🇺🇸 United States State Guide 10 min read

Georgia Solar Compliance Guide 2026: NEC 2020, Georgia Power Interconnection & Net Metering

Complete guide to solar permitting and compliance in Georgia. Covers NEC 2020, Georgia Power interconnection (Schedule 62), statewide net metering, Atlanta and Savannah AHJ permit requirements, and ITC for residential and commercial solar.

Rainer Neumann

Written by

Rainer Neumann

Content Head · SurgePV

Keyur Rakholiya

Reviewed by

Keyur Rakholiya

CEO & Co-Founder · SurgePV

Published ·Last reviewed ·Regulator: Georgia Public Service Commission / NFPA NEC

Georgia has grown into a significant solar market, ranking in the top 10 states for installed solar capacity. Georgia Power’s Schedule 62 interconnection process is straightforward for residential systems, and the statewide net metering mandate provides predictable economics for both residential and commercial installations.

Georgia Solar Snapshot

NEC Edition: 2020 | Primary Utility: Georgia Power (Southern Company subsidiary) | Net Metering: Statewide mandatory (retail rate) | State Tax Credit: None for solar | Property Tax: Solar equipment exempt | Federal ITC: 30% residential / up to 50% commercial

NEC 2020 in Georgia

Georgia adopted NEC 2020 statewide. Solar PV installations must comply with all applicable Article 690 sections:

NEC SectionRequirementGeorgia Notes
690.7Residential 600V / Commercial 1000V maxStandard
690.8125% conductor sizing + Atlanta temp deratingAtlanta: effective 58°C (0.71 factor)
690.9DC-rated OCPDs, 125% IscStandard
690.12Rapid shutdown for rooftopRequired statewide
690.31PV Wire/USE-2 for module wiringStandard
690.41System groundingStandard

Atlanta Climate — Conductor Derating

Atlanta’s climate requires rooftop conductor derating:

ParameterValue
ASHRAE max air temp36°C
+ 22°C rooftop adder+22°C
Effective conductor temp58°C
THWN-2 (90°C) correction factor0.71

A 10 AWG THWN-2 in Atlanta rooftop conduit: 40A × 0.71 = 28.4A available ampacity.

Georgia Power Interconnection — Schedule 62

Georgia Power’s Schedule 62 defines the interconnection process for distributed generation:

Residential Track (under 10 kW)

StepActionTimeline
1Submit Schedule 62 application onlineDay 1
2Georgia Power reviews application10–30 days
3Execute interconnection agreementAfter approval
4Complete installation + inspectionsPer local AHJ
5Georgia Power installs net meter5–10 business days after sign-off

Commercial Track (10 kW–2 MW)

Level 1 interconnection study required. Timeline: 45–90 days. Georgia Power evaluates feeder capacity and voltage impact.

Large System Track (over 2 MW)

Full Level 2 interconnection study. 6–18 month timeline. May require substation upgrades at project cost.

EMC Territory in Georgia

Approximately 42% of Georgia’s land area is served by Electric Membership Cooperatives (Georgia’s 42 EMCs). Each EMC has its own interconnection process and net metering policy. The Georgia EMC Association provides a member finder — identify the specific co-op before submitting any interconnection application, as timelines and requirements differ significantly from Georgia Power.

Net Metering in Georgia

Georgia’s net metering rules under O.C.G.A. § 46-3 mandate the following for Georgia Power customers:

ParameterResidentialCommercial
Eligible sizeUp to 10 kWUp to 100 kW
Credit rateFull retail rateFull retail rate
Monthly carryoverYesYes
Annual true-upUnused credits at avoided costUnused credits at avoided cost
EligibilityAll Georgia Power residentialAll GP commercial

For systems exceeding 100 kW: Georgia Power offers Power Purchase Agreements (PPAs) or the Large Generator Interconnection path, which typically results in below-retail export rates.

Georgia Property Tax Exemption

Georgia Code § 48-5-48.1 provides a 100% property tax exemption for solar energy equipment:

  • Applies to both residential and commercial solar
  • Solar equipment value is excluded entirely from property tax assessment
  • No application required — exemption applies by statute
  • This applies to the solar equipment itself, not to any increase in the property value from having solar

Atlanta AHJ Permit Process

City of Atlanta

Atlanta participates in SolarAPP+ for residential systems under 15 kW:

  1. Submit design through SolarAPP+-compatible design software
  2. SolarAPP+ automated plan review (typically same-day approval)
  3. Obtain approved permit from Atlanta Permits and Inspections
  4. Complete installation
  5. Schedule inspection through Atlanta’s portal
  6. Receive inspection sign-off

For non-SolarAPP+ projects and commercial systems:

  • Submit structural and electrical drawings
  • Plan review: 5–15 business days
  • Permit fee: ~$200–500 residential, varies for commercial

Fulton County (Unincorporated)

  • Separate from City of Atlanta Building Department
  • SolarAPP+ participation varies — confirm before submitting
  • Similar process but Fulton County Building and Inspection

Savannah / Chatham County

  • Chatham County Building Services
  • Separate permitting from City of Savannah
  • Coastal zone wind load requirements apply

Georgia Power vs. Municipal Utility Territory

The City of Dalton (northwest GA) operates its own municipal electric utility and has separate interconnection requirements from Georgia Power. Several other small municipalities also operate municipal utilities. If the project is not in Georgia Power or an EMC territory, identify the specific utility before submitting any interconnection application.

Commercial Solar in Georgia

Georgia’s commercial solar market has grown substantially with large utility-scale projects in the southeast part of the state. Key considerations for C&I:

  • Georgia Power offers a Commercial Solar program for business customers
  • C&I systems under 2 MW can participate in Level 1 interconnection
  • Property tax exemption applies to commercial solar equipment
  • IRA Section 48E: 30% base credit + up to 20% bonus credits
  • Energy community designation: Former Georgia coal plant areas (Plant Bowen, Plant Scherer vicinity) may qualify for +10% energy community bonus

Generate Georgia Power-Ready Permit Packages

SurgePV produces NEC 2020-compliant permit packages for Georgia — complete with Schedule 62 documentation requirements, one-line diagrams, and NEC 690 calculations formatted for Atlanta and other GA AHJs.

Book a Demo

No commitment required · 20 minutes · Live project walkthrough

Frequently Asked Questions

What NEC edition does Georgia use for solar?

NEC 2020. Georgia adopted NEC 2020 statewide. Atlanta and other large cities follow the state adoption with potential local amendments — always confirm with the specific AHJ.

How does Georgia Power net metering work?

Georgia Power credits excess generation at the full retail rate for residential systems up to 10 kW and commercial systems up to 100 kW. Monthly credits carry forward; annual remaining credits are paid at the avoided cost rate. EMC customers should contact their specific cooperative.

Does Georgia have state solar tax credits?

Georgia has no state income tax credit for solar. The primary incentives are the federal ITC (30% residential, up to 50% commercial) and the property tax exemption for solar equipment (100% exemption from property assessment per state statute).

About the Contributors

Author
Rainer Neumann
Rainer Neumann

Content Head · SurgePV

Rainer Neumann is Content Head at SurgePV and a solar PV engineer with 10+ years of experience designing commercial and utility-scale systems across Europe and MENA. He has delivered 500+ installations, tested 15+ solar design software platforms firsthand, and specialises in shading analysis, string sizing, and international electrical code compliance.

Editor
Keyur Rakholiya
Keyur Rakholiya

CEO & Co-Founder · SurgePV

Keyur Rakholiya is CEO & Co-Founder of SurgePV and Founder of Heaven Green Energy Limited, where he has delivered over 1 GW of solar projects across commercial, utility, and rooftop sectors in India. With 10+ years in the solar industry, he has managed 800+ project deliveries, evaluated 20+ solar design platforms firsthand, and led engineering teams of 50+ people.

Georgia solarGeorgia Power interconnectionGeorgia net meteringNEC 2020 GeorgiaAtlanta solar permit

Solar Compliance Updates in Your Inbox

Join 2,000+ solar professionals. Regulatory changes, code updates, and design tips — weekly.

No spam · Unsubscribe anytime