🇲🇾 Malaysia Regulatory Guide 9 min read

Malaysia LSS (Large-Scale Solar) Tender 2026: Competitive Bidding Guide

Complete guide to Malaysia's Large-Scale Solar (LSS) competitive tender program — eligibility, bidding process, PPA terms, and compliance for projects above 1 MW.

Nirav Dhanani

Written by

Nirav Dhanani

Co-Founder · SurgePV

Rainer Neumann

Reviewed by

Rainer Neumann

Content Head · SurgePV

Published ·Last reviewed ·Regulator: Suruhanjaya Tenaga (ST) / Energy Commission

Malaysia’s Large-Scale Solar (LSS) program is the primary route for developers to build utility-scale solar farms and sell power to Tenaga Nasional Berhad (TNB) under a long-term Power Purchase Agreement. Unlike NEM 3.0 — which serves self-consumption customers — LSS is a competitive tender where developers bid on price. The lowest viable bids win. This guide covers the LSS program structure, tender history, eligibility, bid preparation, PPA terms, and the full project timeline from announcement to energisation.

Program
Large-Scale Solar (LSS) Competitive Tender
Minimum Project Size
1 MW (varies by tender round)
PPA Term
21 years (fixed tariff, no escalation)
Tariff Type
Competitive bid — lowest viable tariff wins
Applicable Region
Peninsular Malaysia (TNB network)
Governing Legislation
Electricity Supply Act 1990 (Act 447); Renewable Energy Act 2011 (Act 725)
Last Updated
May 2026

LSS Is Not a Self-Consumption Scheme

LSS is designed for independent power producers selling electricity to TNB — not for factories or commercial buildings that want to reduce their own electricity bill. If you are a C&I buyer seeking solar for self-consumption, use NEM 3.0 or SELCO instead. LSS requires a generation licence, competitive bidding, and a 21-year PPA commitment. The regulatory complexity and capital requirement are an order of magnitude higher than rooftop NEM.

What Is the LSS Program?

The Large-Scale Solar (LSS) program was introduced by the Malaysian government to diversify the national energy mix and meet renewable energy targets under the Malaysia Renewable Energy Roadmap. LSS projects are ground-mounted or large rooftop solar farms that generate electricity for sale into the TNB grid — not for on-site consumption.

Key characteristics of LSS:

  • Competitive bidding: Developers submit sealed bids with a proposed tariff (RM/kWh). The Energy Commission evaluates bids on price and technical merit.
  • Fixed PPA price: The winning bid tariff is locked for 21 years with no escalation clause.
  • TNB offtake: TNB purchases all generated electricity at the bid tariff under a standard-form PPA.
  • Grid connection: Projects must connect to TNB’s transmission or distribution network at a technically feasible point.
  • Development timeline: Winning bidders typically have 24–36 months from award to commercial operation date (COD).

LSS complements Malaysia’s other solar pathways:

PathwaySystem SizePurposeRevenue Model
NEM 3.0Domestic ≤12 kWp; Non-domestic ≤75% MDSelf-consumption with grid exportBill offset (1:1 credit)
SELCOAny size (within TNB limits)Self-consumption onlyBill offset (no export)
LSS>1 MW (tender-based)Utility-scale generation for grid salePPA revenue from TNB

LSS Tender Round History

Malaysia has run multiple LSS tender rounds since the program’s inception. Each round specifies the total capacity to be allocated, minimum project size, and any technology or location preferences.

Historical Tender Rounds

RoundYearCapacity AllocatedNotable Features
LSS 12016–2017500 MWFirst competitive solar tender in Malaysia
LSS 22017–2018563 MWIncreased competition; tariffs declined
LSS 32019–2020~1,000 MWLarger round; more stringent technical criteria
LSS 42021–2022~1,000 MWIncluded floating solar and agrivoltaic categories
LSS 52023–2024~2,000 MWLargest round to date; accelerated timeline

LSS tariffs have fallen sharply as competition intensified and technology costs declined:

PeriodTypical Winning Tariff Range
LSS 1 (2016)RM 0.28–0.39/kWh
LSS 2 (2017)RM 0.20–0.30/kWh
LSS 3 (2019)RM 0.18–0.25/kWh
LSS 4 (2021)RM 0.16–0.22/kWh
LSS 5 (2023–2024)RM 0.15–0.20/kWh

The downward trajectory reflects global module price declines, improved financing terms, and aggressive bidding by developers seeking market share. Bidders today must model costs precisely — margins are thin and underbidding can render a project unbankable.

Who Can Participate in LSS Tenders?

Eligibility Requirements

LSS tenders are open to companies and consortiums that meet the Energy Commission’s qualification criteria:

  • Malaysian-registered company: The bidding entity must be incorporated in Malaysia. Foreign companies may participate through joint ventures with Malaysian partners.
  • Technical capability: Demonstrated experience in solar project development, construction, or operation. The Energy Commission may require evidence of past projects or technical partnerships.
  • Financial capacity: Proof of financial strength — typically through audited financial statements, bank references, or letters of support from financial institutions.
  • Land control: Evidence of land access — either ownership, lease agreement, or letter of intent from the landowner. The land must have suitable solar resource and grid access.
  • Equity requirement: Bidders must commit a minimum equity contribution (typically 20–30% of project cost) and demonstrate the ability to raise debt financing for the remainder.

Consortium Bidding

Many LSS bids are submitted by consortiums that combine:

  • A local Malaysian partner (land access, regulatory knowledge, local relationships)
  • An international developer or EPC contractor (technical expertise, equipment procurement)
  • A financial investor (equity capital, project finance relationships)

The consortium agreement must define each party’s role, equity split, and decision-making authority. The Energy Commission evaluates the consortium’s combined capability as a single bidding entity.

The LSS Bidding Process

Step 1: Tender Announcement

The Energy Commission publishes a tender notice on st.gov.my specifying:

  • Total capacity to be allocated (MW)
  • Minimum and maximum project size per bid
  • Application deadline
  • Bid bond amount and format
  • Evaluation criteria (price weighting, technical score)
  • Any special categories (floating solar, agrivoltaic, BIPV)

Register on the Energy Commission website for email notifications of new tender rounds.

Step 2: Pre-Bid Preparation

Before submitting a bid, developers must:

  1. Secure land: Identify and secure land with suitable solar irradiance (4.5–5.5 PSH), flat or gently sloping terrain, and proximity to TNB grid infrastructure.
  2. Conduct feasibility study: Assess grid connection feasibility, environmental impact, and land use restrictions.
  3. Form bidding entity: Establish the Malaysian-registered company or consortium that will submit the bid.
  4. Arrange financing: Secure indicative financing terms from banks or financial institutions.
  5. Prepare technical design: Develop a preliminary engineering design including array layout, inverter configuration, and grid connection design.

Step 3: Bid Submission

The bid submission typically includes:

DocumentPurpose
Technical proposalSystem design, equipment specifications, construction plan
Financial proposalBid tariff (RM/kWh), financial model, funding plan
Environmental Impact Assessment (EIA)Compliance with Department of Environment requirements
Land documentsProof of ownership, lease, or land use agreement
Company credentialsRegistration documents, financial statements, past project experience
Bid bondBank guarantee or cash deposit (typically 1–2% of project value)

Late submissions are rejected. Incomplete submissions may be disqualified or scored lower.

Step 4: Bid Evaluation

The Energy Commission evaluates bids using a weighted scoring system. Typical weightings:

  • Price (tariff bid): 60–70% of total score
  • Technical merit: 20–30% (design quality, experience, track record)
  • Local content / other criteria: 10–20% (Malaysian participation, technology innovation)

The lowest tariff does not always win — a bid with a very low tariff but weak technical credentials may be rejected if the evaluator determines the tariff is not credible or the project is not deliverable.

Step 5: Award and PPA Negotiation

Winning bidders receive a Letter of Award from the Energy Commission. The next steps:

  1. Sign PPA with TNB: Negotiate and execute the standard-form Power Purchase Agreement. The PPA term is 21 years at the bid tariff.
  2. Obtain generation licence: Apply to the Energy Commission for a generation licence under the Electricity Supply Act 1990.
  3. Achieve financial close: Secure final project financing and satisfy lender conditions precedent.
  4. Commence construction: Begin engineering, procurement, and construction (EPC) within the timeline specified in the PPA.

Bidding Strategy: Model Costs Before Setting Tariff

The most common mistake in LSS bidding is setting a tariff based on competitor behaviour rather than project-specific costs. Build a detailed financial model that includes: module and inverter costs (with shipping and duties), EPC costs, land lease, grid connection costs, financing costs, O&M over 21 years, and contingency. Add a minimum equity return hurdle (typically 10–12% IRR) and solve for the tariff that meets it. Only then compare with market benchmarks. A bid that wins but cannot be financed wastes 18 months of development effort.

PPA Terms and Structure

The LSS PPA is a standard-form agreement between the project company and TNB. Key terms include:

Tariff and Payment

  • Fixed tariff: The bid tariff applies for the full 21-year term with no annual escalation.
  • Payment mechanism: TNB pays for all metered generation (kWh) at the tariff rate.
  • Billing cycle: Monthly invoicing based on TNB meter readings.
  • Currency: Ringgit Malaysia (RM).

Commercial Operation Date (COD)

  • Target COD: Typically 24–36 months from PPA execution.
  • Liquidated damages: Delayed COD may trigger liquidated damages payable to TNB.
  • Early COD: Projects may achieve COD early if construction finishes ahead of schedule.

Performance Obligations

  • Availability requirement: The plant must maintain a minimum availability factor (typically 80–85%).
  • Degradation allowance: Module degradation is factored into the expected output profile.
  • Force majeure: Defined events (natural disasters, grid failure beyond project control) excuse non-performance.

Termination

  • TNB termination: TNB may terminate for persistent non-performance, failure to achieve COD, or insolvency.
  • Developer termination: Limited — typically only for persistent TNB payment default or grid unavailability.
  • Early termination compensation: Calculated based on outstanding debt and equity return.

LSS Project Timeline

The full LSS lifecycle from tender announcement to commercial operation:

PhaseDurationKey Milestones
Tender announcement and bidding3–6 monthsTender published; bids prepared and submitted
Bid evaluation and award2–4 monthsTechnical and financial evaluation; Letter of Award issued
Financial close and land acquisition6–12 monthsPPA signed; financing secured; land formalised
Construction (EPC)12–18 monthsEngineering, procurement, construction; grid connection built
Commissioning and COD2–3 monthsTNB inspection; performance tests; PPA activation

Total timeline: 24–36 months from tender announcement to COD for a typical ground-mounted project. Floating solar or complex grid connections may extend this.

Financing LSS Projects

LSS projects are typically financed through project finance structures:

  • Debt-to-equity ratio: Typically 70:30 to 80:20
  • Debt tenor: 15–18 years (shorter than the 21-year PPA)
  • Interest rate: Based on Malaysian reference rates plus margin
  • Security package: PPA cash flows, project assets, land rights, and sponsor guarantees

Lenders conduct detailed due diligence on:

  • PPA bankability (tariff sufficiency, TNB credit risk)
  • EPC contractor track record
  • Technology risk (module degradation, inverter reliability)
  • Grid connection feasibility
  • Environmental and social compliance

Land and Grid Connection Considerations

Land Requirements

  • Size: Approximately 2–2.5 hectares per MW for ground-mounted systems
  • Terrain: Flat or gently sloping; avoid flood-prone areas
  • Land use: Must be permissible for solar under local planning regulations
  • Access: Road access for construction and O&M vehicles
  • Grid proximity: Within economically viable distance of TNB substation or transmission line

Grid Connection

  • Voltage level: Typically 33 kV or 132 kV depending on project size and grid capacity
  • Connection cost: Borne by the developer; can be significant for remote sites
  • Grid impact study: TNB conducts a grid impact study to assess the effect of the solar injection on the local network
  • Timeline: Grid connection approvals can take 6–12 months; start early in the development process

Environmental and Social Compliance

LSS projects require:

  • Environmental Impact Assessment (EIA): For projects above certain size thresholds, a full EIA is required by the Department of Environment (DOE).
  • Social impact assessment: For projects affecting local communities, particularly on agricultural land.
  • Permits: Planning permission, land conversion (if agricultural), watercourse permits, and any other local approvals.

Environmental compliance is a bid evaluation criterion and a PPA condition. Projects that fail to secure environmental approvals risk PPA termination.

Model LSS Solar Farm Economics with Precision

SurgePV’s financial tool models Malaysian irradiance, TNB grid constraints, and 21-year PPA cash flows — producing bankable solar farm proposals that reflect actual LSS cost structures.

See the Financial Tool

No commitment required · 20 minutes · Live project walkthrough

LSS vs NEM vs SELCO: Which Pathway?

For developers and investors deciding which Malaysian solar pathway to pursue:

FactorLSSNEM 3.0SELCO
Project size>1 MWDomestic ≤12 kWp; Non-domestic ≤75% MDAny size
Revenue modelPPA with TNBBill offset (1:1 credit)Bill offset (no export)
Regulatory routeEnergy Commission tenderSEDA quota + TNB connectionTNB connection only
Capital requirementHigh (RM millions)Low to moderateLow to moderate
Development timeline24–36 months4–6 months2–4 months
Risk profileCompetitive bidding risk; long-term PPA commitmentQuota availability risk; straightforwardLowest regulatory risk
Suitable forSolar farm developers, IPPs, energy investorsCommercial building owners, factories24/7 operations with high self-consumption

Choose LSS if: You are a developer or investor with access to land, capital, and project development expertise. You want to sell electricity to TNB as a business.

Choose NEM 3.0 if: You own or operate a commercial building and want to reduce your TNB bill through solar self-consumption and export credits.

Choose SELCO if: You have high 24/7 base load and want solar for self-consumption only, avoiding the SEDA quota process.

For a full comparison of NEM 3.0 and SELCO for commercial buyers, see the C&I Solar Malaysia guide.

Common LSS Development Pitfalls

PitfallCausePrevention
Underbidding and unbankable projectTariff set below true cost to win bidBuild detailed cost model before bidding; set minimum IRR hurdle
Grid connection delaySubstation capacity constraints; remote siteConduct grid feasibility study before bid submission
Land title issuesAgricultural land; unresolved ownership disputesSecure clean land title or long-term lease before bidding
EIA rejectionSensitive ecological area; community oppositionConduct pre-application environmental screening
Financing failureWeak sponsor balance sheet; non-bankable PPA termsSecure indicative financing before bid; use experienced lenders
Construction delayEPC contractor underperformance; equipment shortagesEngage proven EPC with track record; secure equipment early

Use solar design software that models Malaysian irradiance data, TNB tariff structures, and LSS PPA cash flows to produce accurate financial projections for utility-scale solar development.

Frequently Asked Questions

Can a foreign company bid for LSS projects in Malaysia? Yes, foreign companies can participate in LSS tenders through joint ventures with Malaysian-registered partners. The bidding entity itself must be incorporated in Malaysia. Foreign ownership restrictions may apply depending on the tender round conditions — check the specific tender document for local content and equity requirements.

What happens if an LSS project fails to achieve COD on time? The PPA typically includes liquidated damages for delayed COD — a fixed amount per day of delay, capped at a maximum period. Persistent delay beyond the cap may trigger PPA termination. Developers should build contingency into construction schedules and secure EPC contracts with delay penalties that mirror the PPA liquidated damages.

Is the LSS tariff really fixed for 21 years with no escalation? Yes. The standard LSS PPA uses a fixed tariff with no annual escalation. This means the real value of the tariff erodes with inflation over time. Developers must model this erosion in their financial projections. Some developers have explored inflation-linked financing or hedging strategies to mitigate this risk.

Can LSS projects include battery storage? Battery storage is not a standard feature of LSS PPAs, but the Energy Commission has indicated openness to hybrid solar-plus-storage projects in recent tender rounds. Storage would require additional technical evaluation and may affect the bid tariff. Check the specific tender conditions for storage eligibility.

What is the difference between LSS and feed-in tariff (FiT) in Malaysia? Malaysia’s Renewable Energy Act 2011 originally introduced a feed-in tariff (FiT) mechanism where approved projects received a guaranteed tariff without competitive bidding. The FiT scheme has been largely replaced by competitive tender mechanisms (LSS for large projects, NEM for self-consumption). LSS projects compete on price; FiT projects received a fixed tariff set by the regulator. New FiT approvals are limited — LSS is now the primary route for utility-scale solar.

How does LSS interact with Malaysia’s renewable energy targets? LSS is a key mechanism for Malaysia to meet its renewable energy capacity targets under the Malaysia Renewable Energy Roadmap and Nationally Determined Contributions (NDC) under the Paris Agreement. The size and frequency of LSS tender rounds are calibrated to national target trajectories. Developers should monitor government policy announcements for signals on future round sizes and timelines.

About the Contributors

Author
Nirav Dhanani
Nirav Dhanani

Co-Founder · SurgePV

Nirav Dhanani is Co-Founder of SurgePV and Chief Marketing Officer at Heaven Green Energy Limited, where he oversees marketing, customer success, and strategic partnerships for a 1+ GW solar portfolio. With 10+ years in commercial solar project development, he has been directly involved in 300+ commercial and industrial installations and led market expansion into five new regions, improving win rates from 18% to 31%.

Editor
Rainer Neumann
Rainer Neumann

Content Head · SurgePV

Rainer Neumann is Content Head at SurgePV and a solar PV engineer with 10+ years of experience designing commercial and utility-scale systems across Europe and MENA. He has delivered 500+ installations, tested 15+ solar design software platforms firsthand, and specialises in shading analysis, string sizing, and international electrical code compliance.

LSS tenderlarge-scale solarMalaysia utility solarcompetitive bidding

Solar Compliance Updates in Your Inbox

Join 2,000+ solar professionals. Regulatory changes, code updates, and design tips — weekly.

No spam · Unsubscribe anytime