🇲🇾 Malaysia Regulatory Guide 8 min read

Sabah & Labuan Solar Guide 2026: SESB Net Metering & Connection

Complete guide to solar installations in Sabah and Labuan under SESB — net metering scheme, connection requirements, and regional specifics.

Nirav Dhanani

Written by

Nirav Dhanani

Co-Founder · SurgePV

Rainer Neumann

Reviewed by

Rainer Neumann

Content Head · SurgePV

Published ·Last reviewed ·Regulator: SESB / EC

Sabah and Labuan operate under Sabah Electricity Sdn Bhd (SESB), a separate utility from Peninsular Malaysia’s TNB and Sarawak’s SEB. Solar installers working in Sabah must understand that SEDA’s NEM 3.0 portal does not apply here. SESB runs its own net metering scheme with its own application process, size caps, and technical requirements. This guide covers what SESB requires and how the Sabah solar process differs from Peninsular Malaysia.

Governing Legislation
Electricity Supply Act 1990 (Act 447); Electricity Regulations 1994
NEM Scheme
SESB Net Metering — separate from SEDA NEM 3.0
Application Portal
SESB Commercial Services / Regional SESB office
SEDA Approval
Not required — SESB operates independently of SEDA
Residential Cap
Typically 12 kWp (confirm with SESB)
Non-Domestic Cap
Typically 75% of Maximum Demand (confirm with SESB)
Applicable Region
Sabah and the Federal Territory of Labuan
Last Updated
May 2026

Do Not Submit SEDA NEM Applications for Sabah or Labuan

Applications submitted via nem.seda.gov.my for premises in Sabah or Labuan will be rejected. SEDA’s NEM 3.0 scheme applies only to Peninsular Malaysia under TNB’s network. Sabah and Labuan customers must apply directly to SESB. Contractors who submit SEDA applications for SESB territory waste weeks and damage client relationships.

Malaysia’s Three Solar Jurisdictions

Malaysia has three separate electricity utilities, each with its own solar connection process:

RegionUtilityNEM Application RouteLegislation
Peninsular MalaysiaTNBSEDA NEM 3.0 via nem.seda.gov.myElectricity Supply Act 1990 (Federal)
SarawakSEBSEB’s own NEM schemeSarawak Electricity Ordinance 2012 (State)
Sabah & LabuanSESBSESB Net Metering (direct to SESB)Electricity Supply Act 1990 (Federal)

Sabah and Labuan are federally governed under the Electricity Supply Act 1990 — the same legislation as Peninsular Malaysia. However, SESB operates as an independent utility with its own distribution network, tariff structure, and solar connection procedures. The federal legislation means equipment standards and general electrical regulations align with Peninsular Malaysia, but the application process is utility-specific.

SESB Net Metering Scheme

How SESB Net Metering Works

SESB’s net metering scheme follows the same conceptual model as NEM 3.0: a bi-directional meter records import and export, and exported kWh are credited against imported kWh. The specific credit rate, rollover rules, and administrative details are set by SESB and may differ from Peninsular Malaysia’s 1:1 offset.

Installers must confirm the following with SESB before project design:

ParameterWhere to Confirm
Export credit rate (RM/kWh or ratio)SESB Commercial Services
Residential system size capSESB Commercial Services
Non-domestic system size capSESB Commercial Services
Credit rollover periodSESB terms and conditions
Application processing timelineSESB Commercial Services
Required documentationSESB application form

SESB Electricity Tariffs

SESB sets its own electricity tariffs for Sabah and Labuan, separate from TNB’s Peninsular Malaysia tariffs. SESB’s generation mix includes thermal power plants and some renewable energy, and tariffs reflect the cost structure of Sabah’s isolated grid.

Customer CategoryNotes
DomesticTiered tariff structure; confirm current rates with SESB
CommercialTypically higher than domestic; demand charges may apply
IndustrialSpecial industrial tariffs available for large consumers

Financial modelling implication: Use SESB’s actual tariff schedule (available from SESB or from the customer’s SESB bill) for Sabah solar financial models. Do not apply TNB Peninsular Malaysia tariff rates — they will produce incorrect savings and payback calculations.

Key Takeaway

Sabah’s electricity tariffs and grid characteristics differ from Peninsular Malaysia. Solar financial models for Sabah must use SESB-specific tariffs and account for any grid stability considerations that may affect SESB’s technical assessment.

SESB Application Process

Step 1 — Confirm SESB Territory

Verify the installation address is served by SESB. Sabah and Labuan are the only SESB territories. If the address is in Peninsular Malaysia, the application goes to TNB/SEDA. If in Sarawak, it goes to SEB.

Step 2 — Obtain Current SESB Terms

Contact SESB Commercial Services before starting design. SESB’s net metering terms — size caps, credit rates, and processing timelines — may change. Do not assume they match Peninsular NEM 3.0 parameters.

Step 3 — Prepare Documentation

SESB’s documentation requirements are broadly similar to TNB’s but confirm the exact list with SESB:

DocumentTypical Requirement
PE-stamped SLDMandatory — BEM-registered PE
Inverter datasheetMust be on Energy Commission approved list
Solar panel datasheetIEC 61215 / IEC 61730 certified
Contractor registrationEnergy Commission licence for Sabah
Customer SESB account detailsAccount number and supply address
System capacity and design summarykWp, expected annual generation

Step 4 — Submit to SESB

Submit the application to SESB’s Commercial Services division via their current application channel (portal, email, or regional office). Obtain an application reference number for tracking.

Step 5 — SESB Technical Assessment

SESB reviews the application and may issue a technical assessment with additional requirements. Common considerations for Sabah:

  • Grid stability at the connection point (Sabah’s grid is smaller and more isolated than Peninsular Malaysia’s)
  • Protection relay requirements for larger systems
  • Metering arrangement and bi-directional meter specifications

Step 6 — Installation and Inspection

After SESB connection approval:

  1. Install the solar system per the approved SLD
  2. Commission the system and test all protection functions
  3. Book SESB site inspection

During inspection, SESB verifies:

  • Installed capacity matches approved design
  • Inverter model and settings match documentation
  • Anti-islanding function operates correctly
  • Metering arrangement is correct
  • Protection devices are installed and functional
  • Earthing and labelling comply with regulations

Step 7 — Meter Installation and Billing

After a passing inspection, SESB installs the bi-directional net metering meter. Net metering billing begins in the following billing cycle.

Technical Requirements for Solar in Sabah

Inverter Requirements

Inverters must comply with the same Malaysian standards as Peninsular Malaysia:

  • MS IEC 62109-1 (safety) and MS IEC 62109-2 (grid requirements)
  • Anti-islanding protection per IEC 62116 (disconnect within 2 seconds)
  • Voltage protection: disconnect outside 196V–253V (230V nominal)
  • Frequency protection: disconnect outside 47.5–52.0 Hz

Confirm with SESB whether the Energy Commission’s approved equipment list for Peninsular Malaysia is accepted in Sabah, or whether SESB maintains its own approved list.

Protection Relay Requirements

For larger commercial systems, SESB may require a dedicated protection relay at the point of connection. The specific requirements — relay type, settings, and interface — are determined during SESB’s technical assessment. Confirm these requirements before designing the protection scheme.

PE-Stamped SLD

All grid-connected solar applications in Sabah require a Single-Line Diagram stamped by a Professional Engineer registered with the Board of Engineers Malaysia (BEM). The SLD must show:

  • Solar array configuration (strings, panels per string, total kWp)
  • DC and AC protection devices
  • Inverter specifications and protection functions
  • Metering arrangement (bi-directional meter location)
  • Connection to SESB distribution network
  • Earthing and bonding arrangement

Electrical Contractor Licensing

Electrical work on grid-connected solar installations in Sabah must be performed by contractors licensed under the Energy Commission’s framework. Confirm with SESB whether Peninsular Malaysia ST licences are recognised in Sabah, or whether additional Sabah-specific registration is required.

Sabah Solar Market Context

Grid Characteristics

Sabah’s electricity grid is smaller and more isolated than Peninsular Malaysia’s integrated TNB network. Key characteristics:

  • Generation mix: primarily thermal (natural gas and diesel) with increasing renewable energy
  • Grid stability: smaller grid means voltage and frequency fluctuations may be more pronounced
  • Rural electrification: significant off-grid and mini-grid solar deployment in rural Sabah

These characteristics mean SESB’s technical assessment may place greater emphasis on grid impact studies for larger systems than TNB does in Peninsular Malaysia.

Solar Irradiance in Sabah

Sabah’s solar irradiance is comparable to Peninsular Malaysia:

LocationApproximate PSH/DayAnnual kWh/kWp
Kota Kinabalu4.5–5.01,400–1,550
Sandakan4.5–5.01,400–1,550
Tawau4.5–5.51,400–1,600
Labuan4.5–5.01,400–1,550

Use site-specific irradiance data for financial modelling rather than Peninsular Malaysia averages.

Rural and Off-Grid Solar

Rural Sabah has a significant off-grid solar market. Off-grid systems in rural areas are not subject to SESB’s net metering or grid connection requirements. Government and NGO-funded rural electrification programmes have their own procurement and technical standards.

Design Solar Systems for Sabah with Local Irradiance Data

SurgePV supports Malaysian irradiance datasets including Sabah and Labuan locations — producing yield estimates and financial models using site-specific data rather than Peninsular averages.

See Financial Modelling

No commitment required · 20 minutes · Live project walkthrough

Common Issues for Solar in Sabah

IssueCauseResolution
Application submitted to wrong authorityContractor assumed SEDA NEM 3.0 appliesConfirm utility: SESB for Sabah/Labuan, TNB for Peninsular, SEB for Sarawak
Financial model uses wrong tariffApplied TNB Peninsular rates to SESB customerObtain current SESB tariff schedule; use actual customer bill
PE stamp not acceptedPE not registered with BEMEnsure PE holds valid BEM registration; confirm SESB accepts BEM registration
Grid impact study requiredLarge system on weak grid pointEngage PE to prepare grid impact study; submit with SESB application
Contractor licence questionedHolds Peninsular ST licence onlyConfirm with SESB whether additional Sabah registration is needed
Equipment not on approved listSpecified inverter not recognised by SESBCheck SESB/EC approved equipment list before specifying

Key Contacts for Solar in Sabah

AuthorityRoleContact Point
SESB Commercial ServicesNet metering applications, grid connectionsesb.com.my
Suruhanjaya Tenaga (ST)Equipment standards, contractor licensingst.gov.my
Board of Engineers Malaysia (BEM)PE registration verificationbem.org.my

Use solar design software that models Malaysian irradiance data including Sabah locations to produce accurate solar proposals for SESB territory.

Frequently Asked Questions

Can a Peninsular Malaysia solar contractor install systems in Sabah? A contractor licensed under Peninsular Malaysia’s ST Electrical Contractor framework may need additional registration or confirmation from SESB before carrying out work in Sabah. While the Electricity Supply Act 1990 is federal law, SESB may have specific contractor registration requirements. Contact SESB Commercial Services to confirm licensing requirements before accepting Sabah projects.

Does SESB offer a self-consumption (SELCO) option like TNB? SESB may offer a self-consumption-only option for facilities that do not want to export to the grid. Contact SESB directly to confirm whether a SELCO-type pathway exists and what the application process entails. The technical requirements — zero-export configuration, export limitation function — would be similar to Peninsular Malaysia’s SELCO requirements.

What is the solar market like in rural Sabah? Rural Sabah has significant off-grid and mini-grid solar deployment, often through government rural electrification programmes. These systems are not subject to SESB net metering requirements because they are not grid-connected. Installers working on rural electrification projects should confirm compliance requirements with the programme administrator.

Are there tax incentives for solar in Sabah? Malaysia’s federal tax incentives — GITA (Green Investment Tax Allowance) and GITE (Green Income Tax Exemption) — apply nationwide, including Sabah. Applications are submitted to MIDA (Malaysian Investment Development Authority) regardless of location. See the Malaysia Solar Tax Incentives guide for details.

How does Labuan differ from Sabah for solar installations? Labuan is a federal territory served by SESB. The electricity supply and solar connection process for Labuan follows SESB’s procedures. There is no separate utility for Labuan. Contractors should treat Labuan the same as Sabah for application purposes — submit to SESB, not SEDA or TNB.

About the Contributors

Author
Nirav Dhanani
Nirav Dhanani

Co-Founder · SurgePV

Nirav Dhanani is Co-Founder of SurgePV and Chief Marketing Officer at Heaven Green Energy Limited, where he oversees marketing, customer success, and strategic partnerships for a 1+ GW solar portfolio. With 10+ years in commercial solar project development, he has been directly involved in 300+ commercial and industrial installations and led market expansion into five new regions, improving win rates from 18% to 31%.

Editor
Rainer Neumann
Rainer Neumann

Content Head · SurgePV

Rainer Neumann is Content Head at SurgePV and a solar PV engineer with 10+ years of experience designing commercial and utility-scale systems across Europe and MENA. He has delivered 500+ installations, tested 15+ solar design software platforms firsthand, and specialises in shading analysis, string sizing, and international electrical code compliance.

SESBSabah solarLabuan solarBorneo solar

Solar Compliance Updates in Your Inbox

Join 2,000+ solar professionals. Regulatory changes, code updates, and design tips — weekly.

No spam · Unsubscribe anytime