Answer
Since 25 August 2026, the feed-in tariff approved by PUCSL (the Public Utilities Commission of Sri Lanka, which regulates the electricity industry) for a new rooftop solar system up to 10 kW is LKR 23.11/kWh. A feed-in tariff is the price paid for each kWh you send to the grid. The rate falls to LKR 19.15 for 10 to 40 kW, LKR 17.11 for 40 to 250 kW and LKR 15.81 above 250 kW. PUCSL’s 8 September 2026 clarification confirms that Net Metering, Net Accounting and Net Plus continue under a two-meter arrangement. Your return still depends on the scheme in your agreement, your own consumption and your project cost.
Sri Lanka solar tariff 2026: what changed
PUCSL’s new rooftop solar tariff for new systems up to 10 kW is LKR 23.11/kWh, effective 25 August 2026. PUCSL is the Public Utilities Commission of Sri Lanka, which regulates the electricity industry. LKR means Sri Lankan rupees.
The Commission made the decision on 21 August 2026. The rates apply until the next tariff revision. They follow a flat tariff of LKR 27.06/kWh for systems up to 500 kW. The new rates fall with system size. A feed-in tariff is the rate paid for each kWh you send to the grid.
| Capacity | Earlier flat tariff | August 2026 tariff, new rooftop PV |
|---|---|---|
| Up to 10 kW | LKR 27.06/kWh (up to 500 kW, from 1 July 2024) | LKR 23.11/kWh |
| Above 10 kW and up to 40 kW | LKR 27.06/kWh | LKR 19.15/kWh |
| Above 40 kW and up to 250 kW | LKR 27.06/kWh | LKR 17.11/kWh |
| Above 250 kW and up to 1,000 kW | LKR 27.06/kWh (up to 500 kW), LKR 23.18 above | LKR 15.81/kWh |
The earlier figures come from PUCSL’s rooftop connection-scheme overview. It lists a fixed flat tariff from 1 July 2024 for a 20-year agreement period. The new rates come from PUCSL’s Decision on Feed in Tariffs. The Annex 2 summary of approved feed-in tariffs lists them in one table.
Last updated: 29 October 2026. PUCSL changes tariffs from time to time. Check its Decisions and Orders page for later changes.
What to check before you choose a solar scheme
Start with your electricity account, proposed capacity, connection setup and application status. Ask the licensee to confirm the scheme available to the project. Also ask for the tariff and conditions it will put in the agreement. The licensee (the distribution licensee) is the company licensed to distribute power and connect you to the grid.
PUCSL’s Decisions and Orders page lists the August 2026 approved feed-in tariffs. It also lists a later clarification on implementation of Net Metering, Net Accounting and Net Plus. That clarification is dated 8 September 2026 and addressed to Electricity Distribution Lanka (Pvt) Ltd. It is a scanned letter. Its content is summarized below from the document itself.
For a new application or an extension, get written confirmation of the scheme and tariff. An existing customer should keep the signed agreement and any accepted amendment. A newly published tariff does not replace an existing contract on its own. The decision applies approved feed-in tariffs through the standard power purchase agreement (SPPA). That is the contract for selling power. It treats retrofits of existing prosumers separately.
Net Metering vs Net Accounting vs Net Plus: which one is better?
PUCSL’s rooftop connection-scheme overview describes the three arrangements. These differences explain why the financial model changes with the arrangement.
| Feature | Net Metering | Net Accounting | Net Plus |
|---|---|---|---|
| What exports earn | Credit for energy added to the grid; no payment for surplus beyond consumption | Surplus exported and paid | All solar output paid, not just the surplus |
| Payment basis | Credits banked and used against later consumption, up to ten years | Cabinet-approved feed-in tariff agreed at signing | Cabinet-approved methodology, agreed at signing |
| Meters | Same connection layout as Net Accounting | Same connection layout as Net Metering | Two meters, for imports and exports |
| Consumption billing | Net energy imported in months when consumption exceeds generation | Net imported energy billed | Bill paid at end-user tariff rates on all consumption, with exports reimbursed |
Which is better depends on the share of output you use yourself and the retail tariff you avoid. Net Metering gives value only through credits against later imports. Net Accounting and Net Plus pay at the feed-in tariff. So the tariff level and your retail tariff decide the result. Run each one against a metered (measured) load profile.
PUCSL’s overview also describes a fourth arrangement, Net Plus Plus. It is for rooftop systems larger than the customer’s contract demand. It classifies the rooftop system as a power plant and limits on-site use to auxiliary power. It also requires wiring separate from the premises’ internal wiring. It supports roof-rental and aggregator (a company that pools many small systems) models.
What PUCSL’s September 2026 clarification says
In its 8 September 2026 letter (reference PUC/EER/2026/EDL/31), PUCSL explains the National Tariff Policy’s requirement for a “Net Plus” basis. It says this requirement means separate measurement of electricity imported from and exported to the distribution network. The commercial settlement arrangements under Net Metering, Net Accounting or Net Plus stay in place.
PUCSL says its decision to continue Net Metering and Net Accounting under the two-meter arrangement fits the National Electricity Policy and the National Tariff Policy. It says the distribution company must implement it.
The August decision’s implementation conditions say the same. Distribution licensees shall continue to support Net Metering, Net Accounting and Net Plus. They do this through virtual offsetting, or another arrangement the Commission approves. This follows the prosumer’s selected scheme under a two-meter arrangement. The letter also notes something else. Cabinet approved financing on 13 July 2026 for a Rooftop Solar Aggregation and Virtual Net Metering Project.
Take the letter as the regulator’s position. Take the signed agreement as the contract. CEB’s business portal lists rooftop-solar applications and information. CEB is the Ceylon Electricity Board. The licensee’s current forms and instructions decide how your application proceeds. A contractor’s preliminary quote is not a grid-connection approval.
Published August 2026 rooftop tariff bands
The regulator’s Annex 2 lists these rates for new rooftop solar PV in the prosumer category:
| Capacity band in the published table | Feed-in tariff, LKR/kWh |
|---|---|
| Up to 10 kW | 23.11 |
| Above 10 kW and up to 40 kW | 19.15 |
| Above 40 kW and up to 250 kW | 17.11 |
| Above 250 kW and up to 1,000 kW | 15.81 |
| Above 1,000 kW | 15.81 |
Check the recognized capacity, scheme and contract date before you model revenue. The same annex lists two power-plant rates. Ground-mounted solar is LKR 18.00 non-escalable plus LKR 2.72 O&M. Floating solar is LKR 23.58 plus LKR 3.92. Non-escalable means the rate does not rise over time, and O&M means operation and maintenance. Those power-plant rows belong in a separate calculation from the rooftop table.
Storage payments for rooftop solar with a battery
The decision set battery-inclusive prosumer tariffs for projects above 250 kW only. PUCSL gives three reasons. Distribution control centers cannot see small battery systems. Large prosumers have the technical know-how and safety precautions. Batteries below 250 kW cost more because of import duty, which PUCSL says is under discussion. It will consider battery-inclusive tariffs below 250 kW in upcoming reviews.
| Capacity band | Applicant type | At the prioritized feed-in time, LKR/kWh | At other times, LKR/kWh |
|---|---|---|---|
| Above 250 kW and up to 1,000 kW | New rooftop PV and battery | 45.53 for the first 15 years | 15.81 |
| Above 250 kW and up to 1,000 kW | Existing rooftop prosumer adding a battery | 33.51 + R1/0.95 for the first 15 years | R1 |
| Above 1,000 kW | New rooftop PV and battery | 42.49 for the first 15 years | 15.81 |
| Above 1,000 kW | Existing rooftop prosumer adding a battery | 30.27 + R1/0.95 for the first 15 years | R1 |
R1 is the feed-in tariff from the existing agreement. The prioritized feed-in time is a four-hour window, set at 17:30 to 21:30 in this review. PUCSL may move it by up to three hours. The prioritized rate applies for the first 15 years. The standalone tariff applies for the rest of the agreement.
Exports under battery schemes are capped at 123 kWh per kW of contracted capacity in a 30-day billing cycle. PUCSL calculated the 250 to 1,000 kW battery rates assuming the Bonded Warehouse Scheme tax concession. It says it would revise them if the concession does not apply. A battery’s presence alone does not qualify a project for these rows. Get the operating conditions in the decision.
Payback example for 5 kW and 10 kW
PUCSL’s decision states the cost assumptions behind the tariff. For systems up to 10 kW it uses a capital cost of LKR 178,000 per kW with a grid-tied inverter. It uses an operating cost of 2% of capital cost a year and a plant factor of 17%. Plant factor is the share of full-power output a system makes over a year. This example applies those regulator assumptions to the tariff. It assumes every kWh is paid at the tariff, as under Net Plus. So it is not a household quote.
| Item | 5 kW | 10 kW |
|---|---|---|
| Capital cost (LKR 178,000 per kW) | LKR 890,000 | LKR 1,780,000 |
| First-year output at 17% plant factor | 7,446 kWh | 14,892 kWh |
| Revenue at LKR 23.11/kWh | LKR 172,077 | LKR 344,154 |
| Operating cost (2% of capital) | LKR 17,800 | LKR 35,600 |
| Net annual benefit | LKR 154,277 | LKR 308,554 |
| Simple payback | 5.8 years | 5.8 years |
Both sizes pay back in the same period because the regulator uses one cost per kW for both. Real payback moves with several things. These are your quote, inverter replacement (PUCSL includes one in year 11), degradation, tax treatment and how much output you use yourself instead of selling. Degradation is the slow loss of panel output over time. Under Net Metering and Net Accounting, the value of self-consumed energy depends on your retail tariff. This example does not use it.
Keep generation, imports and exports separate
Record modeled production and customer demand on a compatible time basis. Work out which generation is used on site, exported or otherwise treated under the actual metering setup. Then apply the correct contract terms to each flow.
For an illustrative calculation only, suppose 1,000 kWh is eligible for payment at an assumed contractual rate of LKR 23.11/kWh. Gross modeled payment would be LKR 23,110, before any applicable adjustments or charges. The figure is arithmetic on assumed inputs. It is not an actual monthly output or a customer’s net return.
A production estimate alone does not give bill savings. Imports may have tariff blocks or other billing conditions. A separate-generation scheme needs a different calculation from on-site consumption. Keep a copy of the tariff and contract used by the model.
Tax and import concessions need their own evidence
PUCSL’s decision refers to two concessions. One is import duty on batteries below 250 kW, which it says is under discussion for removal. The other is the Bonded Warehouse Scheme tax concession that its battery tariff for 250 to 1,000 kW assumes. Neither is a general rebate for rooftop solar.
Identify the exact current tax or customs rule. Also identify the qualifying goods, the applicant and the programme conditions. Do this before you count any concession as a project saving. Get the importer’s written classification. Also get a review of whether the concession applies. Business capital allowances, grants and borrowing terms are separate questions. Confirm who pays the tax, what spending is eligible and when the benefit comes.
Who regulates rooftop solar in Sri Lanka
| Body | Role |
|---|---|
| Public Utilities Commission of Sri Lanka (PUCSL) | Sets feed-in tariffs under Section 29(3) of the Sri Lanka Electricity Act No. 36 of 2024 and issues the implementation conditions |
| Distribution licensees (PUCSL’s September 2026 letter is addressed to Electricity Distribution Lanka (Pvt) Ltd; CEB’s business portal also lists rooftop applications) | Process applications, publish hosting capacity monthly and implement the tariffs and schemes |
| National System Operator (NSO) | Procures electricity from distributed generators through the distribution licensees, up to annual and cumulative capacity limits |
| Ministry of Energy | Sets national electricity and tariff policy; PUCSL has written to it about policy provisions it considers inconsistent with the Electricity Act |
Common mistakes with Sri Lankan rooftop solar
- Oversizing for export. Licensees must assess and publish the hosting capacity of their networks every month. Hosting capacity is how much solar a network can take. The National System Operator (NSO) buys from distributed generators only up to set annual and cumulative capacities. A larger array does not guarantee export.
- Ignoring curtailment. Rooftop and battery systems must follow any temporary export limit or curtailment instruction from the licensee or NSO. Curtailment means being told to cut your output. This keeps the system secure.
- Missing the 100 kW licence. Rooftop solar and rooftop-plus-battery systems of 100 kW and above will need a Generation Licence. This starts once the new Electricity (Applications for Licenses and Exemptions) Regulations are enacted.
- Assuming a battery adds an export tariff below 250 kW. Battery-inclusive tariffs in the August decision cover only systems above 250 kW.
- Applying an old description. An older webpage may describe schemes or tariffs that PUCSL has since revised.
A project requirements register
| Item | Evidence to retain |
|---|---|
| Scheme eligibility | Written licensee confirmation and current governing instruction |
| Connection | Application, capacity assessment and approval conditions |
| Contract | Signed agreement, tariff basis, period and amendments |
| Equipment | Exact model specifications and required documentation |
| Production | Weather, shading, equipment and loss assumptions |
| Customer load | Metered profile and bill assumptions |
| Tax treatment | Applicable instrument and project-specific review |
| Financial case | Cost quote, operating expenses, financing and scenario inputs |
Resolve major gaps before you promise a payback period. Compare a base case with clearly labeled what-if runs (sensitivities). Examples are lower eligible energy or higher operating costs.
Model your Sri Lanka rooftop payback at the 2026 tariff
Bring the confirmed scheme, tariff and your project inputs to a guided demo and see how SurgePV’s proposal workflow handles financial modeling and proposal output.
Book a DemoNo credit card is required for the demo.
The software models the inputs you enter. Check the current tariff and your scheme with the licensee before relying on the result.
Frequently asked questions
What is the new solar tariff in Sri Lanka in 2026?
PUCSL’s feed-in tariffs took effect on 25 August 2026. For new rooftop solar PV, the rate is LKR 23.11/kWh up to 10 kW. It is LKR 19.15 above 10 kW and up to 40 kW. It is LKR 17.11 above 40 kW and up to 250 kW, and LKR 15.81 above 250 kW. Apply a rate only after you confirm the scheme and agreement conditions for the project.
Which is better: Net Metering, Net Accounting or Net Plus?
It depends on how much of your output you use yourself. Net Metering credits your exports against later consumption. It pays nothing for surplus. Net Accounting pays for exported surplus at the agreed feed-in tariff. Net Plus pays for all generation and bills all consumption at end-user tariffs, using two meters. Model all three against your own load before you choose.
Can every new applicant choose Net Metering, Net Accounting or Net Plus?
PUCSL’s 8 September 2026 clarification says Net Metering, Net Accounting and Net Plus continue under a two-meter arrangement. Its August 2026 decision tells distribution licensees (the companies licensed to distribute power) to support these schemes. They follow the scheme the prosumer selected. A prosumer is a customer who both uses and generates power. Get the licensee’s written confirmation for your application.
Does a tariff table establish the project’s return?
No. The return also depends on who qualifies and how energy actually flows. It also depends on project cost, running costs, financing and any tax treatment you have checked.
Does Sri Lanka pay for a battery with rooftop solar?
Under PUCSL’s August 2026 decision, battery-inclusive prosumer tariffs apply only to systems above 250 kW. A new rooftop solar system with a battery above 250 kW and up to 1,000 kW gets LKR 45.53/kWh for the first 15 years. This applies at the prioritized feed-in time (17:30 to 21:30). After that it is LKR 15.81. PUCSL says it will consider tariffs for battery systems below 250 kW in upcoming reviews.
Sources
- PUCSL, Decision on Feed in Tariffs (decided 21 August 2026, effective 25 August 2026) and its Annex 2.
- PUCSL, Clarification on Implementation of Net Metering, Net Accounting and Net Plus Schemes, 8 September 2026.
- PUCSL, Rooftop solar PV connection schemes.
- CEB business portal.
The payback table applies the regulator’s own cost assumptions and the tariff, with a first-year output estimate. It is not a customer case study. It omits tax, financing and inverter replacement.
Where this fits
This article is part of SurgePV's Solar Incentives & Policy hub, which works through the topic from first principles to the decisions a project team actually has to make.


