Georgia has grown into a significant solar market, ranking in the top 10 states for installed solar capacity. Georgia Power’s Schedule 62 interconnection process is straightforward for residential systems, and the statewide net metering mandate provides predictable economics for both residential and commercial installations.
Georgia Solar Snapshot
NEC Edition: 2020 | Primary Utility: Georgia Power (Southern Company subsidiary) | Net Metering: Statewide mandatory (retail rate) | State Tax Credit: None for solar | Property Tax: Solar equipment exempt | Federal ITC: 30% residential / up to 50% commercial
NEC 2020 in Georgia
Georgia adopted NEC 2020 statewide. Solar PV installations must comply with all applicable Article 690 sections:
| NEC Section | Requirement | Georgia Notes |
|---|---|---|
| 690.7 | Residential 600V / Commercial 1000V max | Standard |
| 690.8 | 125% conductor sizing + Atlanta temp derating | Atlanta: effective 58°C (0.71 factor) |
| 690.9 | DC-rated OCPDs, 125% Isc | Standard |
| 690.12 | Rapid shutdown for rooftop | Required statewide |
| 690.31 | PV Wire/USE-2 for module wiring | Standard |
| 690.41 | System grounding | Standard |
Atlanta Climate — Conductor Derating
Atlanta’s climate requires rooftop conductor derating:
| Parameter | Value |
|---|---|
| ASHRAE max air temp | 36°C |
| + 22°C rooftop adder | +22°C |
| Effective conductor temp | 58°C |
| THWN-2 (90°C) correction factor | 0.71 |
A 10 AWG THWN-2 in Atlanta rooftop conduit: 40A × 0.71 = 28.4A available ampacity.
Georgia Power Interconnection — Schedule 62
Georgia Power’s Schedule 62 defines the interconnection process for distributed generation:
Residential Track (under 10 kW)
| Step | Action | Timeline |
|---|---|---|
| 1 | Submit Schedule 62 application online | Day 1 |
| 2 | Georgia Power reviews application | 10–30 days |
| 3 | Execute interconnection agreement | After approval |
| 4 | Complete installation + inspections | Per local AHJ |
| 5 | Georgia Power installs net meter | 5–10 business days after sign-off |
Commercial Track (10 kW–2 MW)
Level 1 interconnection study required. Timeline: 45–90 days. Georgia Power evaluates feeder capacity and voltage impact.
Large System Track (over 2 MW)
Full Level 2 interconnection study. 6–18 month timeline. May require substation upgrades at project cost.
EMC Territory in Georgia
Approximately 42% of Georgia’s land area is served by Electric Membership Cooperatives (Georgia’s 42 EMCs). Each EMC has its own interconnection process and net metering policy. The Georgia EMC Association provides a member finder — identify the specific co-op before submitting any interconnection application, as timelines and requirements differ significantly from Georgia Power.
Net Metering in Georgia
Georgia’s net metering rules under O.C.G.A. § 46-3 mandate the following for Georgia Power customers:
| Parameter | Residential | Commercial |
|---|---|---|
| Eligible size | Up to 10 kW | Up to 100 kW |
| Credit rate | Full retail rate | Full retail rate |
| Monthly carryover | Yes | Yes |
| Annual true-up | Unused credits at avoided cost | Unused credits at avoided cost |
| Eligibility | All Georgia Power residential | All GP commercial |
For systems exceeding 100 kW: Georgia Power offers Power Purchase Agreements (PPAs) or the Large Generator Interconnection path, which typically results in below-retail export rates.
Georgia Property Tax Exemption
Georgia Code § 48-5-48.1 provides a 100% property tax exemption for solar energy equipment:
- Applies to both residential and commercial solar
- Solar equipment value is excluded entirely from property tax assessment
- No application required — exemption applies by statute
- This applies to the solar equipment itself, not to any increase in the property value from having solar
Atlanta AHJ Permit Process
City of Atlanta
Atlanta participates in SolarAPP+ for residential systems under 15 kW:
- Submit design through SolarAPP+-compatible design software
- SolarAPP+ automated plan review (typically same-day approval)
- Obtain approved permit from Atlanta Permits and Inspections
- Complete installation
- Schedule inspection through Atlanta’s portal
- Receive inspection sign-off
For non-SolarAPP+ projects and commercial systems:
- Submit structural and electrical drawings
- Plan review: 5–15 business days
- Permit fee: ~$200–500 residential, varies for commercial
Fulton County (Unincorporated)
- Separate from City of Atlanta Building Department
- SolarAPP+ participation varies — confirm before submitting
- Similar process but Fulton County Building and Inspection
Savannah / Chatham County
- Chatham County Building Services
- Separate permitting from City of Savannah
- Coastal zone wind load requirements apply
Georgia Power vs. Municipal Utility Territory
The City of Dalton (northwest GA) operates its own municipal electric utility and has separate interconnection requirements from Georgia Power. Several other small municipalities also operate municipal utilities. If the project is not in Georgia Power or an EMC territory, identify the specific utility before submitting any interconnection application.
Commercial Solar in Georgia
Georgia’s commercial solar market has grown substantially with large utility-scale projects in the southeast part of the state. Key considerations for C&I:
- Georgia Power offers a Commercial Solar program for business customers
- C&I systems under 2 MW can participate in Level 1 interconnection
- Property tax exemption applies to commercial solar equipment
- IRA Section 48E: 30% base credit + up to 20% bonus credits
- Energy community designation: Former Georgia coal plant areas (Plant Bowen, Plant Scherer vicinity) may qualify for +10% energy community bonus
Generate Georgia Power-Ready Permit Packages
SurgePV produces NEC 2020-compliant permit packages for Georgia — complete with Schedule 62 documentation requirements, one-line diagrams, and NEC 690 calculations formatted for Atlanta and other GA AHJs.
Book a DemoNo commitment required · 20 minutes · Live project walkthrough
Frequently Asked Questions
What NEC edition does Georgia use for solar?
NEC 2020. Georgia adopted NEC 2020 statewide. Atlanta and other large cities follow the state adoption with potential local amendments — always confirm with the specific AHJ.
How does Georgia Power net metering work?
Georgia Power credits excess generation at the full retail rate for residential systems up to 10 kW and commercial systems up to 100 kW. Monthly credits carry forward; annual remaining credits are paid at the avoided cost rate. EMC customers should contact their specific cooperative.
Does Georgia have state solar tax credits?
Georgia has no state income tax credit for solar. The primary incentives are the federal ITC (30% residential, up to 50% commercial) and the property tax exemption for solar equipment (100% exemption from property assessment per state statute).