Back to Blog
solar roi9 min read

P50 vs P90 Cost Estimates: How Lenders Use Each

P50 vs P90 cost estimates explained for solar projects: when to use each, how lenders apply P90 to debt and reserves, and how to avoid the P50 budget trap.

Akash Hirpara

Written by

Akash Hirpara

Co-Founder · SurgePV

Rainer Neumann

Edited by

Rainer Neumann

Editorial contributor · SurgePV

Published ·Updated

Answer

A P50 cost estimate has a 50% chance of being enough and is the median planning figure. A P90 estimate has a 90% chance of being enough, so it is higher and carries more contingency. Lenders commonly size debt and reserves on P90, and the gap between the two is the contingency.

Hypothetical example, not a real project: a 5 MW commercial rooftop project wins board approval on a $5.15 million budget. That number is the P50 estimate. Six months later the EPC contract comes in higher and the interconnection upgrade costs more than planned. The lender asks for a P90 view, and the project needs $5.8 million to close. The board is surprised. The finance team is not.

This is the P50 trap. A P50 cost estimate is the median: the number with a 50/50 chance of being enough. It is a useful planning figure, but it is not a safe budget for a financed project. Developers and EPCs who treat P50 as a funding ceiling invite overruns, strained covenants and missed returns.

Last updated: November 2026. SurgePV publishes this post and sells solar design software.

In this guide, you will learn:

  • What P50 and P90 mean for cost estimates, not just energy yield
  • How probabilistic cost estimates are built from base estimates and contingencies
  • Why lenders use P90 for debt sizing and contingency reserves
  • How P50/P90 applies to both CAPEX and revenue in solar finance
  • Common mistakes in using P50 and P90, and how to avoid them
  • A worked example for a commercial solar project

Model P50 and P90 on your own project?

Bring one project to a demo and see how SurgePV links energy yield scenarios to financial modeling in one workspace.

Book a Demo

Checking cost first? See the SurgePV pricing page · 20 minutes · Live project walkthrough

What P50 and P90 Mean for Cost Estimates

P50 and P90 come from probabilistic estimation. Instead of producing one deterministic number, the estimator models ranges of uncertainty and reads percentiles from the resulting distribution. The same logic applies to energy yield estimates, where P50 is median production and P90 is the conservative case. Our guide to P50 vs P90 energy yield covers that side in detail.

P50 cost estimate is the median. Half of simulated outcomes fall below it, and half fall above it. It represents the expected outcome if the project is repeated many times under the same conditions. For internal planning and investor presentations, P50 is the base case.

P90 cost estimate is the conservative percentile. In 90% of simulated outcomes, the final cost is at or below this number. Only 10% of outcomes are worse. P90 includes more contingency and is the figure typically used for funding approval, lender covenants, and board risk reporting.

The gap between P50 and P90 is not a fudge factor. It reflects real uncertainty: commodity price volatility, geotechnical conditions, permitting delays, labor availability, equipment lead times, and scope changes. The wider the gap, the more uncertainty the project carries.

Pro Tip

Treat P50 as the expected cost and P90 as the funding limit. If you only have one number in front of the board, make it P90. P50 is for internal target-setting, not for committed budgets.

How P50/P90 Cost Estimates Are Built

The standard method is Monte Carlo simulation. Each cost element is assigned a probability distribution, usually a triangular or beta distribution based on minimum, most likely, and maximum values. The model runs thousands of iterations and produces an S-curve of possible total costs.

The steps are:

  1. Break down the cost estimate into line items: modules, inverters, racking, labor, EPC management, interconnection, civil works, permitting, and contingency.
  2. Assign uncertainty ranges to each item. Modules may have a narrow range if prices are locked. Civil works may have a wide range if geotechnical data is limited.
  3. Run Monte Carlo simulation for 5,000 to 10,000 iterations, sampling from each distribution.
  4. Read the percentiles from the output curve. P50 is the median. P90 is the 90th percentile.
  5. Add escalation if the estimate is in nominal dollars for a future out-turn date.

For projects where full simulation is not practical, a simplified approach uses the normal distribution approximation:

P90 ≈ Mean + (1.28 × Standard Deviation)

The multiplier 1.28 corresponds to the 90th percentile of a standard normal distribution. If total cost uncertainty is 8%, the P90 cost is roughly 10.2% above the mean.

The Australian Government’s Department of Infrastructure, Transport, Regional Development, Communications and the Arts (DITRDCA) provides a worked example: a $100 million base estimate becomes a $115 million P50 project estimate and a $140 million P90 project estimate. After applying 2.5% escalation, the P50 out-turn cost is $124.33 million and the P90 out-turn cost is $151.36 million, according to the Commonwealth Cost Estimation Guidance.

The guidance sets rules for when probabilistic estimation is expected and when a deterministic approximation is acceptable. Read the current note for the dollar thresholds before you apply them to a project.

P50 vs P90 in Solar: CAPEX and Energy Yield

Solar projects face two distinct P50/P90 applications: cost and energy yield. Both matter to project finance, but they move in opposite directions.

CAPEX P50/P90 estimates the total cost to build the project. P90 is higher than P50 because it includes upside cost risk.

Energy yield P50/P90 estimates annual production. P90 is lower than P50 because it reflects downside production risk from weather variability, modeling uncertainty, and equipment performance.

A lender looks at both. In practice, lenders commonly test debt against a conservative case such as P90; the exact percentile is set in each loan agreement. Higher CAPEX P90 means more capital is needed. Lower energy yield P90 means less revenue is available to service debt. The combination determines whether the project is bankable.

Application P50 Meaning P90 Meaning Direction
CAPEX Median construction cost Conservative construction cost P90 higher than P50
Energy yield Median annual production Conservative annual production P90 lower than P50
Revenue Expected annual revenue Conservative annual revenue P90 lower than P50

This dual application is why solar financial models run separate scenarios. The equity investor usually focuses on P50 production and P50 cost to calculate expected IRR. The lender focuses on P90 production and P90 cost to calculate debt service coverage ratio (DSCR).

A solar design platform that models both energy yield uncertainty and project cost ranges in the same workspace makes this analysis far easier than passing spreadsheets between teams. For community-scale projects, the same principle applies: see how community solar design handles P50/P90 yield modeling for lender bankability.

Why Lenders Care More About P90 Than P50

Project finance is non-recourse or limited-recourse lending. The lender’s repayment depends on project cash flows, not the sponsor’s balance sheet. If costs overrun or production underperforms, the lender is exposed. A strong solar proposal makes this risk explicit by showing both P50 and P90 scenarios side by side.

P90 gives the lender a buffer. By sizing debt to P90 revenue and requiring contingency reserves based on P90 cost, the lender creates a margin of safety. The project can still service debt even if costs are high and the sun year is poor.

Key lender metrics tied to P90 include:

  • Debt service coverage ratio (DSCR): Typically calculated using P90 revenue divided by annual debt service. The minimum ratio is set in each loan agreement, so this guide does not quote a typical figure.
  • Debt sizing: The maximum loan amount is often set so that P90 revenue covers debt payments with the required DSCR.
  • Contingency release: Some lenders may hold contingency in reserve and release it only against demonstrated need.

A wide P50/P90 spread signals high uncertainty. That uncertainty translates directly into higher cost of capital, lower leverage, or additional sponsor equity. Tightening the spread with better data, firmer contracts, and on-site measurements improves bankability. PV shade analysis is one of the most effective ways to reduce yield uncertainty on complex sites.

Common Mistakes and How to Avoid Them

Mistake 1: Presenting P50 as the committed budget

A P50 estimate has a 50% chance of being exceeded. Using it as a fixed budget means the project is underfunded half the time. For financed projects, the committed budget should be P90 or include a separate contingency that bridges P50 to P90.

Mistake 2: Ignoring correlation between cost risks

Monte Carlo models often treat cost items as independent. In reality, risks correlate. A delay in permitting can increase labor costs, extend equipment storage, and push work into worse weather. Build correlation assumptions into the model or the P90 will be too optimistic.

Mistake 3: Confusing energy yield P90 with cost P90

New project finance analysts sometimes add the two together or treat them as interchangeable. They are separate distributions. Energy yield P90 affects revenue. Cost P90 affects CAPEX. Both flow into the same financial model, but they should not be mixed in the same calculation.

Mistake 4: Using outdated escalation assumptions

A base estimate in 2026 dollars is not the same as an out-turn cost in 2028 dollars. Escalation must be applied before reading P50 and P90 percentiles, or the funding request will fall short.

Mistake 5: Forgetting soft costs and owner costs

EPC contracts, legal fees, development costs, insurance, and financing fees are often excluded from early estimates. A P50 cost estimate that omits them is not really P50.

Practical Guidance: When to Use Which P-Value

Different stakeholders need different confidence levels.

Use P50 when:

  • Setting internal targets and expected-case IRR
  • Reporting to equity investors who understand probabilistic estimates
  • Comparing projects on an expected-return basis
  • Building management dashboards and KPIs

Use P90 when:

  • Submitting funding requests to lenders or government agencies
  • Setting board-approved project budgets
  • Calculating contingency reserves
  • Writing fixed-price EPC contracts with limited change-order flexibility
  • Reporting to risk-averse owners or public-sector clients

Some teams also report P75 or P80 as a middle ground. Use whichever percentile the lender or client names in writing.

For solar developers, the rule is simple: P50 is for the pitch deck, P90 is for the term sheet.

P50/P90 Across the Solar Project Lifecycle

The relevance of P50 and P90 changes as the project moves from early development to operation.

Development and pre-feasibility

At this stage, cost estimates are based on limited information. Geotechnical studies may not be complete, interconnection capacity is assumed, and equipment pricing is indicative. The P50/P90 gap is wide. P50 is useful for screening and go/no-go decisions. P90 is too uncertain to be a reliable budget, but it signals the funding range the sponsor should prepare for.

Final investment decision (FID)

By FID, major contracts are in negotiation and technical studies are complete. The P50/P90 gap narrows. This is when lenders commit and the board approves a P90 budget. Contingency is sized to bridge the gap between the expected cost and the conservative cost.

Construction

During construction, the focus shifts from probabilistic estimates to actual costs and contingency drawdown. A well-structured project releases P90 contingency only against demonstrated need. If the project finishes below P90, the remaining contingency returns to equity or reduces debt.

Operations

In operations, P50 and P90 apply to energy production and revenue, not cost. Actual production is compared to the P50 estimate to judge performance. Debt service is checked against P90 production to ensure coverage in poor weather years.

Stage P50 use P90 use What happens to the gap
Pre-feasibility Screening returns Funding range indicator Widest, because site data is thin
Development Expected budget Lender or board budget Narrows as studies and quotes arrive
FID Base-case IRR Committed budget and contingency Narrower, with major contracts in negotiation
Construction Target cost Contingency reserve cap Narrows as costs firm up
Operations Expected production Debt service floor Applies to yield, not cost

Contingency is the bridge between P50 and P90. It is not a slush fund for scope growth. It is a calculated reserve for identified risks that have not yet been priced precisely.

There are two common ways to set contingency:

Deterministic contingency

The estimator reviews each risk and assigns a specific dollar amount. For example, with made-up figures, geotechnical uncertainty might add $50,000 and interconnection upgrade risk might add $100,000. The sum becomes the contingency. This method is transparent but can underestimate combined risk if risks interact.

Probabilistic contingency

The Monte Carlo model calculates the contingency needed to reach a target percentile. If the P50 cost is $5.15 million and the P90 cost is $5.80 million, the probabilistic contingency to reach P90 is $650,000. This method captures the combined effect of multiple risks and correlations.

Whichever method you pick, document it and the assumptions behind each uncertainty range.

A common error is to set contingency as a flat percentage of the base estimate, such as 10%. This ignores the actual risk profile. A project with fixed-price equipment and a simple site needs less contingency than a project with custom civil works and uncertain permitting.

Communicating P50 and P90 to Non-Technical Stakeholders

Board members, homeowners, and procurement officers often interpret a single number as a guarantee. Probabilistic estimates require explanation.

Use plain language:

  • “The P50 cost of $5.15 million is our best estimate. There is a 50/50 chance the final cost will be higher or lower.”
  • “The P90 cost of $5.80 million is our conservative budget. We expect the final cost to come in at or below this number 90% of the time.”
  • “The $650,000 between P50 and P90 is contingency for risks we can identify but not yet price exactly.”

Avoid statistical jargon in customer-facing materials. Present a range instead of percentiles when possible. For example: “We expect the project to cost between $5.15 million and $5.80 million, with $5.15 million as the most likely outcome.”

For internal finance teams, show the S-curve or a table of percentiles. This makes the distribution visible and supports informed decisions about risk appetite.

Worked Example: 5 MW Commercial Solar Project

This is an illustrative example with made-up numbers, not market data. Consider a 5 MW commercial rooftop project in the southwestern United States.

Base estimate: $5,000,000

Cost uncertainty breakdown:

Cost Item Base Cost Uncertainty Range Risk Level
Modules $1,500,000 ±5% Low
Inverters $600,000 ±7% Low-Medium
Racking and BOS $900,000 ±10% Medium
Labor $800,000 ±12% Medium
Civil and structural $400,000 ±20% High
Interconnection $350,000 ±18% High
Permitting and soft costs $250,000 ±15% Medium
EPC management $200,000 ±10% Medium

Assume a Monte Carlo simulation returns these percentiles:

Percentile Total Cost vs Base
P10 $4,650,000 -7.0%
P50 $5,150,000 +3.0%
P75 $5,450,000 +9.0%
P90 $5,800,000 +16.0%
P99 $6,350,000 +27.0%

The P50 is $5.15 million. The P90 is $5.80 million. The $650,000 gap represents the contingency needed for a 90% confidence budget.

Now apply energy yield. The project models P50 production at 9,200 MWh/year and P90 production at 8,050 MWh/year, which is 12.5% below P50. At a power purchase agreement price of $0.08/kWh:

  • P50 revenue: $736,000/year
  • P90 revenue: $644,000/year

If annual debt service is $520,000:

  • DSCR at P50: 1.42x
  • DSCR at P90: 1.24x

Whether 1.24x is enough depends on the lender’s minimum ratio. If the project had used P50 cost and P50 revenue together, the apparent DSCR would be 1.42x and the project might have been over-leveraged. Using P90 for both sides of the ledger gives a more realistic view of financed risk.

Sensitivity check: What if the P90 cost rises to $6.0 million because of steel tariff uncertainty, while revenue stays at P90? The equity contribution must increase by $200,000, or the debt amount must fall. This is why lenders require sensitivity analysis alongside base-case P50/P90 numbers.

Illustrative example, not market data: total project cost by percentile, 5 MW rooftop (US$ million, made-up example from this post)
  • P10$4.65M
  • P50$5.15M
  • P75$5.45M
  • P90$5.8M
  • P99$6.35M

Source: worked example in this post (illustrative simulation output, not market data), checked November 2026.

Key Takeaway

A project can look attractive at P50 and still be risky at P90. The P90 view decides whether the project closes. In this example the P50 to P90 gap is $650,000, which is the contingency a 90% confidence budget needs.

Link yield uncertainty to project financials

SurgePV’s generation and financial tool connects energy yield assumptions to project financials, so you can run a conservative scenario next to the base case.

Book a Demo

Want the numbers first? Visit the SurgePV pricing page · No commitment required

How P50/P90 Cost Estimates Affect Project Returns

The choice of percentile changes the return profile. Equity investors care about expected returns, but they also care about downside cases. A project with a high P50 IRR but a thin P90 DSCR is riskier than one with a lower P50 IRR but a strong P90 DSCR.

Consider two illustrative 5 MW projects, with made-up numbers, that have the same P50 IRR of 12%:

Project P50 IRR P90 DSCR P90 Cost / P50 Cost Assessment
Project A 12% 1.15x 1.22 High risk; thin lender buffer
Project B 12% 1.30x 1.12 Lower risk; stronger lender buffer

Project B is more bankable because its P90 metrics are stronger, even though both projects have the same expected return. Lenders will offer better terms on Project B, which improves the equity IRR after financing.

This is why experienced developers do not optimize only for P50. They optimize for the spread between P50 and P90. Reducing uncertainty through better site data, fixed-price contracts and proven equipment is often more valuable than pushing the P50 return higher.

P50/P90 in Proposals and RFPs

When responding to a commercial RFP, be explicit about which percentile each number represents. A proposal that says “estimated cost: $5.15 million” without stating P50 or P90 creates confusion. The procurement committee may assume it is a fixed price, while the developer intended it as an expected value.

Best practice for proposals:

  • State the base estimate, P50 estimate, and P90 estimate separately
  • Explain the contingency methodology
  • Show how P90 cost affects financing and DSCR
  • Include sensitivity tables for key variables
  • Reference independent engineering or third-party validation where available

For more on commercial RFP strategy, see our guide on closing commercial solar deals with procurement committees.

Tools and Standards for P50/P90 Cost Estimation

Monte Carlo add-ins such as @RISK and Crystal Ball are common ways to run probabilistic cost models in a spreadsheet. The Australian Government publishes its method in the Commonwealth Cost Estimation Guidance, a useful public template even for private projects.

For energy yield P50/P90, tools such as PVsyst, Solargis and NREL SAM model weather variability, equipment uncertainty and system losses. PVsyst’s documentation defines P50 and P90 as exceedance values, with P90 about 1.28 standard deviations below the mean on a normal distribution, in its P50 and P90 evaluations page. Solargis publishes a methodology that calculates P90 as the P50 value minus 1.282 times the standard deviation, with uncertainty components combined by root-sum-square.

When selecting tools, consider whether the cost and yield models can share inputs. A disconnected cost model and yield model force manual transfers that introduce errors. Integrated platforms reduce this risk.

A modern solar design platform that integrates layout, shading, yield simulation, and financial modeling reduces the handoff errors that often widen the P50/P90 spread.

How to Tighten the P50/P90 Cost Gap

A wide P50/P90 cost gap is not always bad, but it increases the cost of capital and reduces leverage. Developers can narrow the gap by reducing uncertainty before seeking financing.

Lock in major contracts early. Fixed-price module and inverter contracts remove pricing volatility. The earlier these are signed, the narrower the equipment uncertainty range.

Complete site investigations. Geotechnical reports, roof load assessments, and electrical infrastructure surveys reduce civil and interconnection uncertainty. A site with unknown soil conditions widens the uncertainty range on civil works.

Secure permitting milestones. Conditional use permits, interconnection agreements, and building permits should be advanced before FID. Permitting delays can push up labor and storage costs.

Use reference class forecasting. Compare the project to similar completed projects. The Grattan Institute discusses this approach in its piece on getting infrastructure megaproject cost estimates right.

Document assumptions transparently. Lenders and independent engineers will test every assumption. A well-documented uncertainty log makes it easier to defend the P90 and can reduce lender-imposed margins.

Further Reading

For the yield side, read P50 vs P90 energy yield explained. For what lenders ask for beyond percentiles, see solar bankability: what lenders check.

Percentiles only help if the cost and yield models share inputs. To see how SurgePV handles that handoff, book a demo and bring a project with real cost and yield assumptions.

Frequently Asked Questions

What is the difference between P50 and P90 cost estimates?

P50 is the median cost estimate, with a 50% probability the final cost will not exceed it. P90 is a conservative estimate with a 90% probability the final cost will not exceed it. P90 includes more contingency and is the figure lenders and risk-averse owners commonly use.

Why do solar lenders use P90 instead of P50?

Lenders commonly size debt on P90 because it is a conservative case. It shows whether debt service can still be covered when construction costs run high or energy production falls below the median. The exact percentile and minimum coverage ratio are set in each loan agreement.

How do you calculate P90 from a base cost estimate?

P90 is calculated by adding contingency to the base estimate, often using probabilistic Monte Carlo simulation. For a normal distribution, P90 ≈ mean + 1.28 × standard deviation of total cost uncertainty.

What is a typical P50 to P90 cost gap?

There is no single typical gap, because it depends on project maturity and risk. In the Commonwealth guidance worked example used in this post, the P90 project estimate is about 22% above the P50 one. Early-stage projects with little site data usually show a wider gap than projects near financial close.

Should solar proposals use P50 or P90?

Customer-facing proposals usually present P50 as the expected outcome. Financing documents and lender reports should use the percentile the lender specifies, often P90, for debt sizing and contingency planning.

Can P50 and P90 apply to energy yield as well as cost?

Yes. In solar, P50 is median expected annual production and P90 is conservative production exceeded 90% of the time. Lenders size debt against P90 revenue, not P50 revenue.

Where this fits

This article is part of SurgePV's Solar Business & Operations hub, which works through the topic from first principles to the decisions a project team actually has to make.

About the Contributors

Author
Akash Hirpara
Akash Hirpara

Co-Founder · SurgePV

Akash Hirpara is identified by SurgePV as a company co-founder. His SurgePV author page lists only role information that can be tied to the public profile below; education, certifications, project totals, financial results, speaking engagements, and media appearances are not asserted without retained evidence.

Editor
Rainer Neumann
Rainer Neumann

Editorial contributor · SurgePV

Rainer Neumann is credited as an editorial contributor on SurgePV content. This profile does not assert engineering credentials, project totals, software-testing experience, education, speaking engagements, or media citations because independent verification evidence is not retained in the publication record.

Get Solar Design Tips in Your Inbox

Join 2,000+ solar professionals. One email per week - no spam.

No spam · Unsubscribe anytime

Book Free Demo

Choose which optional technologies SurgePV may use. Essential storage remains active for security and requested features.