Back to Blog
solar case study28 min read

Off-Grid Solar for Chile Mines: Diesel Swap Example

A worked design example of off-grid solar, battery storage and diesel for a remote Chilean mine, with payback math and three published projects.

Akash Hirpara

Written by

Akash Hirpara

Co-Founder · SurgePV

Nirav Dhanani

Edited by

Nirav Dhanani

Co-Founder · SurgePV

Published ·Updated

Answer

Off-grid solar with battery storage can displace part of a remote mine's diesel use, but the saving depends on the load, solar fraction and fuel price. In a hypothetical Chilean example, a 4 MWp array and 6 MWh battery cut fuel by about 57% and paid back in about 4.5 years. Test your own inputs.

Last updated: November 2026

SurgePV publishes this post and sells solar design software.

This is a worked design example, not the record of a named mine. The site, the load and every cost in it are assumptions chosen to show how a solar, battery and diesel hybrid is sized and checked for a remote mine in Chile’s Atacama region. Real projects have different numbers, so use the method and replace each input with measured data. The comparison with three published mining projects later in the post uses figures from public reports, which are linked.

The Atacama Desert in northern Chile is one of the driest places on Earth and one of the richest mining regions. Operations there need steady power, and remote sites without a grid connection have historically relied on diesel generation. Delivered fuel can be expensive because it travels long distances by road, so a hybrid that replaces part of the diesel burn can change the cost of power.

TL;DR: Off-Grid Solar for a Chilean Mine

In this hypothetical example, a 4 MWp solar array, a 6 MWh battery and a 2.25 MW diesel plant serve a mine with a 1 MW average load. At an assumed 58% solar fraction, diesel use falls from about 2.45 million litres to about 1.07 million litres a year, and simple payback is about 4.5 years. The result depends on the diesel price, the solar fraction and the capital cost, so test your own inputs.

Size your own hybrid before you ask for quotes

Run yield, shading and financial scenarios with your own load profile and fuel price, so the first conversation with suppliers starts from your numbers.

Book a Demo

Checking cost first? See the SurgePV pricing page.

In this guide:

  • The hypothetical mine, its load and why grid extension is compared with a hybrid
  • Site conditions in the Atacama: solar resource, altitude, temperature swings and dust
  • Load analysis for a 24-hour mining process
  • Hybrid design: PV array, battery bank and diesel plant
  • How an energy management system dispatches the three sources
  • A financial model with payback, NPV, IRR and sensitivities
  • Installation, logistics, monitoring and maintenance in a remote location
  • Three published off-grid mining solar projects for comparison
  • Lessons for future projects, and an FAQ

Example Overview: The Hypothetical Mine and Its Energy Problem

Assume a copper oxide operation in the Antofagasta Region that uses heap leaching and solvent extraction-electrowinning (SX-EW) and runs around the clock. It sits at about 3,000 metres above sea level, with no grid connection, and has always generated its own power with diesel sets.

Assumptions Used Throughout This Example

Parameter Assumed value
Location Antofagasta Region, Chile, at altitude
Average load 1,000 kW (8,760 MWh per year)
Coincident peak load 1,250 kW
Schedule 24 hours a day, most days of the year
Diesel plant today Three sets, 750 kW each, 2.25 MW total
Specific fuel use, diesel only 0.28 litres per kWh
Delivered diesel price USD 1.60 per litre
Baseline fuel About 2.45 million litres, or USD 3.92 million, per year

Every later table builds on these inputs. If your load, fuel price or fuel use differ, the results change in proportion, which is why the sensitivity section matters.

Grid Extension vs a Hybrid: How to Compare

For a remote mine, the first question is whether the grid can reach the site at a reasonable cost. A fair comparison has three cases: continued diesel, a grid extension if one is feasible, and a hybrid. For the grid case, collect quotes for the line, the substation, the right-of-way work and the recurring connection and capacity charges, and note the timeline, because permitting across mining concessions and protected areas can take years. Compare the total cost of each case over the remaining reserve life, not only the capital cost.

The grid case often loses where the distance is long and the reserve life is short, because the capital is spread over fewer years. A hybrid can win where solar resource is strong and delivered diesel is expensive. This post does not state a general distance threshold, because the break-even depends on line cost per kilometre, terrain, reserve life and fuel price, and none of these is a fixed number.

Pro Tip: Build Three Cases Before Any Design

Model continued diesel, grid extension and the hybrid on the same load, reserve life and discount rate. If the hybrid only wins at one fuel price, you have found the risk you need to manage before you sign anything.


Site Assessment: Atacama Conditions

The Atacama offers some of the best solar resource in the world and some of the hardest operating conditions. A design has to deal with both.

Solar Resource

The Atacama is among the highest-irradiance regions measured. For a real project, do not use a regional figure. Pull site-specific data from the Global Solar Atlas, and where possible install a ground station for a year or more, because bankable yield estimates need measured data. This example assumes a specific yield of 2,300 kWh per kWp per year for fixed tilt before soiling, which is an assumption for illustration, not a measured site value.

The features that drive resource in the Atacama are well known: very dry air, few cloudy days and a high sun angle, with strong direct irradiance. Compare tilt, azimuth and tracking options in a simulation using your own data, instead of copying values from another site.

Altitude Effects

Altitude changes how a system behaves in several ways. Air is thinner, so convective cooling of electronics is weaker and inverters, transformers and switchgear need derating or extra cooling. Irradiance is somewhat higher than at sea level because there is less atmosphere above the site. Crews need time to acclimatize, which affects schedules and labour cost. Ask each equipment supplier for the altitude derating curve for your site, and confirm that insulation clearances in switchgear are specified for the elevation.

Temperature Swings

The Atacama can see cold nights and warm days, so equipment cycles through a wide range. For PV modules, hot cells lose power, and you can estimate the loss with simple arithmetic. With an assumed temperature coefficient of power of −0.35% per °C, a cell temperature of 65°C is 40°C above the 25°C test condition, which gives a loss of about 14% from the nameplate rating at that moment. Check the temperature coefficient on the datasheet of the module you plan to buy, because lower coefficients matter more in hot sites.

Batteries need thermal management at both ends of the range. Lithium iron phosphate (LFP) chemistry is common for stationary storage, but charging at low cell temperatures is restricted by most manufacturers, so heating may be needed on cold mornings, and cooling is needed in the heat. Specify the operating temperature range and the thermal system in the battery supplier’s datasheet, and size the auxiliary load for heating and cooling in the energy balance.

Dust: The Operating Constraint

Dust is the main operating issue for desert PV. It comes from dry lake beds, alluvial fans and wind erosion, and it can include salts that are corrosive to frames and electrical contacts over time. Soiling can cut output quickly between cleanings, and rain that would wash panels is rare.

Cleaning options include automated dry brush systems, scheduled wet cleaning with demineralized water, and hydrophobic or anti-soiling coatings. Each has a different cost, water need and risk, so evaluate them against your water supply. This example assumes an average soiling and other loss of 8% across the year with a planned cleaning routine, and tests a worse case in the sensitivity section.

Key Takeaway: Design for the Environment, Not the Datasheet

The Atacama’s resource is excellent, but dust, temperature, altitude and UV all affect equipment. Ask for derating curves, soiling assumptions, thermal specifications and UV ratings in writing from each supplier, and keep them in the design basis.


Load Analysis: What the Mine Consumes

Accurate load profiling is the basis of an off-grid hybrid design. Mining loads are large, continuous and often include processes that cannot be interrupted.

Assumed Load Categories

Category Average kW Peak kW Daily energy (kWh) Critical?
SX-EW processing 620 700 14,880 Yes, not interruptible
Heap leach pumps and process water 180 230 4,320 Yes, restart takes hours
Crushing and agglomeration 100 190 2,400 No, can pause
Camp and facilities 80 120 1,920 Partly, safety systems are critical
Workshop and equipment charging 20 50 480 No
Total 1,000 1,250 coincident 24,000

Peaks in the table add to 1,290 kW, but the assumed coincident peak is 1,250 kW because not every load peaks at the same time. Replace these figures with metered data from the site.

Daily Load Profile

Mining loads do not follow a commercial daytime peak. Electrowinning runs continuously, pumps run on a schedule, camp loads peak at meal and shower times, and crushing follows ore deliveries. The result is a fairly flat profile, with a night minimum not far below the day peak.

That flatness drives the design. The battery must supply a sustained draw for many hours each night, and midday solar beyond the load can only be used if the battery can absorb it. A system sized for a commercial rooftop pattern would underperform on a profile like this.

Load Growth

If a process expansion is planned, include it. Adding PV or battery capacity after the first build is usually more expensive per unit than including it at the start, because of remote mobilization and integration work. Size for the planned load at about year five, not year one, and phase the equipment where the design allows.


Hybrid System Design: PV, Battery and Diesel

The design goal is to maximize diesel displacement while keeping full availability for critical loads. Solar carries the daytime load, the battery covers part of the night, and diesel runs only when the other two are not enough.

PV Array: 4 MWp

Parameter Example specification
DC capacity 4,000 kWp
Modules About 7,270 modules of 550 Wp
Inverter capacity 3,200 kW AC, so DC to AC ratio of 1.25
Mounting Fixed tilt, steel structure
Tilt and azimuth Latitude-based tilt, facing true north
Annual yield before losses (assumed) 2,300 kWh per kWp, or 9,200 MWh
Net energy after an assumed 8% soiling and other losses About 8,464 MWh

Fixed tilt or tracking? Single-axis tracking increases yield but adds moving parts, which means more maintenance in a dusty site. Evaluate both in a simulation with your own soiling and O&M assumptions. For this example, assume fixed tilt for simplicity.

Bifacial or monofacial? Rear-side gain depends on ground reflectivity and mounting height. Over dark gravel the gain is small, so a bifacial module may not pay for itself. Read our bifacial solar panel design guide before choosing, and model rear gain with site-specific albedo.

Battery Bank: 6 MWh

Parameter Example specification
Chemistry Lithium iron phosphate
Nominal energy 6 MWh
Usable energy at 90% depth of discharge 5.4 MWh
Power rating 2.5 MW
Thermal management Active heating and cooling per container
Round-trip efficiency Per supplier datasheet

The overnight energy need is large. At an average of about 0.95 MW over 12 hours, the night load is roughly 11.4 MWh, so a 5.4 MWh usable battery covers about half of it. That is why diesel still runs on most nights in this design. A larger battery covers more of the night and cuts diesel further, but each extra MWh costs money and sits idle on good days, so size it by testing options in an hourly simulation.

Depth of discharge. Cycling the battery between about 10% and 90% state of charge protects its life and leaves a reserve for generator start-up delays. The exact window comes from the battery manufacturer’s warranty terms.

Diesel Plant: Three 750 kW Sets

Parameter Example specification
Total capacity 2,250 kW (three sets of 750 kW)
Role Cover the night balance, cloudy spells and any shortfall
Minimum loading Per manufacturer, often around 30% of rating
Start time From warm standby in seconds; check the datasheet
Fuel storage Sized for several days at full operation

Several smaller sets match load better than one large set, because a set running at low load burns more fuel per kWh and wears faster, and a spare set keeps availability high when one is in maintenance. Operating modes in a hybrid typically include off, warm standby, spinning reserve and full operation, and the EMS chooses the mode for each set.

Energy Balance in the Example

Item Value
Annual load 8,760 MWh
Net PV energy About 8,464 MWh
Assumed solar fraction 58%
Solar energy delivered to load (directly and via battery) About 5,081 MWh
Share of PV output used About 60%
Diesel energy About 3,679 MWh

Only about 60% of PV output is used in this example, because midday PV exceeds the load once the battery is full, and storage has losses. This is why adding more PV does not raise solar fraction in proportion, and why the next MWh of battery often adds more than the next MWp of PV.


Energy Management System: The Brain of the Hybrid

The energy management system (EMS) decides how the three sources share the load. Without good dispatch, the system either wastes solar or runs diesel more than it should.

Control Layers

Real-time control (milliseconds to seconds): Frequency and voltage regulation. The battery inverter can provide fast frequency response, and the diesel sets provide secondary control when online.

Short-term dispatch (minutes to hours): Load following and solar smoothing. The EMS compares actual PV output with forecast, adjusts battery charge and discharge, and decides when to start or stop generators.

Predictive optimization (hours to a day ahead): A rolling optimization uses weather forecasts, load schedules and generator fuel curves to minimize diesel use while meeting every constraint.

The Diesel Minimization Problem

The core problem is to minimize fuel use over the next period, subject to:

  • Power balance at all times, generation equal to load plus losses
  • Battery state-of-charge and power limits
  • Generator minimum loading, ramp limits and start-stop costs
  • A guarantee of power for critical loads

This is commonly set up as a mixed-integer linear program (MILP) that is re-solved at a fixed interval. The output is which sets run, their setpoints, the battery charge or discharge power and the expected fuel burn.

Typical Operating Modes Across a Day

Time of day Typical mode in a winter pattern
Night Battery supplies part of the load and diesel carries the rest
Early morning Diesel carries the load while solar is low and the battery is near its lower limit
Mid-morning to afternoon Solar carries the load and charges the battery, diesel off
Late afternoon Battery takes over as solar declines
Evening Battery discharges, diesel starts again if the battery is depleted early

In summer, longer days mean the battery reaches a higher state of charge and diesel runs less overnight. The pattern, not the exact hours, is what matters for design.

Load Prioritization

Not all loads are equal, so the EMS needs a shedding order agreed with operations.

Tier 1, critical: electrowinning cells, solution pumps, ventilation, safety lighting, communications and fire suppression. These get guaranteed power.

Tier 2, important: irrigation pumps that can pause for a short time, camp heating and cooling, and water treatment.

Tier 3, flexible: crushing and agglomeration, workshop equipment and non-critical lighting.

Tier 4, optional: mobile equipment charging and other non-essential loads, shed first whenever diesel would otherwise need to start.

The shedding is carried out by controllers on each feeder, with the EMS sending commands over the site control network. Test every shedding step during commissioning.

Key Takeaway: The EMS Decides How Much of the Hardware Is Used

The panels, batteries and generators are standard products. How well the EMS forecasts and dispatches them largely decides how much diesel is actually saved. Ask each supplier how its dispatch works, how forecasts are produced and how you can audit the results.


Financial Analysis: The Business Case

In this example the case rests on diesel savings alone. It assumes no incentives, tariffs or carbon revenue.

Capital Cost Assumptions

Component Assumed cost (USD)
PV modules, mounting and balance of system (4,000 kWp at USD 1.05 per Wp) 4,200,000
Battery system (6 MWh at USD 380 per kWh installed) 2,280,000
Inverters and medium-voltage equipment 550,000
EMS, SCADA and controls 300,000
Civil works and site preparation 400,000
Remote logistics and mobilization 600,000
Engineering and project management 350,000
Subtotal 8,680,000
Contingency at 8% 694,400
Total 9,374,400

These are assumptions for illustration. Real quotes vary with supplier, logistics and timing, so replace every line with a quote.

Annual Operating Cost Comparison

Item Diesel only Hybrid
Diesel fuel (2.45 million litres vs 1.07 million litres at USD 1.60) USD 3,924,480 USD 1,707,149
Fuel saving USD 2,217,331
Added PV cleaning and O&M USD 110,000
Added battery maintenance USD 50,000
Added EMS licence and support USD 30,000
Added insurance USD 35,000
Less lower generator maintenance −USD 90,000
Net annual saving USD 2,082,331

Hybrid fuel assumes a 58% solar fraction and 0.29 litres per kWh for the remaining diesel energy, which is a little higher than the diesel-only figure because of part-load operation and spinning reserve.

Illustrative example, not market data: annual fuel cost, diesel only vs hybrid (USD million per year)
  • Diesel only, fuel$3.92
  • Hybrid, fuel$1.71
  • Net annual saving after added O&M$2.08

Source: Worked arithmetic with the stated assumptions (illustrative example, not market data), checked November 2026.

Payback and Return Metrics

Metric Value
Total capital cost USD 9,374,400
Net annual saving USD 2,082,331
Simple payback About 4.5 years
NPV over 15 years at 10%, with a USD 1.8 million battery replacement in year 12 About USD 5.9 million
IRR over 15 years, same assumptions About 20%

The NPV and IRR assume a constant annual saving and a battery replacement cost of USD 1.8 million in year 12, both of which are assumptions. If the reserve life is shorter than 15 years, truncate the cash flows and recompute. The calculation ignores tax, inflation, fuel price changes and degradation.

Sensitivity Analysis

Variable Case Net annual saving Simple payback
Diesel price USD 1.28 per litre (−20%) USD 1.64 million 5.7 years
Diesel price USD 1.92 per litre (+20%) USD 2.53 million 3.7 years
Solar fraction 48% USD 1.68 million 5.6 years
Solar fraction 68% USD 2.49 million 3.8 years
Capital cost +20% USD 2.08 million 5.4 years
Capital cost −20% USD 2.08 million 3.6 years

The results are most sensitive to the diesel price and the solar fraction, so the first job of a feasibility study is to pin both down with real data. Fuel price volatility cuts both ways: higher prices shorten payback, while lower prices lengthen it.

Remote Fuel Logistics: The Cost Behind the Price

A delivered diesel price is more than the commodity price. It includes transport over long distances, storage and handling, inventory carrying cost, security, insurance and taxes. Ask your fuel supplier for a breakdown so you know which parts move with the market and which are fixed. Fewer tanker deliveries also mean less road risk, which the example does not monetize.

Test the payback on your own load and fuel price

Use the generation and financial tool to model solar yield, battery use and fuel savings for your site, then compare cases before you commit capital.

Book a Demo

Checking cost first? See the SurgePV pricing page.


Installation and Logistics: Building in the Desert

Remote construction is its own discipline. A site like this may have no infrastructure, no local labour pool, limited water and little tolerance for schedule slippage.

Site Access and Transport

Plan the route before you plan the schedule. Check road class and bridge limits, seasonal closures from rain or snow at altitude, and heat limits on heavy haulage. Heavy components such as battery containers, inverters and generator sets usually arrive by ship at a port and travel the last leg by heavy-haul trailer, so confirm axle loads and escort requirements with the carrier. PV modules arrive in standard containers, and the number of container loads and truck trips drives both cost and schedule. Build a transport plan with the actual component weights from the supplier.

Prefabrication

Maximize prefabrication for remote sites. Battery containers can arrive with batteries, battery management system, thermal system, fire suppression and power conversion installed and checked at the factory, which cuts site work to positioning, cabling and commissioning. An inverter and switchgear building can arrive as one module and be craned onto its foundation. A control room with EMS servers and SCADA workstations can be built and checked in a container. Factory acceptance testing finds wiring and configuration errors before the equipment is shipped to a site where fixes cost far more.

Heavy Lifts

Some components are too heavy for the available crane or the access road. Where a main transformer or large building module cannot be moved by road, plan a crane with enough capacity, or consider a helicopter lift where regulations and site conditions allow. Heavy lifts add cost and weather risk, so decide early and price them in the logistics line.

Water for Construction and Cleaning

The Atacama has no surface water, so construction and cleaning water come from the mine’s own supply, often a desalination or reverse-osmosis plant, or from trucked supply. Estimate water for concrete, dust suppression and module cleaning, and check that the supply can serve both the project and the mine’s process needs. Water for ongoing cleaning is a continuing demand, so size it in the operating plan.

Construction Schedule

Phase Main activities
Mobilization and site preparation Camp expansion, road grading, laydown area
Civil works Foundations, trenches, fencing
PV installation Mounting, string wiring, DC testing
Battery and inverter installation Container placement, cabling, commissioning
Generator integration Installation, fuel system, synchronization
EMS commissioning Programming, testing, operator training
Performance testing Load tests and a continuous run

Durations depend on crew size, access and weather, so ask your EPC contractor for a resource-loaded schedule instead of assuming a number.


Performance: How to Judge the First Year

A hybrid is only as good as its measured results. Agree on the performance indicators before commissioning, and compare them against the design case.

Key Performance Indicators

Indicator How to calculate it What it tells you
Solar fraction Solar energy delivered to load divided by total load How much of the energy comes from PV
Diesel reduction 1 minus (hybrid diesel litres divided by baseline litres at the same load) Fuel actually saved
Specific fuel consumption Litres divided by diesel kWh Whether generators run efficiently
PV performance ratio Measured PV energy divided by expected energy for the measured irradiance Whether the array and cleaning plan work
Battery cycles and state-of-charge window From the battery management system Whether the battery is used as designed
Availability Hours of power available to critical loads divided by total hours Reliability of supply

Compare diesel reduction with solar fraction. They are not the same, because generators still run for stability and reserve even when solar fraction is high.

Why First-Year Results Can Fall Below the Design Case

First-year performance of a new hybrid can fall below design for reasons that are easy to test in advance:

  • Soiling is worse than modeled. A dust event or a longer interval between cleanings can push soiling above the assumed 8%.
  • Operators run conservative limits at first. A narrower battery state-of-charge window gives less usable capacity and brings generators on earlier.
  • Load changes. Higher production raises demand, which can raise diesel use even when the system works as designed.
  • Forecast errors. A weak solar forecast leads to unnecessary generator starts.

The first two can be checked in the example. Suppose soiling rises from 8% to 12%, so net PV falls from 8,464 MWh to about 8,096 MWh, a drop of about 4%. If the solar fraction falls with it, a drop of about 3 percentage points would add roughly 260 MWh of diesel energy, or about 75,000 litres at 0.29 litres per kWh, worth about USD 120,000 a year at USD 1.60. The point is the method: change one input at a time and see the cost.

Seasonal Pattern

Winter days are shorter, so solar fraction is lower and diesel use is higher than in summer. Plan fuel deliveries, generator maintenance and storage cycling around that pattern, and show the seasonal swing in the financial model instead of an annual average only.


Environmental Impact

The environmental effects of a hybrid come from burning less diesel, and they can be estimated with arithmetic.

CO2 Emissions Reduction

The US EPA’s GHG Emission Factors Hub (2025) lists diesel combustion at 10.21 kg CO2 per gallon, which is about 2.7 kg CO2 per litre. Applying it to the example:

Item Litres per year Tonnes CO2 per year
Diesel only 2,452,800 About 6,615
Hybrid 1,066,968 About 2,878
Avoided 1,385,832 About 3,738

The figures count combustion only. Battery manufacturing emissions, fuel transport and equipment embodied carbon are separate lines, so a full lifecycle assessment should include them. The factor comes from the US EPA GHG Emission Factors Hub.

Noise, Spill Risk and Water

Fewer generator hours reduce noise around the camp. Smaller annual fuel throughput means fewer tanker deliveries and less fuel transfer, which are the activities most associated with spills. Generators that run less also use less cooling-circuit makeup water. None of these is quantified here, so measure them at your site if they matter for permitting or community relations.


Challenges: What the Atacama Throws at You

Every off-grid solar project faces challenges. The Atacama adds a few of its own.

Dust on Panels

Dust is the largest operating challenge. A cleaning plan usually combines several layers. Automated dry cleaning can remove loose dust between visits. Scheduled wet cleaning with demineralized water restores output. Anti-soiling coatings may reduce adhesion, though their durability needs checking. Evaluate each against the site’s water supply and labour cost, and test the cleaning interval in the financial model, since the optimum depends on how fast soiling accumulates.

UV Exposure

UV intensity is high at altitude in a dry, clear atmosphere. Polymer components, cable insulation, backsheets and seals can age faster, so specify UV-rated cables and enclosures and ask module suppliers for UV test data. Prefer metal conduit and trays where plastic would be exposed, and include a plan to inspect polymer parts during maintenance.

Battery Thermal Management

A battery container sees a wide daily ambient range. The cooling and heating systems consume power, which reduces net output, so include that auxiliary load in the energy balance. Ask the supplier what happens if the thermal system faults, how the container behaves on backup ventilation and what alarm limits trigger a shutdown.

Altitude Effects on Electronics

Check the supplier’s altitude derating for inverters, the oil cooling needs of transformers and the clearances for air-insulated switchgear. Specify equipment for a higher elevation than the site where possible, to leave margin.

Personnel and Remote Operations

Remote sites run with small crews, and specialists may need a flight and acclimatization time. Plan for remote monitoring, clear operator manuals and spare parts, so that most faults are solved without a site visit. Satellite links can provide connectivity where there is no terrestrial network.

Pro Tip: Make Remote Diagnostics a Contract Requirement

Ask each equipment supplier for remote diagnostic access and for written response times for fly-in support. A false alarm that needs a specialist visit costs far more than the connectivity and software that would have cleared it. Use predictive maintenance alerts where the platform supports them.


Chilean Mining and Energy Context

This example sits within a broader trend in which mines look to renewables for cost and emissions reasons. For the national context, check primary sources: the Chilean Copper Commission (Cochilco) publishes mining sector energy consumption studies, and Chile’s Ministry of Energy publishes the national energy statistics and renewable targets.

Policy Items to Check

Policy affects the case in several ways, so a feasibility study should check the current rules for each:

  • Renewable energy requirements for large consumers. Whether an off-grid mine can count on-site generation toward any requirement
  • Carbon pricing. Chile has a carbon tax on stationary sources, and the rate and scope can change, so check the current text
  • Grid access and PPAs. Mines near the grid may buy renewable energy through power purchase agreements, while remote mines generate their own
  • Corporate targets. Many mining companies publish emissions targets that influence project selection

The Grid Extension vs Hybrid Decision in Chile

Chilean mining regions have a distinctive geography: the main grid runs along the coast and the interior plateau is far from it. Compare, for each site, the cost of a line, a substation and the recurring charges, against the cost of a hybrid, using the structure from the overview section. Because distances and costs vary widely by site, the table below lists the questions to answer, not a price.

Question Why it matters
How far is the nearest transmission connection point? Sets line length and capital cost
What is the terrain and the concession status along the route? Drives permitting time and cost
What is the remaining reserve life? Sets the period over which costs are recovered
What is the delivered diesel price, and how volatile is it? Sets the fuel saving of a hybrid
What is the load shape and growth? Sets PV and battery sizing

Maintenance in Remote Locations

Maintenance for off-grid mining solar differs from a grid-tied commercial roof. A technician does not arrive in an hour, parts take days and downtime costs production.

Maintenance Organization

A common structure has three tiers. Tier 1 is on-site electrical technicians who do daily inspections, cleaning and basic fault clearing. Tier 2 is a specialist contractor who visits on a schedule for detailed electrical testing, thermal imaging, EMS updates, battery health checks and generator overhauls. Tier 3 is equipment manufacturer support, with remote diagnostics and fly-in specialists for major faults.

Example Preventive Maintenance Schedule

Task Frequency Responsible
Visual panel inspection Daily On-site technician
Automated cleaning system check Daily On-site technician
Inverter data review Daily Remote operator
String voltage measurement Weekly On-site technician
Module wet cleaning Monthly or as soiling data requires Contractor crew
Thermal imaging scan Monthly or quarterly Contractor
Battery capacity test Quarterly Contractor
Generator load bank test Quarterly Contractor
Inverter filter replacement Per manufacturer Contractor
Grounding resistance test Annually Contractor
Battery cell balancing and health review Annually Manufacturer specialist

This is a template, not a mandated schedule. Use the manufacturers’ maintenance manuals and your own soiling data to set the intervals.

Spare Parts Strategy

Hold spare parts on site for failures that would otherwise stop the plant for days. Choose them by lead time and criticality, not by price.

Item type Why hold it
PV modules Rock impact, hail or manufacturing defects
String fuses and connectors The most common electrical faults
Inverter power stages and control boards Long lead times and critical for operation
Battery management cards Often proprietary with long lead times
Battery thermal system components A common container fault
Generator controllers Critical for diesel backup

Ask the manufacturers for recommended spare lists and the lead times for each item, then price the inventory against the cost of downtime.

Water for Cleaning

Water is a constraint that does not go away. Wet cleaning consumes demineralized water that has to come from the mine’s supply, so schedule cleanings around process demand. Waterless options, including electrostatic dust repulsion and robotic dry cleaning, can reduce the water need, but they add capital cost and have their own maintenance, so compare them in your model.


Comparable Projects: Three Published Off-Grid Mining Solar Systems

Published projects show different approaches to the same problem. The figures below come from the linked reports, and sources differ in places, which is noted.

1. B2Gold Fekola Mine, Mali

At the Fekola gold mine, B2Gold commissioned a 30 MW solar plant with battery storage in 2021, according to MINING.COM. Commissioning reports give the battery as 15.4 MWh, while an earlier approval report gave 13.5 MWh. Reports describe savings of about 13.1 million litres of heavy fuel oil a year, with the plant replacing the power from three of six heavy fuel oil generators, and a project cost of USD 38 million. A later report says a second phase added 22 MW of solar and 12.7 MWh of battery, expected to supply roughly 30% of the site’s electricity demand.

2. DeGrussa Copper-Gold Mine, Australia

At DeGrussa in Western Australia, a 10.6 MW tracking solar plant was paired with a 6 MW battery and integrated with the mine’s existing diesel station. According to RenewEconomy and other reports, it supplied up to about 20% of the mine’s energy, offset about 5 million litres of diesel and abated more than 12,000 tonnes of CO2-equivalent a year. Battery energy capacity is reported variously as 1.4 to 1.8 MWh. The plant was decommissioned less than eight years after commissioning. The lesson for design is that a plant sized for a mine’s life can end when the mine does, so plan the asset’s second life or removal.

3. Essakane Gold Mine, Burkina Faso

At IAMGOLD’s Essakane mine, a 15 MWp solar plant was added to the existing heavy fuel oil plant and inaugurated in March 2018, per Mining Weekly. Reports cite fuel savings of about 6 million litres a year and CO2 reduction of nearly 18,500 tonnes, and Total Eren owns the plant under a 15-year power purchase agreement. It is a retrofit without batteries, which keeps cost and risk low but limits solar fraction.

Comparison Summary

Project Country Solar Battery Published saving or share What it shows
Fekola (2021, phase 1) Mali 30 MW 15.4 MWh reported About 13.1 million litres of fuel oil a year Large PV and battery on a large load
DeGrussa Australia 10.6 MW tracking 6 MW, 1.4 to 1.8 MWh reported About 5 million litres of diesel, up to about 20% of energy Tracking and storage at a remote mine, later decommissioned
Essakane (2018) Burkina Faso 15 MWp None About 6 million litres a year Retrofit on an existing fuel oil plant

The three projects achieve different solar fractions because the mines have different loads, storage and objectives. A high fraction at a mine with a flat 24-hour load requires storage sized for the night, as the design example shows, while retrofits on larger loads often use PV to cut fuel without storage.


Sizing Method: From Load Data to a Design Basis

A sizing study for a remote hybrid follows a repeatable sequence. Use it to replace the assumptions in this example.

  1. Collect a year of metered load data. Use 15-minute or hourly data for the whole site, split by process area. If metered data does not exist, build the profile from equipment lists and operating schedules, and flag it as an estimate.
  2. Establish the delivered diesel cost. Get the price from the supplier, with the breakdown of commodity, transport, storage and taxes, and check how contracts index it.
  3. Build the solar resource file. Use site-specific hourly data, ideally calibrated to a year of ground measurements. Add the soiling model and the temperature model.
  4. Run an hourly dispatch simulation. Include battery limits, generator minimum loading, reserve requirements and the EMS strategy. Compare PV sizes against battery sizes in a grid, and record fuel use, solar fraction, curtailment and cycling for each pair.
  5. Add the cost model. Price each option with quotes, then compute net annual saving, payback, NPV and IRR over the reserve life. Include battery replacement and degradation.
  6. Stress the result. Vary the fuel price, soiling, load and capital cost one at a time, then together. Pick the design that holds up across the range, not the one that is best in a single case.
  7. Write the design basis. Record every assumption with its source and date, so that suppliers and auditors work from the same inputs.

The output of the sequence is a short list of designs with their economics, and a clear view of the risks that could change the answer. The generation and financial tool can hold the cost side of this model, and your simulation tool handles the hourly dispatch.

Procurement and Contract Checklist

Remote projects often go wrong in the contract, not the design. Use this checklist when you write supply and construction agreements.

Topic What to put in writing
Performance guarantees Solar fraction or fuel saving, how it is measured, and the remedy if it is missed
Availability Required availability for critical loads, with the test method
Altitude and temperature Derating curves and rated operating ranges for the site
Soiling and cleaning Assumed soiling loss, cleaning method and who bears the cost of exceeding it
Battery warranty Capacity retention, cycle count, state-of-charge window and temperature conditions
Spares and response Spare parts list, lead times and fly-in response times
Remote access Diagnostic access, data ownership and cybersecurity requirements
Factory acceptance Tests to witness before shipping
End of life Responsibility for removal or relocation when the mine closes

Agree the measurement method for any guarantee before signing. A guarantee on solar fraction is only useful if everyone agrees how to measure the load and the solar energy delivered.

Lessons for Future Projects

These are design lessons from the example, supported by the arithmetic above and by the published projects.

1. Size the Battery for the Load Profile, Not as a Fixed Ratio to PV

For a flat 24-hour load, the battery decides how much of the night is covered. Test several sizes in an hourly simulation and compare the cost of each extra MWh with the diesel it displaces.

2. Invest in Soiling Control

Soiling can move the result by several percent. The sensitivity table shows that a few points of solar fraction change payback by about a year, so a cleaning system that protects output deserves a real budget.

3. Build Operator Confidence Before Commissioning

Operators who do not trust a new system run conservative limits, which gives up some of the saving. Use training, simulation and a digital twin where available, so that operators have practiced the edge cases before they run the plant.

4. Prefabricate and Factory-Test

Prefabricated containers and buildings reduce site labour and catch errors before shipment. Specify factory acceptance tests in the contract.

5. Plan for Load Growth and Asset Life

Size for the planned load, and decide what happens to the plant at the end of the mine’s life, as DeGrussa shows. Containerized equipment can often be relocated.

6. Treat Remote Monitoring as Essential

Remote diagnostics reduce the number of site visits and shorten faults. Specify the monitoring platform, the connectivity and the response times in the supply contracts.


Conclusion

Off-grid solar for mining is no longer experimental, and published projects in Mali, Australia and Burkina Faso show what has been built. The design example here shows how to test a hybrid for a remote Chilean mine: define the load, set the fuel price, size the PV and battery with an hourly simulation, and check the payback against the sensitivities.

In the example, a 4 MWp PV array, a 6 MWh battery and a 2.25 MW diesel plant cut fuel use by about 57% and give a simple payback of about 4.5 years at an assumed USD 1.60 per litre. The result is sensitive to the diesel price, the solar fraction and the capital cost, so a real project must replace each of those with data from the site and quotes from suppliers.

Three actions for mining operators considering off-grid solar:

  1. Build a load profile from metered data and size the battery for the night, not a ratio to PV
  2. Budget for dust control and test cleaning intervals in the financial model
  3. Agree the performance indicators, remote monitoring and operator training before commissioning

To run your own sizing and payback, use solar design software for yield and layout, solar shadow analysis software for site shading, and the generation and financial tool for the cost model, or book a SurgePV demo. Related reading: adding battery storage services.

Frequently Asked Questions

What is a solar-diesel hybrid system for mining?

A solar-diesel hybrid combines photovoltaic panels, battery storage and diesel generators to power a remote operation without a grid connection. Solar carries the daytime load, the battery covers part of the night, and diesel runs only when the other two cannot meet demand.

How much diesel can off-grid solar save at a mining site?

It depends on load, solar resource, battery size and fuel use. In the worked example here, a 1 MW average load with a 4 MWp array and 6 MWh battery cut diesel from about 2.45 million to about 1.07 million litres a year at an assumed 58% solar fraction.

What are the main challenges of solar in the Atacama Desert?

The main challenges are dust that cuts output between cleanings, high UV exposure, wide temperature swings, and altitude effects on cooling and insulation. Battery thermal management, water for cleaning and remote maintenance also matter, so each needs a plan and a cost line in the design.

What does a hybrid mining solar system cost?

Cost varies by supplier, logistics and timing, so use quotes. The worked example assumes USD 1.05 per Wp for the PV system, USD 380 per kWh for the battery and a remote logistics premium, giving about USD 9.4 million for 4 MWp, 6 MWh and a diesel plant already on site.

How does an energy management system control a hybrid mining microgrid?

An energy management system dispatches solar, battery and diesel in real time. It forecasts PV output, tracks battery state of charge and starts generators only when needed, while a load priority scheme protects critical equipment first. Many systems re-solve a mixed-integer optimization at a fixed interval.

What is solar fraction in off-grid mining?

Solar fraction is the share of total annual energy supplied by PV, directly or through storage, instead of diesel. The worked example assumes 58%. Higher fractions need more storage and load management, and they show diminishing returns because surplus midday PV is curtailed or lost in storage.

Is the Atacama a good place for solar?

The Atacama is among the highest-irradiance regions measured, with dry air and few cloudy days. Site yield still has to be measured or taken from a site-specific source such as the Global Solar Atlas, and dust, temperature and altitude all affect real output.

Where this fits

This article is part of SurgePV's Solar Incentives & Policy hub, which works through the topic from first principles to the decisions a project team actually has to make.

About the Contributors

Author
Akash Hirpara
Akash Hirpara

Co-Founder · SurgePV

Akash Hirpara is identified by SurgePV as a company co-founder. His SurgePV author page lists only role information that can be tied to the public profile below; education, certifications, project totals, financial results, speaking engagements, and media appearances are not asserted without retained evidence.

Editor
Nirav Dhanani
Nirav Dhanani

Co-Founder · SurgePV

Nirav Dhanani is identified by SurgePV as a company co-founder. His SurgePV author page lists only role information that can be tied to the public profile below; credentials, project totals, conversion results, and market-expansion claims are not asserted without retained evidence.

Get Solar Design Tips in Your Inbox

Join 2,000+ solar professionals. One email per week - no spam.

No spam · Unsubscribe anytime

Book Free Demo

Choose which optional technologies SurgePV may use. Essential storage remains active for security and requested features.