yr | £54.60/kW/yr | 6.2 yr / 5.8 yr |
| Solar generation | 47,800 kWh | 38,240 kWh | 57,360 kWh | 7.0 yr / 5.2 yr |
| Upfront cost | £95,000 | £76,000 | £114,000 | 4.8 yr / 7.2 yr |
| Battery replacement (payback incl. replacement) | £22,000 | £17,600 | £26,400 | 7.1 yr / 7.6 yr |
Even if electricity prices and demand charges both fall 20% together, simple payback in this model is about 7.4 years. The example is most sensitive to upfront cost and to the energy price, not to the demand charge.
Key Takeaway: Energy Savings Carry the Case
In this model, 75% of first-year savings come from solar energy used on site and 20% from lower demand charges. Energy savings alone (£11,960 plus £340 SEG) would stretch simple payback to about 7.7 years, against 6.0 years with demand charges. Model both, and check your own tariff to see how demand is billed.
Test these payback numbers on your own roof
Enter your tariff, battery size and load data to see how far your payback moves from this example. The generation and financial tool handles the financial model.
See a Project WalkthroughChecking cost first? See the SurgePV pricing page · 20 minutes · Walkthrough on a project of your choice
Battery Sizing and Control Strategy
The battery control strategy is what separates a peak-shaving system from a simple solar self-consumption setup. The EMS must predict when peaks will occur and ensure the battery has enough charge to cover them.
Control Logic
The example EMS uses a three-mode control strategy:
Mode 1: Solar self-consumption (default, 09:00–16:00)
- Solar generation feeds site loads directly
- Excess solar charges the battery
- Battery only discharges if site demand exceeds solar generation
- Target: maintain battery SOC at 60–80% by 16:00
Mode 2: Peak shaving (active, 07:00–09:00 and 13:00–15:00)
- Battery discharges at up to 50 kW to limit grid import
- Target: keep grid import below 80 kW
- If forecast peak exceeds 100 kW, pre-charge battery overnight from grid at off-peak rates
Mode 3: Off-peak charging (22:00–06:00, conditional)
- Only activates if the next day’s forecast peak exceeds battery capacity
- Charges battery at off-peak rate (£0.15/kWh) to 80% SOC
- Cost: £6.00 for 40 kWh charge. Benefit: avoids £45.50/kW of demand charges on the next peak
Forecasting Method
The EMS uses a simple but effective forecasting approach:
- Historical average: The system maintains a rolling 30-day average load profile by day of week and hour
- Weather adjustment: Solar generation forecast from the Met Office API adjusts expected solar contribution
- Event detection: If the current day’s load is tracking 15% above the 30-day average, the EMS raises the peak forecast and pre-conditions the battery
This approach does not require machine learning or complex modeling. It works because commercial load profiles are highly predictable, a warehouse operates on a weekly rhythm that repeats with minor variation.
Battery State of Charge Profile (Modeled Winter Weekday)
| Time | SOC | Activity |
|---|---|---|
| 06:00 | 45% | Overnight standby, minor discharge for security loads |
| 07:00 | 42% | Peak window opens (battery was pre-charged overnight if forecast peak was high) |
| 08:00 | 75% | Peak shaving active, discharging at 40 kW |
| 09:00 | 55% | Morning peak passed, solar begins contributing |
| 12:00 | 70% | Solar charging battery during lunch lull |
| 13:30 | 85% | Battery full, excess solar exported |
| 14:00 | 70% | Afternoon peak, discharging at 35 kW |
| 16:00 | 50% | Production winding down, solar still charging |
| 18:00 | 60% | Site closes, battery holds reserve |
| 22:00 | 55% | Decision point: charge overnight or not? |
Depth of Discharge and Cycle Life
The model assumes the battery runs 1.2 full cycles per operating day, about 320 equivalent full cycles a year. The average depth of discharge is 65% (charging to 85%, discharging to 20%), which is gentler on cells than 100% cycling. Both numbers are design assumptions that your EMS and battery warranty terms would need to support.
| Parameter | Value |
|---|---|
| Average daily cycles (operating days) | 1.2 |
| Average depth of discharge | 65% |
| Equivalent full cycles per year | 320 |
| Years to 6,000 cycles (assumed warranty limit) | 18.8 |
| Planning life for the model | 12 years, then replacement |
Calendar life, not cycle count, is the likelier limit. Batteries age even when idle, so the model carries a £22,000 replacement allowance in Year 12 instead of assuming the cycle count alone sets the life. Check the warranty wording of any battery you specify. See how battery degradation modeling approaches this.
Installation Timeline
A project of this size can plausibly run about 18 weeks from enquiry to handover. The timeline below is an assumed schedule, not a record of a real job. DNO review times in particular vary by network and queue, so ask your DNO.
| Week | Activity | Duration |
|---|---|---|
| 1 | Initial site survey and energy bill review | 2 days |
| 2 | Load monitoring equipment installed | 1 day |
| 2–7 | Six weeks of load data collection | 6 weeks |
| 8 | System design finalised, quote accepted | 3 days |
| 9 | DNO grid connection application submitted | 1 day |
| 9–11 | DNO technical review (assumed) | 3 weeks |
| 12 | DNO approval received with connection offer | n/a |
| 13 | Equipment ordered, scaffolding erected | 1 week |
| 14–15 | Solar installation and DC cabling | 5 days |
| 15 | Battery and inverter installation | 2 days |
| 16 | AC connection, testing, commissioning | 3 days |
| 17 | MCS certification and documentation | 3 days |
| 18 | Handover and operator training | 1 day |
Assumed total: 18 weeks from enquiry to handover.
DNO Application Detail
A grid connection application for a system like this typically needs documents along these lines. The DNO’s own form and guidance decide the final list.
- Single-line diagram
- Site plan showing inverter and meter locations
- Inverter specification and grid-code compliance certificate
- Battery specification and charge/discharge profile
- Existing supply capacity confirmation
- Export limitation setting (50 kW maximum export in this example)
DNOs commonly ask about anti-islanding behaviour, meaning the system must not keep exporting during a grid outage. Have the inverter’s certificate ready. The UK compliance guides explain the G99 application process and battery storage compliance in more detail.
In this example the export limit is set to 50 kW, the inverter’s maximum output. In practice the battery absorbs most surplus solar, so exports should stay well below that.
Modeled First-Year Performance
This section shows what the example model predicts over a first year of operation. No metered data sits behind it. When you design a real system, replace these rows with your own load data and an hourly or half-hourly simulation.
Generation and Consumption
| Metric | Modeled Value |
|---|---|
| Total solar generation | 47,800 kWh |
| Solar used directly on site | 32,800 kWh |
| Solar to battery (then to loads) | 8,400 kWh |
| Solar exported to grid | 6,600 kWh |
| Self-consumption rate | 86.2% |
| Grid import (with system) | 76,800 kWh |
| Grid import (baseline) | 118,000 kWh |
| Grid import reduction | 34.9% |
Peak Demand Reduction
| Month | Baseline Peak (kW) | Modeled Peak with System (kW) | Reduction |
|---|---|---|---|
| April | 128 | 70 | 45% |
| May | 122 | 67 | 45% |
| June | 116 | 62 | 47% |
| July | 120 | 64 | 47% |
| August | 126 | 68 | 46% |
| September | 132 | 71 | 46% |
| October | 138 | 74 | 46% |
| November | 140 | 75 | 46% |
| December | 141 | 75 | 47% |
| January | 142 | 75 | 47% |
| February | 138 | 74 | 46% |
| March | 134 | 72 | 46% |
| Annual average | 131 | 71 | 46% |
The headline 47% compares the single highest peak of the year, 142 kW to 75 kW. The monthly average reduction is slightly lower at 46%. Both are modeled. Winter months are the hard ones, because morning peaks arrive before solar generation and the battery may not hold enough overnight charge to cover a full ramp.
Monthly Bill Comparison
| Month | Baseline Bill | Modeled Bill with System | Savings |
|---|---|---|---|
| April | £3,340 | £2,100 | £1,240 |
| May | £3,210 | £2,000 | £1,210 |
| June | £3,080 | £1,920 | £1,160 |
| July | £3,300 | £2,070 | £1,230 |
| August | £3,440 | £2,160 | £1,280 |
| September | £3,600 | £2,280 | £1,320 |
| October | £3,760 | £2,380 | £1,380 |
| November | £3,930 | £2,520 | £1,410 |
| December | £4,090 | £2,660 | £1,430 |
| January | £4,160 | £2,730 | £1,430 |
| February | £4,030 | £2,610 | £1,420 |
| March | £3,860 | £2,470 | £1,390 |
| Total | £43,800 | £27,900 | £15,900 |
The monthly split is a shape assumption: bills are higher in winter and savings follow. Your real profile will differ with tariff, weather and operating pattern.
System Availability Assumptions
| Metric | Planning Value |
|---|---|
| Solar array uptime | 99.7% |
| Battery availability | 99.2% |
| Inverter availability | 99.5% |
These are planning assumptions, not measured availability. Real uptime depends on the equipment, service contract and the grid. Plan for some downtime for firmware updates, battery communication faults and grid outages, and make sure the system restarts automatically after an outage.
Performance Ratio
The model assumes a performance ratio of 84.9%, built from the loss budget below. Treat the individual loss numbers as design assumptions, then replace them with your simulation output.
| Loss Category | Assumed Impact |
|---|---|
| Temperature derating | 6.2% |
| Soiling (not cleaned during year) | 4.8% |
| Inverter losses | 1.8% |
| Mismatch and cabling | 1.5% |
| Shading (minimal) | 0.8% |
| Total losses | 15.1% |
| Performance ratio | 84.9% |
Soiling is the loss owners can control most easily. In this model, one professional clean in mid-summer would recover roughly 3% of annual generation, worth about £350 a year, which is why the example schedules cleaning.
Pro Tip: Log Load for 8 to 12 Weeks
Fit a 15-minute logger before you size the battery and keep it on for at least 8 to 12 weeks. A short window can miss monthly events, like a Saturday stocktake that runs machinery and sets a new peak. One missed peak can set your demand charge for a whole billing period.
Design Risks and How to Handle Them
Five risks come up repeatedly on peak-shaving projects. The examples below are design scenarios with modeled numbers, not an incident log from a real site. Plan for each one at design stage.
Risk 1: Morning Peak Before Solar Generation
Problem: The highest peaks fall at 08:00–09:00, before meaningful solar generation. The battery alone must cover them, and 100 kWh may not be enough for the full ramp on high-demand days.
Mitigation: Configure the EMS to pre-charge the battery from the grid overnight when the forecast next-day peak is high. In the model, a pre-charge of 40 kWh at £0.15/kWh costs £6.00, far less than the demand charge it can avoid at £45.50 per kW of peak reduced. The model assumes pre-charging runs on about 47 days a year (13% of operating days).
Risk 2: Battery Thermal Management in Winter
Problem: A battery enclosure on a north-facing wall sees cold winter temperatures. Internal heating draws power and can trim usable discharge capacity.
Mitigation: Add insulated cladding or choose a sheltered, south-facing position. Check the operating temperature range and heating load on the battery datasheet before deciding where to mount it.
Risk 3: Export Limit Ambiguity
Problem: A connection offer can state an export limit without being clear whether it applies to solar output only or to net export at the connection point. A battery charging from solar and a sudden load drop can briefly push net export above the limit.
Mitigation: Ask the DNO in writing how the limit is measured, and configure the inverter’s export limitation to monitor the grid connection point. Check whether a firmware update is needed.
Risk 4: Staff Behaviour
Problem: If staff assume “solar will cover it” and start high-power equipment at midday, they can raise the peak. Solar is already committed to base loads and battery charging.
Mitigation: Brief the team on how the system works and put a simple dashboard in a visible spot showing solar output, battery state of charge and grid import. Staff can then see when the site is importing heavily and stagger equipment starts.
Risk 5: SEG Tariff Changes
Problem: SEG rates are set by each supplier and can change. A tariff of £0.0515/kWh could fall to £0.0380/kWh, cutting a £340 line to about £250.
Mitigation: Review SEG rates yearly and avoid locking into one supplier for longer than needed. Because the design aims for self-consumption, this risk is small in absolute terms.
UK Regulatory Framework
A commercial solar + storage system in the UK touches several rule sets: grid connection, certification, planning, tax and export payments. This section summarises the topics and points to primary sources. Rules change, so verify each one with the body that owns it.
MCS Certification
MCS is the Microgeneration Certification Scheme, a quality scheme for small-scale renewable installations. Some routes to export payments depend on installer and product certification. Ofgem describes the Smart Export Guarantee for solar PV up to 5 MW on its SEG overview page. Ask your supplier what certification it requires for your system size before you commit. The MCS vs non-MCS comparison and the MCS certification guide cover the practical differences.
In this example, the model allows about £800 for certification fees and paperwork, within the £2,260 testing and commissioning line.
DNO Approval and Grid Connection
Grid-connected generation needs the local DNO’s permission. The application route depends on the system’s capacity, and larger systems need more documentation. The G98 vs G99 guide explains the thresholds and the notification steps, so check it rather than relying on a rule of thumb.
The document set usually includes:
| Document | Purpose |
|---|---|
| Application form | Standard DNO form with site and system details |
| Single-line diagram | Shows all electrical components and protection |
| Site layout plan | Locations of inverter, meter, isolation points |
| Inverter compliance certificate | Manufacturer’s test evidence |
| Battery charge/discharge profile | Shows maximum import and export power |
| Existing supply details | Supply capacity, fuse rating, meter type |
Limiting export to the inverter’s 50 kW rating, as the example does, can keep the technical review simpler. The DNO decides whether a grid impact study is needed.
Building Regulations and Planning
Rooftop solar on commercial buildings can fall under permitted development in England, but the conditions differ from the domestic rules and depend on the building. Check with the local planning authority and read the permitted development guide for the conditions. Use a competent registered electrical contractor and make sure the electrical work is certified.
Tax Treatment
GOV.UK states that the Annual Investment Allowance (AIA) amount is £1 million, covering most plant and machinery up to that amount. See the GOV.UK Annual Investment Allowance page. Whether the solar array and the battery both qualify depends on how your accountant classifies them, so ask before you rely on it.
The arithmetic below assumes the full £95,000 qualifies and the business pays tax at 25%. It ignores the tax due on the savings themselves, so it is a simplified screen.
| Tax Parameter | Value |
|---|---|
| AIA amount per GOV.UK | £1,000,000 |
| Example project cost | £95,000 |
| Assumed claimable amount | £95,000 |
| Assumed tax rate | 25% |
| Tax saving in Year 1 | £23,750 |
| Effective net cost after tax relief | £71,250 |
| Simple payback on net cost | 4.5 years |
On these assumptions, tax relief shortens simple payback from 6.0 years to about 4.5 years. It can move payback a lot, which is why the accountant conversation belongs early in the project.
Smart Export Guarantee (SEG)
The SEG replaced the feed-in tariff for new small-scale generators. Suppliers set their own export rates, and rates change, so compare offers using the supplier’s own published tariffs. The SEG guide explains how the scheme works.
In this example, 6,600 kWh of export at an assumed £0.0515/kWh gives £340, about 2% of savings. The system is designed for self-consumption, not export.
Design Lessons
Six lessons follow from the modeled example. Each one is a design practice, not a finding from a measured site.
Lesson 1: Load Monitoring Duration Matters
Six weeks of data captures the weekly rhythm but can miss a monthly event, such as a Saturday stocktake that runs machinery and creates a 165 kW peak. A 12-week window is more likely to catch it.
Recommendation: Monitor for at least 8 to 12 weeks to capture monthly and seasonal variation.
Lesson 2: Battery Pre-Charging Helps With Morning Peaks
Without overnight pre-charging, a battery of this size may not cover a morning peak on a high-demand day. The model assumes about £282 a year of pre-charge electricity (47 nights at £6.00) against roughly £1,840 of demand-related cost avoided, a 6.5 to 1 ratio. That ratio is an assumption, so test it against your own tariff.
Recommendation: Any site with morning peaks before solar output starts should check whether the EMS can pre-charge from the grid.
Lesson 3: Staff Engagement Can Add to the Result
A visible real-time dashboard and a short briefing can help staff avoid stacking heavy loads. The example treats an extra 8 kW of peak reduction from this as upside, worth about £360 a year at £45.50/kW, and does not include it in the headline numbers.
Recommendation: Install a dashboard and brief staff. The cost is small.
Lesson 4: Panel Cleaning Can Be Worth More Than Expected
The example assumes a 4.8% soiling loss. Industrial areas tend to collect more dust and particulates than residential ones, but the real figure depends on the site. A single mid-summer clean recovers about £350 a year in the model.
Recommendation: Budget for at least one professional clean per year and compare quotes against the generation you expect to recover.
Lesson 5: SEG Supplier Choice Matters
A fall in a SEG rate is small in absolute terms here, but it shows that export income is not guaranteed. Suppliers compete on tariff and set their own terms.
Recommendation: Review SEG rates annually. Read each supplier’s published tariff terms and compare them side by side.
Lesson 6: Battery Enclosure Location Affects Performance
A north-facing wall can leave a battery cold in winter. Heating then consumes energy and can trim usable capacity.
Recommendation: Mount battery enclosures in sheltered locations where possible. If a cold wall is the only option, specify extra insulation and check the datasheet’s temperature range.
Three Modeled Size Variants
The three variants below scale the same assumptions up and down. They are illustrative design variants, not measured projects, and the locations are labels for typical load types. Use them to see how size and load type move the arithmetic.
Variant 1: Distribution Warehouse, 30 kW + 60 kWh
| Parameter | Value |
|---|---|
| Example location | West Midlands |
| Building type | Distribution warehouse (8,500 sq ft) |
| System size | 30 kW solar + 60 kWh LFP battery |
| Total cost | £62,000 |
| Annual consumption (baseline) | 78,000 kWh |
| Annual bill (baseline) | £29,200 |
| Peak demand (baseline) | 98 kW |
| Peak demand (modeled) | 47 kW |
| Peak reduction | 52% |
| Annual savings | £10,200 |
| Bill reduction | 35% |
| Simple payback | 6.1 years |
A smaller site has a lower absolute peak, so a small battery can cover a larger share of it. That is why the percentage reduction looks high.
Variant 2: Manufacturing Facility, 75 kW + 150 kWh
| Parameter | Value |
|---|---|
| Example location | South West |
| Building type | Precision manufacturing (18,000 sq ft) |
| System size | 75 kW solar + 150 kWh LFP battery |
| Total cost | £128,000 |
| Annual consumption (baseline) | 186,000 kWh |
| Annual bill (baseline) | £68,400 |
| Peak demand (baseline) | 210 kW |
| Peak demand (modeled) | 124 kW |
| Peak reduction | 41% |
| Annual savings | £24,900 |
| Bill reduction | 36% |
| Simple payback | 5.1 years |
Machines that cause rapid demand spikes push the EMS toward faster control loops, for example a few seconds instead of 30 seconds. The 150 kWh battery covers 2.5 hours at 50 kW discharge in this variant.
Variant 3: Cold Storage Facility, 100 kW + 200 kWh
| Parameter | Value |
|---|---|
| Example location | North West |
| Building type | Cold storage warehouse (25,000 sq ft) |
| System size | 100 kW solar + 200 kWh LFP battery |
| Total cost | £168,000 |
| Annual consumption (baseline) | 245,000 kWh |
| Annual bill (baseline) | £89,600 |
| Peak demand (baseline) | 285 kW |
| Peak demand (modeled) | 128 kW |
| Peak reduction | 55% |
| Annual savings | £31,700 |
| Bill reduction | 35% |
| Simple payback | 5.3 years |
Refrigeration compressors create a steady baseload with periodic start-up surges. A battery can cover both peak shaving and some load shifting, such as pre-cooling during solar hours. See solar design for cold storage for the design side.
Comparison Summary
| Metric | 30 kW Variant | 50 kW Example | 75 kW Variant | 100 kW Variant |
|---|---|---|---|---|
| Cost per kW of solar (including battery) | £2,067 | £1,900 | £1,707 | £1,680 |
| Peak reduction | 52% | 47% | 41% | 55% |
| Bill reduction | 35% | 36% | 36% | 35% |
| Simple payback (years) | 6.1 | 6.0 | 5.1 | 5.3 |
- 30 kW + 60 kWh6.1 yrs
- 50 kW + 100 kWh (main example)6 yrs
- 75 kW + 150 kWh5.1 yrs
- 100 kW + 200 kWh5.3 yrs
Source: SurgePV worked design example using this guide's assumptions (illustrative, not measured projects), checked November 2026.
Cost per kW of solar falls as size rises in this model, but payback does not fall in a straight line. Load shape matters more than size. Treat all four columns as a way to see which inputs move the result, and rebuild them from your own quotes and bills.
Conclusion
This modeled 50 kW solar + 100 kWh battery example shows how peak shaving can work for a UK commercial site with demand-linked charges, and how the arithmetic is built. The key modeled numbers:
- £95,000 assumed total project cost
- £15,900 modeled first-year savings (36% of the baseline bill)
- 47% peak demand reduction (142 kW to 75 kW)
- 6.0 years simple payback, or 7.4 years with a Year-12 battery replacement added
- 13.6% 15-year IRR on flat savings (a rough screen)
The example holds together because the design starts from load data, the battery control strategy matches the site’s peak windows, and the tax and export assumptions are stated openly. None of these figures is a measured result.
Three actions for a site owner considering solar + storage:
-
Monitor your load for at least 8 weeks before designing. Size the system to real peaks, not estimates. A 15-minute logger is a small cost next to a wrongly sized battery.
-
Model demand charges explicitly. In this example, energy savings alone give a simple payback of about 7.7 years, against 6.0 years once demand-based charges and levies are included. Check how your own tariff bills demand before you copy this split.
-
Ask your accountant about capital allowances before committing. In this example, relief on the full cost cuts payback to about 4.5 years. Whether your system qualifies is a question for your accountant.
For solar installers and EPCs, peak shaving is a specialist service: load profiling, battery control strategy and DNO negotiation raise the barrier to entry. The four variants here show bill reductions in a 35% to 36% band, but the real range depends on the site.
For the wider UK and European context, see European solar incentives, solar energy policies in Europe and European solar tax credits. To build quotes with battery and tariff inputs, look at SurgePV’s solar design platform or generate customer-ready quotes with solar proposal software.
Frequently Asked Questions
What is peak shaving in commercial solar?
Peak shaving uses on-site generation or battery storage to cut the highest power a site draws from the grid. Many UK commercial tariffs include charges linked to peak demand, so a lower peak reduces those charges. Check your own bill to see which charges are demand-based.
How much does a 50 kW solar + battery system cost in the UK?
The modeled example in this guide totals £95,000 for 50 kW of solar and a 100 kWh LFP battery. That figure is built from the line items in the cost table, not taken from a market survey. Real quotes depend on the roof, battery chemistry, grid connection and installer, so collect several.
What is the payback period for commercial solar + storage in the UK?
The example works out to a simple payback of about 6.0 years, or about 7.4 years if a £22,000 Year-12 battery replacement is added to the cost. Both depend on the assumed £0.295/kWh energy rate, £45.50/kW demand charges and 86% self-consumption. Replace those assumptions with your own bill data.
What are DUoS and TNUoS charges in UK electricity bills?
DUoS (Distribution Use of System) and TNUoS (Transmission Network Use of System) are network charges that suppliers pass through on commercial electricity bills. DUoS covers local distribution networks and TNUoS covers the national transmission network. How each is charged depends on your tariff, so read your bill instead of assuming a per-kW rate.
Do I need MCS certification for a commercial solar system in the UK?
MCS (Microgeneration Certification Scheme) is the certification scheme for small-scale renewable installations, and Ofgem’s Smart Export Guarantee (SEG) covers solar PV up to 5 MW. Whether a given system needs MCS to earn SEG payments depends on its size and the supplier’s rules. Ask your supplier before you finalise the design.
What battery size do I need for peak shaving with a 50 kW solar system?
The example uses a 100 kWh battery with a 50 kW inverter, which can discharge at full power for two hours. The right size comes from your own load profile, not from a fixed ratio to the solar array. Log at least 8 to 12 weeks of 15-minute or half-hourly data before choosing.
Can I claim tax relief on commercial solar + storage in the UK?
The Annual Investment Allowance lets a business deduct up to £1 million of qualifying plant and machinery spend in a year, per GOV.UK. Whether a solar and battery installation qualifies in full depends on how it is classified, so ask your accountant. The example’s £23,750 saving assumes the full £95,000 qualifies at a 25% tax rate.
Where this fits
This article is part of SurgePV's Solar Incentives & Policy hub, which works through the topic from first principles to the decisions a project team actually has to make.


