Back to Blog
solar policy22 min read

Floating Solar France 2026: Projects, Tenders, Permits

Floating solar in France: O'MEGA1, Lazer and Les Ilots Blandin, how floating projects bid in CRE tenders, permit steps, grid connection and design points.

Rainer Neumann

Written by

Rainer Neumann

Editorial contributor · SurgePV

Rainer Neumann

Edited by

Rainer Neumann

Editorial contributor · SurgePV

Published ·Updated

Answer

Floating solar in France is built on artificial water bodies such as gravel pit lakes and dam reservoirs. Notable plants include O'MEGA1 (17 MWc, 2019), EDF's Lazer (20 MWc, 2023) and Les Ilots Blandin (74.3 MWc, 2025). Floating plants have no dedicated tender category, so they compete in CRE ground-mount tenders.

France’s floating solar market has moved from one pioneer plant to a handful of large installations in six years. O’MEGA1 in Piolenc (Vaucluse) started operating in 2019, EDF commissioned Lazer on a hydroelectric dam in the Hautes-Alpes in June 2023, and Les Ilots Blandin in Haute-Marne was inaugurated in June 2025 at 74.3 MWc. There is no dedicated tender category for floating plants, so developers compete with ground-mount projects in the CRE (Commission de Regulation de l’Energie) tenders. See our guide on floating solar design for the technical side.

Last updated: November 2026

This guide covers the French floating solar market for developers, EPC contractors, and investors: the notable plants, how floating projects enter CRE tenders, the Loi APER framework, the permit steps to confirm, grid connection, financing examples, and French design challenges. Where the sources checked do not publish a number, this guide says so instead of estimating.

TL;DR: Floating Solar France 2026

Les Ilots Blandin (74.3 MWc, June 2025) is the largest French floating plant found in the sources checked. Floating plants compete with ground-mount projects in CRE tenders, where the 8th period selected 971 MWc. Loi APER (10 March 2023) set the acceleration framework, but its ministry summary does not mention floating solar. Cost and permit-duration benchmarks are not published, so rely on project-specific quotes and early authority contact.

In this guide:

  • Latest updates: Les Ilots Blandin, Lazer, and the CRE tender period results
  • The regulatory framework: Loi APER and what to confirm for water bodies
  • How floating projects enter CRE tenders
  • Notable French floating solar projects
  • Permit steps and authorities to confirm
  • Grid connection with ENEDIS and RTE
  • Financing and cost examples
  • Design challenges: mooring, wind, water levels, and electrical safety

Model a floating array before the site visit

Lay out and size a floating PV system in SurgePV, then compare yield and financial scenarios for your water body.

Book a Demo

No commitment required · 20 minutes · Checking cost first? See the SurgePV pricing page


Latest Updates: Floating Solar France 2026

The biggest recent milestone is the inauguration of Les Ilots Blandin on 20 June 2025, reported by pv magazine France (2025). The plant sits on basins formed by flooded former gravel pits at the Etablissements Blandin site in Perthes, Haute-Marne. Its 74.3 MWc comprises 72.3 MWc floating and 2 MWc ground-mounted.

Notable French Floating Plants: Status From Public Sources

Plant Location Capacity Owner or developer Date
O’MEGA1 Piolenc, Vaucluse 17 MWc, later extended to 22 MWc Akuo (built), floats by Ciel & Terre Operating since 2019, extension in summer 2022
Lazer Hautes-Alpes, on a hydroelectric dam 20 MWc EDF Commissioned June 2023
Les Ilots Blandin Perthes, Haute-Marne 74.3 MWc (72.3 floating) Q Energy, with Velto Renewables (50% acquired Q1 2025) Inaugurated 20 June 2025
Saint Eloi Romilly-sur-Seine, Aube 34.5 MWc Neoen Proposed in the CRE 8th period (2025)
Cheylas Isere Not stated in the source EDF Works planned for early 2026, commissioning targeted for 2027

Sources: pv magazine France (2025), Energie Partagee, Direct Mag, and pv magazine France (2025). Capacity figures differ across articles because of extensions, so verify against the owner’s current data.

Notable French floating solar plants by capacity (MWc) (MWc)
  • Les Ilots Blandin74.3 MWc (operating, 2025)
  • Saint Eloi34.5 MWc (proposed, CRE 8th period)
  • O'MEGA122 MWc (after 2022 extension)
  • Lazer20 MWc (operating, 2023)

Source: pv magazine France (2025), Direct Mag, and Energie Partagee; capacities as reported, checked November 2026.

Key Market Changes Since 2023

June 2023: Lazer is commissioned. EDF commissioned Lazer, a 20 MWc floating plant on a hydroelectric dam in the Hautes-Alpes, reported by Direct Mag. It shows that dam reservoirs are part of the French floating market alongside gravel pit lakes.

June 2025: Les Ilots Blandin opens. The plant uses 134,541 DAS Solar modules of 550 Wc, tilted at 5 degrees, on six islands of between 8 and 17 MWc, per pv magazine France (2025). Ciel & Terre supplied about 230,000 recyclable HDPE floats. Q Energy financed the project in September 2024 with a raise of more than 50 million euro arranged by Credit Agricole Transitions & Energies and Bpifrance.

September 2025: CRE 8th ground-mount period. The 8th period of the PPE2 ground-mount tender selected 165 projects and 971 MWc against 925 MWc called, at an average 79.48 euro per MWh, per pv magazine France (2025). The largest proposed project was the 34.5 MWc Saint Eloi floating plant. The 9th period was set to close on 12 December 2025, and CRE recommended raising the eligibility threshold from 0.5 to 1 MWc.

Key Takeaway

Floating plants in France now compete head to head with ground-mount projects on price, since they have no tender category of their own. Check the current CRE specification and period dates before you plan a bid.


The French Floating Solar Regulatory Framework

Loi APER 2023: What It Set Up

Loi APER is the renewable energy acceleration law promulgated on 10 March 2023. According to the French Ministry of Ecological Transition, it rests on four axes: plan renewable deployment with local elected officials, simplify authorization procedures, use already artificialized land for renewables, and share project value with host territories. Local officials define acceleration zones, and the law aims to halve instruction times and make projects more secure against legal challenges.

The ministry summary does not mention floating solar, agrivoltaics, or water bodies. That is a reminder to treat floating projects under the general framework and check, project by project, how the commune’s acceleration zones and local planning rules apply.

No Dedicated Floating Statute Identified

None of the sources checked for this update describe a standalone floating-solar statute. In practice a floating plant needs the same families of approvals as other generation projects, plus the rules that apply to work on or over water. Confirm the exact list with the DDT(M), the DREAL, and the owner or manager of the water body before you commit to a timeline.

Water Body Status Drives the Route

The legal status and owner of the water body shape the process more than the size of the project:

  • Private artificial water bodies, such as former gravel pit lakes, are the setting for O’MEGA1 and Les Ilots Blandin.
  • Dam reservoirs run by a hydropower operator, as in the Lazer project, need the operator’s agreement as a first step.
  • Public waterways and navigable canals involve the authority that manages them.
  • Natural water bodies and sensitive habitats raise the toughest environmental questions.

Ask the authorities for a written view on the water body’s status before signing a site agreement.


How Floating Projects Enter CRE Tenders

Floating Plants Compete in the Ground-Mount Tender

pv magazine France (2025) states that floating plants have no dedicated tender category and compete in CRE tenders with ground-mounted solar projects. The Saint Eloi floating plant appeared as the largest proposed project in the 8th period of the PPE2 ground-mount tender, per pv magazine France (2025).

What the Latest Period Tells You

Metric (8th period, 2025) Value
Projects selected 165
Capacity awarded 971 MWc, against 925 MWc called
Average price 79.48 euro per MWh
Average project size 5.9 MWc
Largest proposed project 34.5 MWc Saint Eloi floating plant (Neoen)

Source: pv magazine France (2025).

The average price is the number to benchmark against. A floating project carries float, mooring, and electrical costs that a ground-mount project does not, so check that your all-in cost fits under the tender’s price range before you spend on development.

Preparing a Bid

The steps below are generic good practice. The CRE cahier des charges for the active period is the authority on eligibility, documents, and deadlines.

  1. Read the specification for the current period, including thresholds, caps, and required documents.
  2. Secure site control and a view from the water body owner.
  3. Request grid connection studies early, because the connection path and cost shape the bid price.
  4. Build a defensible yield estimate. A generation and financial tool helps you test yield and price scenarios.
  5. Price the float, mooring, and electrical scope from supplier quotes.

Pro Tip

Run the bid model against the previous period’s average price of 79.48 euro per MWh, then stress it 5 to 10 percent lower. If the project only works at the top of the price range, rework the design or the site before you invest in permits.


Notable French Floating Solar Projects

O’MEGA1, Piolenc (Akuo)

O’MEGA1 is the first French floating plant of scale. Energie Partagee reports 17 MWc on an artificial lake in a former quarry near Piolenc, with 47,000 panels over about 17 hectares and operation since 2019. Akuo built the plant using floating technology from Ciel & Terre. The investment budget was 17.3 million euro, and annual production is 23,600 MWh. Other outlets report an extension to 22 MWc in summer 2022.

Energie Partagee holds 20% of the project company’s capital through a 534,664 euro investment, a citizen investment group holds 17%, and the commune of Piolenc holds 6%. The commune also receives an annual rent as the lake’s owner. The project shows how local shareholding can sit alongside a commercial developer.

Lazer, Hautes-Alpes (EDF)

EDF’s Lazer plant sits on a hydroelectric dam in the Hautes-Alpes. Direct Mag reports 20 MWc with more than 50,000 panels, commissioned in June 2023. The same article says EDF’s Cheylas project in Isere has works planned to start in early 2026, with commissioning targeted for 2027. Capacity for Cheylas is not stated there.

Les Ilots Blandin, Haute-Marne (Q Energy)

Les Ilots Blandin is the largest French floating plant in the sources checked. pv magazine France (2025) reports 74.3 MWc, built on basins formed by flooded former gravel pits. The site covers 127 hectares, and about 45.5 hectares carry floating panels. Ciel & Terre supplied the floats and handled anchoring and module installation on the floating structures. Perpetum handled inverters, delivery and transformer stations, and the ground-mounted part, and Solutions30 managed cabling, grid connection, and commissioning.

Saint Eloi, Romilly-sur-Seine (Neoen)

The Saint Eloi floating plant at Romilly-sur-Seine (Aube) was the largest project proposed in the CRE 8th ground-mount period, at 34.5 MWc, per pv magazine France (2025). Check the project’s current status before citing it as built.

Key Takeaway: Project Scale

The French plants found range from 17 MWc to 74.3 MWc and sit mainly on gravel pit lakes and dam reservoirs. Water body size, owner agreement, and grid capacity set the practical limit, not the technology.


Permit Steps and Authorities to Confirm

No source checked publishes a standard French permit timeline for floating solar, so this section lists steps and authorities to confirm rather than durations. Treat each as a question for the DDT(M), the DREAL, and the water body owner.

Typical Approval Families

Step Question to answer Who to ask
Planning permission Which permit applies and what instruction path? Commune and DDT(M)
Environmental assessment What level of environmental review applies to the site? DREAL and the prefecture
Water law What declaration or authorization applies to works on a water body? DDT(M) and the water agency
Protected areas Does the site or its surroundings touch Natura 2000 or protected species areas? DREAL
Owner or manager agreement Who owns the water body and what terms apply? Water body owner, dam operator, or waterway manager
Local acceptance How will residents, anglers, and users be consulted? Commune and local associations

Consultation Takes Time

Les Ilots Blandin was designed more than two years before its inauguration, according to pv magazine France (2025). That is one reference point, not a benchmark, since site conditions vary widely. Start consultation with the commune and neighbors early, and run environmental surveys in parallel with grid studies.

Environmental Questions to Expect

Authorities and stakeholders typically ask about water quality, aquatic habitat, birdlife, and the share of the water surface covered. Direct Mag notes that the impact on aquatic ecosystems should remain a decisive criterion in reviewing future projects. No source checked gives a regulatory ceiling on coverage, so agree the coverage ratio with the authorities and support it with studies.

Pro Tip: Classify the Water Body First

Before you sign a site option, get the water body’s legal status and owner in writing, and ask the DREAL which environmental assessment level it expects. A wrong assumption here can cost a development cycle.


Grid Connection: ENEDIS and RTE

Two Network Operators

French floating projects connect to one of two operators. ENEDIS manages the distribution network, and RTE manages the high-voltage transmission network. The right one depends on the project’s size and the available capacity near the site. Ask both for guidance early, since the connection voltage shapes cost and schedule.

The Connection Proposal

The operator answers a connection request with a technical and financial proposal (PTF, proposition technique et financiere). It sets the connection point, the reinforcement works required, the cost split, and the schedule for network works. Proposal validity and response times are set by the operator’s procedures, so request the current rules in writing.

Regional Capacity Reservation

France plans connection capacity for renewables through regional schemes (S3REnR). Check the capacity reserved near your site and whether works are planned. A site that looks good on irradiance can still stall on connection capacity.

Pro Tip: Grid Check Before Land

Look at published capacity maps and request a preliminary connection view before you commit to a site. A saturated substation can change project economics before development costs are spent.


Financing and Cost Examples

Cost: What Is Published

No source checked publishes a current French benchmark for floating solar cost per watt, so avoid quoting one. One concrete data point is O’MEGA1. Energie Partagee reports an investment budget of 17.3 million euro for 17 MWc, about 1.02 euro per Wp before the 2022 extension. That is a 2019 project budget, so use it as history, not a quote.

Item O’MEGA1 data point
Capacity 17 MWc
Investment budget 17.3 million euro
Implied cost About 1.02 euro per Wp (arithmetic from the two figures)
Annual production 23,600 MWh

Costs for new plants depend on the float system, mooring, water depth, level variation, cable runs, and connection distance. Collect supplier quotes for each.

Financing Examples

Les Ilots Blandin’s financing is a useful reference. pv magazine France (2025) reports that Q Energy financed the project in September 2024 with a raise of more than 50 million euro arranged by Credit Agricole Transitions & Energies and Bpifrance. O’MEGA1 shows a different structure, with a citizen investment group, a citizen investment fund, and the commune as shareholders alongside Akuo.

A typical financing case rests on a long-term revenue contract or a tender award. A power purchase agreement is one alternative route where a corporate buyer is available. Lenders will ask for yield studies, supplier warranties, and grid connection certainty.

Revenue Modeling

Floating solar produces mostly at midday, like other solar, so exposure to low midday prices matters for any contract that tracks market prices. Model price scenarios and consider storage where the tender or contract rewards it. A solar proposal tool can present the scenarios to investors.


Design Challenges for French Floating Solar

Mooring and Water Level Variation

The mooring system keeps the array in place while the water level, wind, and waves change. Reservoirs and dam lakes can have large level swings, while gravel pit lakes are usually steadier. Design the mooring for the actual level range and the soil or bank conditions, and agree anchor types with the authorities, since anchors can disturb the lake floor.

Wind and Structural Design

Floating arrays need structural calculations for wind loading, and French projects use the Eurocode framework for wind actions. Windy corridors such as the Rhone Valley need extra attention. The float supplier’s test data and an independent review help lenders and insurers accept the design.

Float Systems and Standards

No single national standard for floating solar floats was identified in the sources checked. DNV-ST-0584 is a widely used reference for floating solar design, and project teams typically ask suppliers how their systems align with it. Les Ilots Blandin used about 230,000 recyclable HDPE floats, per pv magazine France (2025).

Electrical Safety on Water

Floating arrays need cable management that tolerates movement, protection for connectors and junction boxes against moisture, and careful bonding and grounding. Ask the electrical designer which standards apply to the installation and have the design reviewed by the responsible engineer. Outputs from design software support documentation and do not replace that approval.

Yield and Water Surface Effects

Water cooling and surface reflection can change yield compared with a land array, but measured gains vary by site, module, and float design. Model the project with measured weather data and avoid assuming a fixed premium. Bifacial modules add another variable, since rear-side gain depends on water surface reflectance and tilt. See albedo for the basics.

Operations and Maintenance

Plan for boat access, cleaning, inspection of floats and moorings, and biofouling or bird droppings. Les Ilots Blandin’s low 5-degree tilt, as pv magazine France (2025) reports, is one design choice that reduces wind loading on the floating structures.

Compare floating and ground-mount layouts

Test layouts and yield for a water body or a ground site in SurgePV, and see which fits a tender price.

Book a Demo

No commitment required · 20 minutes · Prefer numbers first? Read the SurgePV pricing page


Site Screening Checklist for French Floating Projects

A short screening list saves months before you spend on surveys. Score each candidate water body against the questions below, then keep only the sites with no unresolved blocker.

Criterion Why it matters Question to answer
Water body status Sets the approvals and who must agree Is it artificial, private, public, or managed by a dam operator?
Owner and lease terms Controls site control and revenue sharing Who owns it, and will they sign a long lease?
Water level range Drives mooring design and cable length What are the seasonal and operational level swings?
Bank and bed conditions Affects anchoring and access What are the soil, bank slope, and depth?
Environmental sensitivity Determines survey scope and consultation Are there protected species, Natura 2000 areas, or fishing and recreation uses?
Coverage ratio Shapes water quality and habitat impacts What share of the surface will the array cover, and what do studies support?
Grid distance and capacity Sets connection cost and timing How far is the nearest substation, and is capacity reserved?
Access for construction Affects float assembly and launch Can trucks and cranes reach a launch area?
Local acceptance Reduces opposition risk Who uses the water, and how will they be consulted?

Investor Due Diligence

Lenders and investors usually ask for the same core documents:

  • Independent yield estimate using measured or modelled weather data
  • Float, mooring, and electrical design review by an independent engineer
  • Supplier warranties and track record for floats and anchoring
  • Permit status, appeal exposure, and the water body agreement
  • Grid connection proposal and schedule for network works
  • Environmental monitoring plan and mitigation commitments
  • Insurance quotes for construction and operation

Community and Stakeholder Engagement

O’MEGA1 shows one engagement model. Citizens and the commune hold shares alongside the developer, and the commune receives rent as owner of the lake, according to Energie Partagee. Whatever model you choose, plan engagement before the permit file is lodged, and explain what changes on the water for anglers, boaters, and neighbors.

Outlook for Floating Solar in France

The CRE tender continues to run in periods. The 9th period was set to close on 12 December 2025, with 925 MWc called, per pv magazine France (2025). Larger, well-sited projects such as Les Ilots Blandin and Saint Eloi show where the market is heading: bigger floating plants on artificial water bodies, competing on price with ground-mount solar. We found no official national target for floating capacity in the sources checked, so avoid quoting one.

For developers, the practical outlook is to prepare a cost-competitive design, secure the water body early, and get grid and authority views in parallel. For other French support schemes, see France feed-in tariffs, and for agrivoltaic options, see the agricultural solar case study in France.


Conclusion

French floating solar is real and growing, with plants from 17 MWc to 74.3 MWc on gravel pit lakes and dam reservoirs. The market has no dedicated tender, so floating projects win or lose on price against ground-mount solar. The work that separates good projects is early: water body status, authority consultation, grid capacity, and a design that fits the tender price. To model a floating project, book a SurgePV demo.


Frequently Asked Questions

Yes, and several large plants already operate, including O’MEGA1 in Piolenc and Les Ilots Blandin in Haute-Marne. The sources checked identify no dedicated floating-solar statute, so projects go through the standard permit, environmental, and water-law procedures. Confirm the route for your water body with the DDT(M), DREAL, and the water body owner.

What is the largest floating solar farm in France?

Les Ilots Blandin in Perthes, Haute-Marne, is the largest, at 74.3 MWc, of which 72.3 MWc is floating and 2 MWc is ground-mounted. It was inaugurated on 20 June 2025, according to pv magazine France. Q Energy developed it, and Velto Renewables acquired 50% in the first quarter of 2025.

How do floating solar projects win CRE tenders in France?

Floating plants have no dedicated tender category and compete with ground-mounted projects in the CRE PPE2 ground-mount tender, according to pv magazine France. The 8th period selected 165 projects and 971 MWc at an average 79.48 euro per MWh, and the largest proposed project was the 34.5 MWc Saint Eloi floating plant at Romilly-sur-Seine.

What is Loi APER and how does it affect floating solar?

Loi APER is the renewable energy acceleration law promulgated on 10 March 2023. It rests on four axes: planning with local officials, simpler authorizations, using already artificialized land, and sharing value with host territories. Communes define acceleration zones. The ministry page does not mention floating solar, so check how your site is treated.

How much does a floating solar plant cost in France?

No current French cost benchmark was found in the sources checked. For one data point, Energie Partagee reports a 17.3 million euro investment budget for the 17 MWc O’MEGA1 plant, about 1.02 euro per Wp before its 2022 extension. Costs vary with water body, mooring, floats, and grid distance, so use developer quotes.

How long does permitting take for a floating solar project in France?

No official timeline was found. Permit duration depends on the water body’s status, owner, environmental sensitivity, and local opposition. As a reference, pv magazine France says Les Ilots Blandin was designed more than two years before its June 2025 inauguration. Plan early consultations and grid studies in parallel.

Who builds and develops floating solar in France?

Akuo built O’MEGA1 with floating technology from Ciel & Terre, EDF operates Lazer in the Hautes-Alpes, and Q Energy developed Les Ilots Blandin, where Ciel & Terre supplied about 230,000 floats. Neoen’s Saint Eloi plant appeared in the 8th CRE ground-mount tender period. Developer lineups change, so check current project announcements.

Where this fits

This article is part of SurgePV's Solar Incentives & Policy hub, which works through the topic from first principles to the decisions a project team actually has to make.

About the Contributors

Author
Rainer Neumann
Rainer Neumann

Editorial contributor · SurgePV

Rainer Neumann is credited as an editorial contributor on SurgePV content. This profile does not assert engineering credentials, project totals, software-testing experience, education, speaking engagements, or media citations because independent verification evidence is not retained in the publication record.

Editor
Rainer Neumann
Rainer Neumann

Editorial contributor · SurgePV

Rainer Neumann is credited as an editorial contributor on SurgePV content. This profile does not assert engineering credentials, project totals, software-testing experience, education, speaking engagements, or media citations because independent verification evidence is not retained in the publication record.

Get Solar Design Tips in Your Inbox

Join 2,000+ solar professionals. One email per week - no spam.

No spam · Unsubscribe anytime

Book Free Demo

Choose which optional technologies SurgePV may use. Essential storage remains active for security and requested features.