Every solar conductor must be sized to carry current safely under the worst-case conditions the installation will ever experience. NEC 690.8 defines how to do that calculation for PV source and output circuits — and the answer is almost never the same as a standard building wiring calculation.
The key difference: solar is treated as a continuous load, which means the 125% rule applies before any other derating. Then ambient temperature correction and conduit fill derating stack on top. Miss any one of these and the permit fails plan review.
The 690.8 Calculation Framework
NEC 690.8 establishes a three-step minimum sizing requirement:
- Step 1: Start with the module rated Isc
- Step 2: Multiply by 1.25 (continuous load factor)
- Step 3: Apply standard NEC derating factors (temperature, conduit fill)
The conductor must carry the result of Step 3 under all conditions. This is the minimum required ampacity — you then select the smallest standard conductor from NEC Table 310.16 that meets or exceeds it.
Source Circuit vs. Output Circuit
A PV source circuit connects modules within a string to the combiner box or inverter input. A PV output circuit connects the combiner box output to the inverter. Source circuit current = single string Isc. Output circuit current = sum of all parallel string Isc values feeding that circuit.
Step 1: Identify Circuit Isc
Series Strings (Source Circuit)
Current does not add in series. A string of 20 modules in series has the same current as a single module:
Source circuit Isc = Module Isc (regardless of string length)
Parallel Strings (Output Circuit)
Current adds in parallel. If 4 strings (each with Isc = 10A) feed a combiner, the output circuit Isc is:
Output circuit Isc = N_strings × Module Isc = 4 × 10A = 40A
Step 2: Apply the 125% Continuous Load Factor
NEC 690.8(A) requires that the minimum conductor ampacity equal at least 125% of the maximum circuit current:
Minimum ampacity (before derating) = Isc × 1.25
| Module Isc | ×1.25 Minimum Ampacity |
|---|---|
| 8.0 A | 10.0 A |
| 9.5 A | 11.9 A |
| 10.0 A | 12.5 A |
| 11.0 A | 13.75 A |
| 12.5 A | 15.6 A |
| 14.0 A | 17.5 A |
This is the floor. Everything after this point only makes the required ampacity larger.
Step 3A: Ambient Temperature Derating
Conductor ampacity decreases as ambient temperature increases. The NEC tables are based on a 30°C (86°F) reference temperature for THWN-2 conductors. In hotter environments, you must derate.
Rooftop Conduit: The 22°C Adder
NEC 310.15(B)(3)(c) requires adding 22°C (40°F) to the local design maximum ambient air temperature when conductors are in conduit installed on or above a rooftop and within 7 inches of the roof surface.
Example: Phoenix, AZ has a design maximum air temperature of 43°C (109°F). Conduit on roof: 43°C + 22°C = 65°C effective ambient
At 65°C, the temperature correction factor for 90°C-rated conductors (THWN-2) from NEC Table 310.15(B)(1)(1) is 0.58.
Phoenix Example Is Not an Edge Case
In Phoenix, the rooftop conduit temperature correction factor of 0.58 means you need a conductor rated for nearly twice the current at table ampacity compared to what the conductor would need at standard conditions. A 10 AWG THWN-2 rated at 40A (table) is only allowed to carry 40A × 0.58 = 23.2A in a Phoenix rooftop conduit — before conduit fill derating.
Temperature Correction Factors for 90°C Conductors (NEC Table 310.15(B)(1)(1))
| Effective Ambient Temperature | Correction Factor |
|---|---|
| 21–25°C (70–77°F) | 1.04 |
| 26–30°C (78–86°F) | 1.00 |
| 31–35°C (87–95°F) | 0.96 |
| 36–40°C (97–104°F) | 0.91 |
| 41–45°C (105–113°F) | 0.87 |
| 46–50°C (113–122°F) | 0.82 |
| 51–55°C (123–131°F) | 0.76 |
| 56–60°C (132–140°F) | 0.71 |
| 61–65°C (141–149°F) | 0.65 |
| 66–70°C (150–158°F) | 0.58 |
| 71–75°C (159–167°F) | 0.50 |
Step 3B: Conduit Fill Derating
When more than 3 current-carrying conductors share a conduit, NEC Table 310.15(C)(1) requires derating:
| Number of Conductors | Derating Factor |
|---|---|
| 1–3 | 1.00 (no derating) |
| 4–6 | 0.80 |
| 7–9 | 0.70 |
| 10–20 | 0.50 |
| 21–30 | 0.45 |
| 31–40 | 0.40 |
| 41+ | 0.35 |
Both positive and negative conductors count as current-carrying. A conduit carrying 3 source circuits has 6 current-carrying conductors (3 positive, 3 negative) → 0.80 derating factor.
Keep Conduit Runs Short and Separate
The single most effective way to manage ampacity derating is to limit source circuit conductors per conduit. Two conduits with 3 circuits each (factor: 1.00) always allows smaller conductors than one conduit with 6 circuits (factor: 0.80), because neither conduit requires conduit fill derating.
Complete Worked Example
Project: 8.64 kW residential, Dallas, TX Module: 360W, Isc = 9.58A, 90°C THWN-2 in conduit String configuration: 2 strings × 12 modules, both strings in same conduit Local maximum air temperature: 40°C (104°F), rooftop conduit
Step 1 — Source circuit Isc:
Isc = 9.58A (single string)
Step 2 — Apply 125% factor:
Minimum ampacity = 9.58 × 1.25 = 11.98A
Step 3A — Temperature correction:
Effective ambient = 40°C + 22°C (rooftop adder) = 62°C
Correction factor at 62°C for 90°C conductor = 0.65
Required ampacity after temp derating = 11.98 / 0.65 = 18.43A
Step 3B — Conduit fill:
Conductors in conduit = 4 (2 positive + 2 negative for 2 source circuits)
Derating factor = 0.80
Required ampacity after fill derating = 18.43 / 0.80 = 23.04A
Step 4 — Select wire size:
From NEC Table 310.16 (90°C column):
- 12 AWG THWN-2: 30A → sufficient (23.04A required)
- 10 AWG THWN-2: 40A → provides more margin
With terminal temperature limitations, if the inverter terminals are only rated for 75°C, use the 75°C ampacity column: 12 AWG = 25A. This still covers the 23.04A requirement.
Result: 12 AWG THWN-2 is the minimum for this installation’s source circuits.
Common 690.8 Mistakes
| Mistake | Consequence | Fix |
|---|---|---|
| Skipping temperature derating for “mild climate” installations | Undersized conductors that overheat — AHJ reject + fire risk | Always calculate — even San Diego rooftops add 22°C |
| Forgetting the 22°C rooftop adder | Underestimated conductor temperature | Add 22°C when conduit is within 7 inches of roof surface |
| Counting only one conductor per circuit | Underestimates fill, misses conduit derating | Count both positive and negative conductors |
| Using 60°C terminal limitation for 75°C-rated equipment | Undersizes conductor | Check inverter terminal temperature rating from spec sheet |
| Using wire ampacity from Table 310.17 (free air) instead of 310.16 (conduit) | Overstates allowable ampacity for conduit installations | Confirm wiring method before selecting table |
Documentation for Permit Packages
AHJ plan reviewers checking 690.8 compliance look for:
- Source circuit Isc clearly labeled on one-line diagram
- 125% calculation shown explicitly
- Ambient temperature documented with source (ASHRAE or local weather data)
- 22°C rooftop adder applied (if applicable) with rooftop conduit noted
- Conductor fill count with total current-carrying conductors per conduit
- Final required ampacity and selected wire size
- Wire size consistent between calculation, one-line diagram, and wire schedule
Automate NEC 690.8 Conductor Sizing
SurgePV calculates source and output circuit ampacity automatically — 125% factor, temperature derating, and conduit fill — and exports the full calculation table in your AHJ-ready permit package.
Try It FreeNo commitment required · 20 minutes · Live project walkthrough
Frequently Asked Questions
What does NEC 690.8 require for conductor sizing?
Conductors in PV source and output circuits must be rated at a minimum of 125% of the module rated short-circuit current (Isc), then derated for ambient temperature and conduit fill per standard NEC ampacity tables.
Why 125% and not 100% of Isc?
Solar PV is classified as a continuous load — it can output near-maximum current for 3 or more hours. The NEC requires continuous loads to be served by conductors (and overcurrent devices) sized at 125% of the actual load.
What’s the biggest factor affecting conductor size on rooftop installations?
Ambient temperature derating, particularly the mandatory 22°C adder for conduit within 7 inches of a rooftop surface. This single factor can reduce allowable conductor ampacity by 30–40% and force upsizing from 12 AWG to 10 AWG or larger.