🇮🇳 India Regulatory Guide 12 min read

India Open Access Solar 2026: Interstate, Intrastate & Group Captive Rules

India open access solar 2026: interstate vs intrastate open access rules, banking charges, wheeling charges, cross-subsidy surcharge, and group captive model requirements.

Nirav Dhanani

Written by

Nirav Dhanani

Co-Founder · SurgePV

Keyur Rakholiya

Reviewed by

Keyur Rakholiya

CEO & Co-Founder · SurgePV

Published ·Last reviewed ·Regulator: Central Electricity Regulatory Commission (CERC) / State ERCs

Open access solar is the primary mechanism through which India’s commercial and industrial consumers access cheaper renewable power. Instead of buying electricity from their local DISCOM at retail tariff, open access allows consumers to contract directly with solar generators and pay only the grid usage charges. For large consumers paying Rs. 8–12 per unit to DISCOMs, open access solar at Rs. 3.50–5.00 per unit (plus charges) represents substantial savings.

The open access framework in India operates at two levels: interstate (across state boundaries, governed by CERC) and intrastate (within a single state, governed by State ERCs). The Green Energy Open Access Rules 2022 have simplified many procedural hurdles, but significant variation remains across states. This guide explains the mechanics, charges, and compliance requirements for solar developers and consumers considering open access.

Intrastate Regulator
State Electricity Regulatory Commission (SERC)
Green Energy Rules
Ministry of Power, Green Energy Open Access Rules 2022
Interstate Minimum Load
1 MW
Green OA Minimum Load
100 kW (as per 2022 Rules)
Last Updated
May 2026

Cross-Subsidy Surcharge Can Make Open Access Uneconomical

In states with high cross-subsidy surcharges (CSS), the total landed cost of open access power can exceed the DISCOM retail tariff. Maharashtra, Tamil Nadu, and some other states have historically imposed CSS rates above Rs. 2.00 per unit. Always calculate the full landed cost — solar tariff + wheeling + transmission + CSS + banking — before committing to an open access project.

How Open Access Solar Works

Open access is a provision under the Electricity Act 2003 that allows consumers with connected load above a threshold to purchase electricity from any generator of their choice. The consumer pays:

  1. Energy charges: The tariff agreed with the solar generator (typically Rs. 3.00–4.50 per unit for long-term contracts)
  2. Wheeling charges: For using the distribution network (varies by state, typically Rs. 0.50–1.50 per unit)
  3. Transmission charges: For using interstate or intra-state transmission lines
  4. Cross-subsidy surcharge (CSS): Compensates the DISCOM for revenue loss
  5. Additional surcharge: Levied by some states to cover stranded power purchase costs
  6. Banking charges: If surplus solar is banked with the grid for later use

The sum of these charges is the “landed cost” of open access power. If the landed cost is below the DISCOM retail tariff, open access is economically viable.

Open Access vs DISCOM Supply: Cost Comparison

Cost ComponentOpen Access SolarDISCOM Supply
Energy chargeRs. 3.50/unitRs. 7.00–9.00/unit (industrial)
Wheeling chargesRs. 0.80/unitIncluded
Transmission chargesRs. 0.30/unitIncluded
Cross-subsidy surchargeRs. 1.20/unitNot applicable
Additional surchargeRs. 0.40/unitNot applicable
Landed costRs. 6.20/unitRs. 7.00–9.00/unit

Figures are illustrative. Actual charges vary by state, voltage level, and consumer category.

Interstate Open Access (CERC)

Interstate open access involves buying power from a generator located in a different state. CERC regulates interstate open access through the CERC (Open Access in Inter-State Transmission) Regulations.

Eligibility for Interstate Open Access

  • Minimum consumption: 1 MW connected load or contract demand
  • Applicant must be a captive consumer, a distribution licensee, or a deemed distribution licensee
  • The generator must have long-term access to interstate transmission lines

Interstate Open Access Process

  1. Long-term open access: Apply to the Central Transmission Utility (CTU) for transmission capacity allocation. The application includes generator details, drawal point, quantum of power, and duration.

  2. Medium-term open access: Apply for 3 months to 3 years of transmission capacity. Allocated through a first-come-first-served basis or competitive bidding depending on corridor availability.

  3. Short-term open access: Apply to the National Load Despatch Centre (NLDC) or Regional Load Despatch Centre (RLDC) for day-ahead or intra-day power. Processed through the power exchange or bilateral contracts.

Interstate Charges

Charge TypeDetermined ByTypical Range
Transmission chargesCERCRs. 0.20–0.50 per unit
Scheduling chargesNLDC/RLDCRs. 0.02–0.05 per unit
Reactive energy chargesCERC regulationsAs per IEGC

Intrastate Open Access (State ERC)

Intrastate open access involves buying power from a generator within the same state. Each State ERC has its own open access regulations, leading to significant variation across India.

State-wise Open Access Thresholds

StateMinimum Load for Open AccessNotable Features
Gujarat1 MWWell-developed open access market
Maharashtra1 MWHigh CSS historically
Karnataka1 MW (100 kW for green energy)Active open access market
Tamil Nadu1 MWHigh CSS and additional surcharge
Rajasthan1 MWLow solar tariffs, attractive for OA
Andhra Pradesh1 MWVariable CSS rates
Telangana1 MWGrowing open access activity
Haryana1 MWGreen energy OA at 100 kW
Delhi1 MWLimited due to small geography

Under the Green Energy Open Access Rules 2022, all states must allow green energy open access at 100 kW. However, implementation has been uneven, with some states resisting the lower threshold.

Banking Provisions by State

Banking allows a solar generator to inject surplus power into the grid and withdraw an equivalent amount later. Banking rules vary:

StateBanking AllowedSettlement PeriodBanking Charges
GujaratYesMonthly2–5% of banked energy
KarnatakaYesMonthly2% banking loss
MaharashtraYesMonthly5% banking loss
RajasthanYesMonthly2% banking loss
Tamil NaduYesMonthly5% banking loss
Andhra PradeshLimitedMonthly5–10%

The Green Energy Open Access Rules 2022 mandate monthly settlement with uniform banking provisions, but states continue to apply their own loss percentages.

Group Captive Model

The group captive model is a popular structure for open access solar. It allows multiple consumers to jointly own a solar project and share the power output.

Group Captive Requirements

To qualify as group captive and avail surcharge exemptions:

  1. Equity requirement: The consuming entity must hold at least 26% of the equity share capital of the generation company
  2. Consumption requirement: The consuming entity must consume at least 51% of the power generated
  3. Proportionality: In multi-consumer group captive structures, each consumer’s share of consumption must be proportional to their equity contribution

Benefits of Group Captive Structure

BenefitExplanation
CSS exemptionMost states exempt group captive consumers from cross-subsidy surcharge
Additional surcharge exemptionGroup captive typically exempt from additional surcharge
Lower landed costSavings of Rs. 1.50–2.50 per unit compared to third-party open access
Long-term price certainty20–25 year PPA with fixed or escalating tariff
Balance sheet flexibilityConsumer does not need to own 100% of the asset

Group Captive vs Third-Party Open Access

ParameterGroup CaptiveThird-Party Open Access
Equity investment requiredYes (minimum 26%)No
CSS applicabilityExempt in most statesPayable
Additional surchargeExempt in most statesPayable
PPA structureDirect ownership + PPAPure PPA
ComplexityHigher (equity, governance)Lower
Landed costLowerHigher

Green Energy Open Access Rules 2022

The Ministry of Power notified the Green Energy Open Access Rules in June 2022 to standardise and simplify renewable energy open access across India.

Key Provisions

ProvisionDetail
Eligibility threshold100 kW for green energy open access
Application timelineDISCOM must process within 15 days
NOC requirementSingle-window clearance — no multiple NOCs
BankingMonthly settlement mandated
CSS capCapped at 50% of the average power purchase cost
Additional surchargeNot applicable for green energy open access
Renewable purchase obligationConsumers can meet RPO through open access

Impact on States

The 2022 Rules override inconsistent state regulations. However, several states have challenged or delayed implementation:

  • Some states continue to require 1 MW minimum despite the 100 kW rule
  • Banking loss percentages remain state-determined
  • DISCOMs in some states delay application processing beyond 15 days
  • CSS calculation methodologies vary

Consumers and developers should verify current state-level implementation status before planning open access projects.

Model Open Access Solar Economics Accurately

SurgePV calculates energy yield, landed cost analysis, and open access tariff modelling for interstate and intrastate solar projects — with state-specific charge structures built in.

Book a Demo

No commitment required · 20 minutes · Live project walkthrough

Common Mistakes in Open Access Projects

Ignoring CSS trends: Cross-subsidy surcharges are revised annually by SERCs. A project viable at current CSS may become uneconomical if the SERC increases CSS significantly.

Incorrect meter specification: Open access requires ABT-compliant special energy meters at both injection and drawal points. Non-compliant meters lead to billing disputes and potential penalties.

Inadequate transmission study: For interstate open access, transmission corridor congestion can prevent scheduled power delivery. A detailed transmission system study is essential before committing to a generator location.

Overlooking banking restrictions: Some states limit banking to certain months or impose high banking losses. Projects sized for annual generation banking may underperform if seasonal restrictions apply.

Poor PPA drafting: Open access PPAs must clearly define liability for grid charges, scheduling deviations, and force majeure. Ambiguous clauses lead to disputes between consumers and generators.

Open Access Charges: State Comparison

StateWheeling Charges (Rs./unit)CSS (Rs./unit)Additional Surcharge (Rs./unit)Overall Attractiveness
Gujarat0.60–0.900.50–0.80NilHigh
Karnataka0.70–1.000.80–1.20NilModerate
Rajasthan0.50–0.700.40–0.60NilHigh
Maharashtra0.80–1.201.50–2.500.50–1.00Low
Tamil Nadu0.60–0.901.00–1.800.30–0.50Low
Andhra Pradesh0.70–1.000.60–1.00NilModerate
Haryana0.60–0.800.50–0.80NilHigh

Figures are indicative and change with SERC tariff orders. Verify current rates before project planning.

For commercial and industrial consumers evaluating solar design software for open access project sizing, accurate energy yield modelling and tariff analysis are essential inputs for investment decisions.

Frequently Asked Questions

What is open access solar in India?

Open access solar allows consumers to buy power directly from solar generators instead of their local DISCOM. The consumer pays the solar tariff plus wheeling charges, transmission charges, and applicable surcharges for using the grid infrastructure.

What is the difference between interstate and intrastate open access?

Interstate open access involves buying power from a generator in another state, regulated by CERC, with a 1 MW minimum load. Intrastate open access is within one state, regulated by the State ERC, with variable minimum load requirements.

What is a group captive model in open access solar?

A group captive structure requires the consumer to hold at least 26% equity in the solar project and consume at least 51% of the generation. This exempts the consumer from cross-subsidy surcharge and additional surcharge in most states.

What are the charges payable in open access solar?

Consumers pay wheeling charges, transmission charges, cross-subsidy surcharge, additional surcharge (in some states), and banking charges. The total is the “landed cost” of open access power.

What are the Green Energy Open Access Rules 2022?

These rules standardise renewable energy open access across India, reducing the eligibility threshold to 100 kW, capping CSS at 50% of average power purchase cost, mandating 15-day application processing, and requiring monthly banking settlement.

About the Contributors

Author
Nirav Dhanani
Nirav Dhanani

Co-Founder · SurgePV

Nirav Dhanani is Co-Founder of SurgePV and Chief Marketing Officer at Heaven Green Energy Limited, where he oversees marketing, customer success, and strategic partnerships for a 1+ GW solar portfolio. With 10+ years in commercial solar project development, he has been directly involved in 300+ commercial and industrial installations and led market expansion into five new regions, improving win rates from 18% to 31%.

Editor
Keyur Rakholiya
Keyur Rakholiya

CEO & Co-Founder · SurgePV

Keyur Rakholiya is CEO & Co-Founder of SurgePV and Founder of Heaven Green Energy Limited, where he has delivered over 1 GW of solar projects across commercial, utility, and rooftop sectors in India. With 10+ years in the solar industry, he has managed 800+ project deliveries, evaluated 20+ solar design platforms firsthand, and led engineering teams of 50+ people.

open access solar Indiainterstate open accessintrastate open accessgroup captive solarCERC open accessgreen energy open access

Solar Compliance Updates in Your Inbox

Join 2,000+ solar professionals. Regulatory changes, code updates, and design tips — weekly.

No spam · Unsubscribe anytime