Back to Blog
solar installation12 min read

Solar Commissioning Checklist: Tests, Documents and Handover

A seven-phase solar commissioning checklist with DC and AC tests, insulation resistance minimums, performance ratio, heat scans and a handover list.

Keyur Rakholiya

Written by

Keyur Rakholiya

CEO & Co-Founder · SurgePV

Rainer Neumann

Edited by

Rainer Neumann

Editorial contributor · SurgePV

Published ·Updated

Answer

A solar commissioning checklist has seven phases: paperwork, inspection, DC tests, AC and grid checks, inverter start-up, performance and heat checks, and handover. The DC tests are earth continuity, polarity, string voltage, string current and insulation resistance. Minimum insulation resistance is 0.5 MΩ below 120 V system voltage and 1 MΩ at 120 V and above.

A PV system can be wired exactly to the drawing and still fail the first time it is switched on. Commissioning catches those faults before the owner does. This page is a working checklist you can print and tick off on site.

Last updated: November 2026. Test values come from a utility guideline that applies IEC 62446-1, read on 28 October 2026.

Commissioning is the set of checks that prove a solar system is built as designed, safe to switch on, and ready to hand over. This page is a checklist in seven phases. For the order of work and the sign-off steps, read our solar commissioning protocol. This page is the list of checks. That page is the procedure.

The seven phases in one line each

  1. Paperwork and safety. Get the approved plans, the single line diagram (SLD, a simple drawing of how the system is wired) and the safety plan.
  2. Visual inspection. Check the build, the labels and the fire measures before you power anything.
  3. DC tests. Test earth continuity, polarity, string voltage, string current and insulation resistance.
  4. AC and grid checks. Test the AC circuit and the grid protection.
  5. Inverter start-up. Follow the maker’s steps, then check settings and monitoring.
  6. Performance and heat checks. Measure performance ratio, and scan for hot spots.
  7. Handover. Give the owner the records, labels, warranties and training.

Where these numbers come from

The test values on this page come from the Saudi Electricity Company (SEC) guideline, Inspection and Testing Guidelines, Version 2. It applies IEC 62446-1 (documentation, commissioning tests and inspection for grid-connected PV) and IEC 61724-1 (PV performance monitoring). IEC standards are paid documents, and the numbers here are read through this guideline. The IEC webstore describes IEC 62446-1:2016 as the paperwork handed to a customer after a grid-connected PV install, plus the startup tests and inspection. Your country, utility and contract can ask for different values. Always follow the rules you must meet.

Catch string faults before commissioning

Many DC test failures start in string design. See how SurgePV handles stringing and the bill of materials on one of your own projects.

Book a Demo

Checking cost first? See the SurgePV pricing page · No commitment required · 20 minutes

Phase 1: Paperwork and safety

  • Approved plans, permits and grid approval are on site.
  • The SLD matches what was built. Update it for any field change.
  • Datasheets and manuals for every main part are on site.
  • A safety plan names the risks on site. SEC asks for a safety form before inspectors visit.
  • The tester has instruments rated for the circuit’s voltage and current.

PV is live in daylight. SEC notes that work on a PV array counts as work under voltage. Short both module connectors, or keep the module connectors and the string breaker open, while you work.

Phase 2: Visual inspection

SEC says inspection comes before testing, and normally before you energize the system.

  • Modules, frames and mounts show no damage. Roof fixings and cable entries are weatherproof.
  • The DC system suits the site’s wind, heat, dust and corrosion.
  • The highest array voltage suits the chosen inverter and site.
  • Earthing and bonding conductors are fitted as designed.
  • Surge protection is in place where the design asks for it.
  • Fire measures follow your local code. Rules differ by country, so see our guide to fire safety setback rules by country.

Labels and signs

SEC’s list of labels to check includes these:

  • Every circuit, device, switch and terminal is labeled.
  • Combiner boxes carry a warning that parts inside may stay live after isolation.
  • The AC isolation point is clearly labeled.
  • Dual-supply warnings are at the point of connection.
  • The SLD, inverter protection settings, installer details and shutdown steps are displayed on site.
  • All signs are fixed and durable.

Phase 3: DC tests

Run the tests in this order. SEC says that if a test finds a fault, you fix it and then repeat the earlier tests.

Test What it checks What to look for
1. Earth and bonding continuity Frame and bonding conductors are connected Continuity on every fitted conductor and to the main earth terminal
2. Polarity Each string cable has the right plus and minus Check before any switch is closed or strings are joined
3. Combiner box Strings are joined correctly Each string is in its right place
4. String open circuit voltage (Voc) The right number of modules are in series Matches the expected value. In stable light, strings agree within 5%
5. String current No big wiring or module fault In stable light, typically within 5% of the average string current
6. Functional tests Switches and inverters work Follow the inverter maker’s steps
7. Insulation resistance The wiring insulation is sound At or above the values in the table below

SEC says an I-V curve test is an accepted way to get both Voc and Isc, so you can skip the separate tests. An I-V curve is a graph of a string’s voltage against its current. See our glossary entry on the I-V curve.

Open circuit voltage: the expected value

The expected Voc depends on cell temperature. A module’s temperature coefficient tells you how much.

Voc at temperature T = Voc(STC) × [1 + βVoc × (T − 25)]

Here STC means standard test conditions, and βVoc is the Voc temperature coefficient from the datasheet. It is a negative number. The numbers below are an example, not a datasheet:

  • Module Voc(STC) 40 V, βVoc −0.30% per °C, cell temperature 45 °C. Expected Voc = 40 × [1 + (−0.003 × 20)] = 40 × 0.94 = 37.6 V per module.
  • Same module at −10 °C: 40 × [1 + (−0.003 × −35)] = 40 × 1.105 = 44.2 V per module. In a 20-module string that is 884 V. This must stay below the inverter’s maximum DC input voltage on its datasheet.

Insulation resistance: minimum values

SEC’s Table 2, taken from IEC 62446-1, sets the test voltage and the minimum resistance. System voltage here means Voc(STC) × 1.25.

System voltage (Voc(STC) × 1.25) Test voltage Minimum insulation resistance
Below 120 V 250 V 0.5 MΩ
120 V to 500 V 500 V 1 MΩ
Above 500 V 1,000 V 1 MΩ
Insulation resistance test voltage by system voltage band (test voltage, volts)
  • Below 120 V250 V min 0.5 MΩ
  • 120 V to 500 V500 V min 1 MΩ
  • Above 500 V1,000 V min 1 MΩ

Source: Saudi Electricity Company Inspection and Testing Guidelines v2, Table 2 (from IEC 62446-1), checked 28 October 2026.

Two examples, with modules of 40 V Voc(STC):

  • 20 modules in series: 20 × 40 = 800 V. Then 800 × 1.25 = 1,000 V, which is above 500 V. Test at 1,000 V. The minimum is 1 MΩ.
  • 8 modules in series: 8 × 40 = 320 V. Then 320 × 1.25 = 400 V, which is in the 120 V to 500 V row. Test at 500 V. The minimum is 1 MΩ.

For arrays up to 10 kWp, measure the whole array. For arrays above 10 kWp, test single strings, or groups of strings that total no more than 10 kWp. Take surge protectors out of the circuit first if they could change the result. SEC suggests a wet insulation test when a result is doubtful.

Key Takeaway

Work out system voltage as Voc(STC) × 1.25 before you pick the test voltage. A 20-module string at 40 V per module needs a 1,000 V test, not 500 V.

Safety during the insulation test

The array is live in daylight, so the test is a shock risk. SEC says to limit access, not to touch metal parts or the back of any module while the tester is on, and to use gear that discharges itself.

Systems with optimizers or microinverters

Module-level electronics change the test plan. SEC’s Table 1 says:

Equipment What changes
AC module No DC test or DC inspection
Microinverter, no site-built wiring No DC test. DC inspection is still needed
Microinverter, site-built wiring DC test and DC inspection are needed
Other module-level electronics, such as power optimizers Follow the basic tests where you can. Ask the maker about limits, such as the insulation test, and about pass or fail values, such as the expected Voc

Design strings that pass the first test

Bring a project to a SurgePV demo and see DC stringing and bill-of-materials output on it, before the crew reaches the combiner box.

Book a Demo

Want pricing first? Visit the SurgePV pricing page · Guided demo · Bring a real project

Phase 4: AC and grid checks

  • Insulation resistance test of the AC circuit, as IEC 60364-6 asks.
  • Interface protection settings match what your utility requires. SEC checks the settings, thresholds and times.
  • The interface device disconnects the system when the grid power fails.
  • After power returns, the interface device reconnects.
  • If the site must limit export, test that the limit works and that the meter reads in the right direction.
  • In the US, check the rapid shutdown rule in NEC 690.12 for the code edition your authority uses (NFPA lists 2026 as the current edition of NFPA 70 and 2023 as the one before it). See our entry on rapid shutdown.

The exact trip values come from your utility’s grid code. We do not give them here because they differ by country.

Phase 5: Inverter start-up and monitoring

  • Follow the inverter maker’s start-up steps. SEC says to test inverters as the maker defines.
  • Set the grid country code and grid settings as your utility requires.
  • Confirm the string voltages sit inside the inverter’s input window, including at the coldest expected cell temperature.
  • Check that the monitoring system records output, and irradiance and temperature if sensors are fitted.
  • Test alarms and the remote alert.
  • Test remote access from off site.

For more on inverter records, see our inverter commissioning data record.

Phase 6: Performance and heat checks

Performance ratio (PR)

Performance ratio compares the energy a system made with the energy it should have made. IEC 61724-1 defines it as PR = Yf ÷ Yr. Yf is the final yield (kWh made per kWp installed). Yr is the reference yield (the sun energy on the array, in kWh per m², divided by 1 kW per m²).

Example for one day: a 10 kWp system makes 49.2 kWh. The sun energy on the array is 6.0 kWh/m².

  • Yf = 49.2 ÷ 10 = 4.92 hours
  • Yr = 6.0 ÷ 1 = 6.0 hours
  • PR = 4.92 ÷ 6.0 = 0.82, or 82%

Hot modules lower PR, so PR is lower in summer. SEC explains that a temperature-corrected PR removes much of this. In the STC version, the power rating at each time step is adjusted by Ck = 1 + γ × (Tmod − 25 °C), where γ is the power temperature coefficient and Tmod is the module temperature.

How long is the test, and what is a pass?

Your contract sets both. SEC gives one example for test length:

System size Test length (SEC)
Up to 11 kW At least one valid measurement
Above 11 kW, up to 100 kW 1 day, with 99% valid data
Above 100 kW At least 10 days, with 95% valid data

SEC’s guideline sets no PR pass or fail value for its commissioning test. If your EPC contract names a PR target, use the contract’s test method. See also our solar performance ratio guide.

I-V curve tests

SEC says to measure string performance at stable irradiance of at least 400 W/m² in the plane of the array. To refer results to STC, use at least 800 W/m².

Thermal (infrared) scan

An infrared camera finds hot spots from bad cells, failed bypass diodes, poor connections and open strings. SEC’s method:

  • Run the array in normal operation.
  • Scan in steady light, ideally above 600 W/m² in the plane of the array.
  • Scan every module, and look closely at junction boxes and connections.
  • Compare each hot spot with its neighbors. A fixed temperature limit is not useful, because array temperature changes through the day.
  • Mark each hot spot on the layout drawing and find the cause.

IEC TS 62446-3 sets the rules for outdoor thermography.

Shade record

SEC suggests recording the as-built shade as a baseline. It helps later if the shade changes or a performance guarantee is in dispute. See our shadow analysis page for how shading is modeled at the design stage.

Phase 7: Handover

The owner or O&M team should receive:

  • As-built drawings and the updated SLD.
  • Test reports with dates, instruments and results. SEC’s report list includes the test engineer, the site, the checks of interface protection and monitoring, and any change from the test plan.
  • Datasheets, serial numbers and warranty papers.
  • The grid approval and the final electrical inspection certificate. Some regions call it a CFEI. See what a CFEI is.
  • Inverter settings, including protection settings, and monitoring log-ins.
  • Shutdown and emergency steps, shown on site.
  • The performance baseline and the shade record.
  • A signed record that the owner’s staff were trained.

Store the records in a shared place, not on one laptop.

Provisional and final acceptance (PAC and FAC)

Many commercial EPC contracts use two certificates. The names and the timing come from your contract, so check yours.

Provisional Acceptance Certificate (PAC) Final Acceptance Certificate (FAC)
When After the commissioning tests pass and the plant runs After the defects period in the contract ends
Why Shows the plant is complete enough to run Shows the defects period is over and defects are fixed
Tests The tests your contract names Any final checks your contract names
Open items Minor items are listed on a punch list The punch list is closed
Who is responsible The owner starts to operate the plant The contractor’s duty to fix defects ends

Common failures and how to avoid them

Problem Likely cause How to prevent it
String voltage is too low Wrong number of modules in the string Check the module count against the SLD before you connect
Insulation resistance fails Damaged cable or water at a gland Test at the pull-through stage, not only at the end
Inverter trips on grid faults Wrong country code or settings Set the grid code before start-up
Performance is low Shade, soiling or wrong inverter settings Run shading analysis at design stage and clean before the test
Papers are missing No process to update drawings Name one person to keep the as-built set
Monitoring does not connect Wrong network or register settings Test communications before the performance test

Good string design can remove some DC test failures before the tester arrives.

After commissioning

The baseline you record now is the reference for later checks. Keep the PR result, the string readings and the monitoring set-up where the O&M team can find them. Set alerts for lost communication, a falling PR against your baseline, and a string that drifts from its neighbors. For more, read our guides to solar monitoring and the solar O&M business.

For the upstream steps, see our guides to panel installation and ground-mount design. For project milestones, see NTP, PTO and COD. To see how SurgePV supports the design stage that feeds this checklist, book a demo.

Further Reading

The continuity step has its own method. See the solar continuity test guide for earthing and bonding checks, and insulation resistance testing for the Phase 3 insulation step.

Source

Frequently Asked Questions

What is a solar commissioning checklist?

A solar commissioning checklist is a list of checks that prove a PV system is built as designed, safe to switch on and ready for handover. It covers paperwork, inspection, DC tests, AC and grid checks, inverter start-up, performance and heat checks, and the handover records.

What standards apply to solar commissioning?

IEC 62446-1 covers documentation, commissioning tests and inspection for grid-connected PV. IEC 61724-1 covers performance monitoring and performance ratio. IEC TS 62446-3 covers outdoor thermography. Your local electrical code and your utility’s grid rules also apply. In the US that includes the NEC rules your authority uses.

What is the minimum insulation resistance for a PV array?

The Saudi Electricity Company guideline, which applies IEC 62446-1, gives 0.5 MΩ for system voltage below 120 V (test at 250 V), 1 MΩ for 120 V to 500 V (test at 500 V), and 1 MΩ above 500 V (test at 1,000 V). System voltage means Voc at STC multiplied by 1.25.

Which DC tests do you run during commissioning?

The basic DC tests are earth and bonding continuity, polarity, the combiner box test, string open circuit voltage, string current, functional tests and insulation resistance. An I-V curve test can replace the separate Voc and Isc tests.

What is the difference between PAC and FAC?

A Provisional Acceptance Certificate (PAC) is issued when the commissioning tests pass and the plant is running. A Final Acceptance Certificate (FAC) is issued after the defects period in the contract ends. Names and timing come from your contract.

Is there a minimum performance ratio for sign-off?

The contract sets it. The Saudi Electricity Company guideline gives no PR pass or fail value for its commissioning test. If your contract names a PR target, use the test method the contract names.

How long does a performance test last?

It depends on the rule you follow. One example is the Saudi Electricity Company guideline: at least one valid measurement up to 11 kW, one day with 99% valid data above 11 kW and up to 100 kW, and at least 10 days with 95% valid data above 100 kW.

Where this fits

This article is part of SurgePV's Solar Installation hub, which works through the topic from first principles to the decisions a project team actually has to make.

About the Contributors

Author
Keyur Rakholiya
Keyur Rakholiya

CEO & Co-Founder · SurgePV

Keyur Rakholiya is identified by SurgePV as its CEO and a company co-founder. His SurgePV author page lists only role information that can be tied to the public profile below; credentials, project totals, testing claims, media appearances, and speaking engagements are not asserted without retained evidence.

Editor
Rainer Neumann
Rainer Neumann

Editorial contributor · SurgePV

Rainer Neumann is credited as an editorial contributor on SurgePV content. This profile does not assert engineering credentials, project totals, software-testing experience, education, speaking engagements, or media citations because independent verification evidence is not retained in the publication record.

Get Solar Design Tips in Your Inbox

Join 2,000+ solar professionals. One email per week - no spam.

No spam · Unsubscribe anytime

Book Free Demo

Choose which optional technologies SurgePV may use. Essential storage remains active for security and requested features.