Back to Blog
solar roi8 min read

NTP, PTO and COD in Solar Projects: Meanings and Timeline

Distinguish contractual notice to proceed, utility permission to operate and commercial operation, with evidence to retain at each project milestone.

Akash Hirpara

Written by

Akash Hirpara

Co-Founder · SurgePV

Rainer Neumann

Edited by

Rainer Neumann

Editorial contributor · SurgePV

Published ·Updated

Answer

COD stands for Commercial Operation Date. It is the date a solar project counts as operating commercially under its contract. For example, it may be when a power purchase agreement starts buying the project's output. NTP is Notice to Proceed, which lets construction start. PTO is Permission to Operate, the utility's approval to run the system on its grid.

Last updated: November 2026

A solar project can be built, inspected and still not earn a cent. Three dates decide when work may start, when the system may switch on and when the contract starts counting: NTP, PTO and COD. This guide defines each one, shows who issues it and lists the evidence to keep, using two public documents as worked examples.

Keep Design Records Ready for Every Milestone

Book a guided demo to see how SurgePV outputs, such as layouts and bill-of-materials lists, can support the documents your permit and utility submittals need.

Book a Demo

Checking cost first? See the SurgePV pricing page.

What do NTP, PTO and COD stand for?

Term Full form What it decides Evidence to retain
NTP Notice to Proceed Authorisation to start specified contractual work The issued notice and the contract conditions behind it
PTO Permission to Operate The utility’s approval to operate the system on its grid The utility’s approval letter and its operating conditions
COD Commercial Operation Date The date commercial operation starts under the agreement The contract definition and proof that its conditions were met

Not every project uses all three terms. The governing contract or utility process sets the exact meaning. The sections below use two public documents. One is a 2019 solar power purchase agreement (PPA) between REC Solar Commercial Corporation and the County of El Dorado, California. A PPA is a contract to buy the power a system makes. The other is Pacific Gas and Electric’s (PG&E) Electric Rule No. 21 (Sheet 45, effective 29 August 2025).

What is COD in a solar project?

COD is the date the agreement treats the project as operating commercially. The definition sits in the contract, so it differs from one document to the next. Two examples show how:

  • The El Dorado County PPA (section 6.D) sets the COD as the date the provider notifies the county that the facility is mechanically and electrically complete and operational. The facility must also be providing output through the meters to the delivery point, under an approved and executed utility interconnection agreement. That agreement lets the system connect to the grid. Its definitions also require that the provider holds all local, state and federal permits and approvals.
  • PG&E’s Electric Rule No. 21 defines the commercial operation date as the date a generator starts commercial operation “as agreed to by the Parties”. Commercial operation means the facility has started to make electricity. It excludes electricity made during on-site test operations and commissioning (final system checks).

The first ties COD to completion, permits and an executed interconnection agreement. The second leaves the date to the parties and excludes test generation. Check which wording your agreement uses.

NTP: what work does it authorise?

A notice to proceed authorises a defined scope of work under a contract. Ask who issues it, which conditions must be met and whether it covers all work or one package. It is not a building permit. It is also not permission to switch the system on (energise).

In the El Dorado PPA (section 6), the county issues the notice to proceed once the provider has met the pre-construction conditions. These include:

  • certificates of insurance;
  • executed copies of the engineering, procurement and construction contracts;
  • a written check of the distribution utility’s transformer and conductor capacity;
  • a 90% complete design, a detailed construction schedule and a project safety plan;
  • evidence that the provider has secured financing for its obligations.

The provider may not start construction until it receives the notice. If the conditions are not met by the deadline, the county may waive (drop) or extend them, or terminate the agreement without the default terms applying. That is one contract. Other contracts name different issuers and conditions.

Pro Tip

Split your milestone log into four dates: physical completion, local inspection, utility permission and contractual acceptance. One “approved” status hides which step is still open.

Keep the issued notice, the authorised scope, the prerequisites and any exclusions on file. If procurement, early works and full construction are authorised separately, record each one.

PTO: local inspection and utility approval are separate steps

DOE’s rooftop permitting and inspection guidance describes the sequence. DOE is the US Department of Energy. The local government issues a permit before installation and inspects the finished array. The utility then connects the system to the grid. Passing inspection does not mean the utility has finished its approval.

PG&E’s Rule 21 shows how the steps connect. Take NEM-1, NEM-2 and NBT-1 (net metering and net billing tariff) generating facilities of 1 MW or smaller. For these, the utility’s approval to interconnect is labelled Permission to Operate. The rule says it “shall normally be processed” within 30 business days of the utility receiving three things. These are a complete interconnection request with payments and a signed interconnection agreement. The third is evidence of the final electric inspection clearance from the local authority. If the utility cannot meet the 30 days, it must tell the applicant and the California Public Utilities Commission. It must give the reason and the expected completion date.

So a system can be fully installed and inspected and still be waiting for PTO. Status updates should say which step is open. Calling the whole project “approved” hides that.

Systems that need new service, utility facilities or upgrades take longer. PG&E gives this advice to some applicants. They are applicants with non-inverter-based generators, uncertified equipment, new services or interconnection facilities. They should apply at least six months before their planned commercial operation date. If the project will be net metered, the net metering savings calculator shows what the credits are worth once operation starts.

What is COD in project finance?

In project finance, COD is the date a set of contract terms starts counting from. The El Dorado PPA shows five of these terms:

  1. Payment for output. The county buys output from the COD at the power price in the agreement (section 4.A).
  2. Contract years. The first contract year starts on the COD, and each later one runs from the anniversary (definitions, “Contract Year”).
  3. Output guarantee. From the third contract year after the COD, metered output over each measurement period must be at least 95% of the annual production estimate. The agreement lists exclusions such as outages, utility actions and force majeure (events outside anyone’s control) (section 4.B).
  4. Delay damages. The agreement sets a commercial operation deadline of 1 March 2020. Suppose commercial operation has not started by the 60th day after the deadline. Then the county may charge liquidated damages (a set fee for delay) of USD 1,000 for each calendar day following the deadline until the COD is reached. These are the county’s sole remedy for the delay. If operation has not started one year after the deadline, the county may terminate without penalty (section 6.D).
  5. Deadline extensions. The deadline extends day for day for delays the provider did not cause. These include a utility’s delay in approving the interconnection and a government authority’s delay in issuing permits. Other extensions are at the county’s discretion and carry a USD 350 per day fee (section 6.E).

The agreement also adds USD 500 per day in administrative delay damages when the punch list (a list of small unfinished jobs) is still open 30 days after the COD (section 6.F).

Daily fees in the El Dorado County PPA (USD per calendar day)
  • Delay damagesUSD 1,000 after day 60 past the COD deadline
  • Admin delay damagesUSD 500 punch list open 30 days after COD
  • Extension feeUSD 350 discretionary extensions

Source: El Dorado County PPA, sections 6.D, 6.E and 6.F (2019), checked November 2026.

This is one public-sector PPA from 2019. Another PPA, EPC (engineering, procurement and construction) contract or loan agreement will set its own deadlines and amounts. It will also set its own certificate requirements. Read the one that governs your project. In this PPA a utility delay extends the deadline. Check whether yours does.

Key Takeaway

COD is a contract term, not a universal date. In the El Dorado PPA it starts output payments, the contract years and the output guarantee. Your agreement may tie it to different events.

Documenting a Project Through COD?

Bring a live project to a guided demo and check which design and electrical outputs your NTP, PTO and COD paperwork needs.

Book a Demo

Checking cost first? See the SurgePV pricing page.

How long do NTP, PTO and COD take?

No single time covers every project. The published figures this guide can point to belong to specific documents:

Source Step Stated timing
PG&E Electric Rule No. 21, Sheet 45 PTO for NEM-1, NEM-2 and NBT-1 systems of 1 MW or smaller Normally within 30 business days of a complete request, signed agreement and final inspection clearance
PG&E Electric Rule No. 21, Sheet 45 Systems needing new service or utility upgrades Apply at least 6 months before the planned COD
El Dorado County PPA, section 6.C COD By 1 March 2020, extendable under section 6.E
El Dorado County PPA, section 6.A Pre-construction conditions before NTP Permits and approvals within 90 days of the effective date, unless extended

Use your contract schedule, the utility’s own service standard and your project’s current application status. Note what starts each processing period. Also note how an incomplete submission or correction work affects it.

When a stage slips, work out which later dates actually move. Not every later date shifts by the same amount.

Keep a milestone register

For each milestone, record its definition, issuer, prerequisite evidence, planned date, actual date and open conditions. Link it to the document revision. Use separate dates where these differ: physical completion, inspection, utility permission and contractual acceptance.

Do not assume COD starts every warranty, payment obligation or accounting treatment. In the El Dorado PPA it starts payment for output, the contract years and the output guarantee clock. A warranty or an accounting treatment may depend on a different trigger in another document.

Design records support the handoffs

Consistent drawings and equipment records help reviewers. But they do not set a permit date, shorten a utility queue or satisfy a commercial contract. Use the solar design workflow to organise document handoffs. Use the permit-ready drawing guide for cross-document review. Use the solar implementation workflow to see how teams control changes between design and installation.

SurgePV supports roof modeling, array layout and shading analysis. It also supports energy-yield and financial modeling, electrical workflow support, bill-of-materials output and proposals. It does not issue an NTP, PTO or COD certificate. Those come from the contract parties and the utility. Read more on SurgePV’s design workflow.

Frequently Asked Questions

What is COD in a solar project?

COD is the Commercial Operation Date. It is the date a solar project counts as operating commercially under its contract. In the El Dorado County power purchase agreement, for example, the county starts buying output from the COD. The exact definition is in the governing agreement.

What is the full form of NTP, PTO and COD in solar?

NTP is Notice to Proceed, PTO is Permission to Operate and COD is Commercial Operation Date.

What is COD in project finance?

In project finance, COD is the date the contract’s payment, guarantee and delay terms are measured from. In the El Dorado County PPA, output purchases begin on the COD. The first contract year starts on it, and delay damages run against a COD deadline.

Does PTO come before COD?

Not always in the same way. The El Dorado PPA defines COD as the date the facility is operational. It must also be delivering output under an approved and executed utility interconnection agreement. PG&E’s Rule 21 defines commercial operation as generating electricity. It excludes on-site test and commissioning output. Read the agreement before fixing the order.

How long does PTO take?

It depends on the utility and system. For NEM-1, NEM-2 and NBT-1 systems of 1 MW or smaller, PG&E’s Electric Rule 21 says approval to interconnect (permission to operate) should normally be processed within 30 business days. That clock runs from a complete request, signed agreement and final inspection clearance. Systems needing new service or utility upgrades are advised to apply at least six months before their planned COD.

Who issues the notice to proceed?

It depends on the contract. In the El Dorado County PPA, the county issues it once the developer meets the pre-construction conditions. The developer may not start construction before receiving it.

If you want to see how design outputs line up with a permit package, book a SurgePV demo.

Where this fits

This article is part of SurgePV's Solar Business & Operations hub, which works through the topic from first principles to the decisions a project team actually has to make.

About the Contributors

Author
Akash Hirpara
Akash Hirpara

Co-Founder · SurgePV

Akash Hirpara is identified by SurgePV as a company co-founder. His SurgePV author page lists only role information that can be tied to the public profile below; education, certifications, project totals, financial results, speaking engagements, and media appearances are not asserted without retained evidence.

Editor
Rainer Neumann
Rainer Neumann

Editorial contributor · SurgePV

Rainer Neumann is credited as an editorial contributor on SurgePV content. This profile does not assert engineering credentials, project totals, software-testing experience, education, speaking engagements, or media citations because independent verification evidence is not retained in the publication record.

Get Solar Design Tips in Your Inbox

Join 2,000+ solar professionals. One email per week - no spam.

No spam · Unsubscribe anytime

Book Free Demo

Choose which optional technologies SurgePV may use. Essential storage remains active for security and requested features.