Phoenix is the single largest US solar market by installed residential capacity, driven by the best solar irradiance in the continental US and high electricity rates. The desert climate creates engineering challenges — Phoenix conductor derating is more aggressive than any other major US city — but the solar resource makes the economics compelling.
Phoenix Solar Snapshot
NEC Edition: 2020 | Utilities: APS (west Phoenix metro) + SRP (east valley) | APS Net Metering: Resource Comparison Proxy (RCP) rate — not full retail | SRP Solar: E-27 plan with solar access charge | Property Tax: Solar devices fully exempt | Federal ITC: 30% residential / up to 50% commercial
Phoenix Desert Climate Engineering
Phoenix presents the most aggressive conductor derating scenario in US solar:
Conductor Ampacity in Phoenix
| Conductor | NEC Table 310.16 (90°C) | Phoenix Derated (0.65) |
|---|---|---|
| 14 AWG | 25A | 16.3A |
| 12 AWG | 30A | 19.5A |
| 10 AWG | 40A | 26.0A |
| 8 AWG | 55A | 35.8A |
| 6 AWG | 75A | 48.8A |
Critical: Terminal Temperature Rating
The 75°C terminal limitation is most consequential in Phoenix:
| Conductor | 90°C Column | 75°C Column (terminal-limited) |
|---|---|---|
| 10 AWG | 40A | 35A |
| 8 AWG | 55A | 50A |
| 6 AWG | 75A | 65A |
Example: 12 AWG derated for Phoenix: 30A × 0.65 = 19.5A. If inverter terminals rated 75°C: 25A × 0.65 = 16.3A. A single string at 9.58A Isc: required = 9.58 × 1.25 / 0.65 = 18.42A. If using 75°C column: 16.3A < 18.42A — fails. Need 10 AWG for Phoenix if inverter terminals are 75°C-rated.
Phoenix NEC 690.7 String Voltage
Phoenix T_min = 2°C:
For Voc = 45.0V, β_Voc = -0.28%/°C:
Factor = 1 + (2 - 25) × (-0.0028) = 1 + 0.0644 = 1.0644
Max modules (600V) = 600 / (45.0 × 1.0644) = 12.52 → 12 modules
Max modules (1000V commercial) = 1000 / (45.0 × 1.0644) = 20.87 → 20 modules
APS Interconnection
Arizona Public Service serves the central and western Phoenix metro (Phoenix, Glendale, Peoria, Avondale, Goodyear, Surprise, Scottsdale west of Hayden Rd):
APS Process
| System Size | Track | Timeline |
|---|---|---|
| Under 10 kW residential | Simplified | 10–20 business days |
| 10 kW–2 MW | Level 1 study | 45–90 days |
| Over 2 MW | Level 2 study | 6–18 months |
APS Net Metering (Resource Comparison Proxy)
APS’s net metering uses the Resource Comparison Proxy (RCP) rate, not full retail:
- RCP rate: approximately $0.09–0.12/kWh (varies quarterly)
- Retail rate: approximately $0.14–0.17/kWh (varies by tier and TOU)
- Monthly excess credits at RCP rate
- Annual excess: paid at RCP rate
APS’s RCP rate is lower than retail but is still a defined and consistent credit. The economics are less favorable than states with full retail net metering but better than states with pure avoided cost credits.
SRP Interconnection
Salt River Project serves eastern Phoenix metro (Mesa, Tempe, Chandler, Gilbert, Scottsdale east, Ahwatukee, parts of Phoenix):
SRP E-27 Solar Plan
SRP’s solar customers are placed on the E-27 Price Plan:
- Monthly solar access charge (~$32–50/month depending on system size)
- Time-of-use rates apply to all electricity consumption
- Solar generation credits applied at a defined rate
- Different economics than APS — monthly fixed charge affects small system ROI
SRP vs. APS: Very Different Economics
SRP’s E-27 solar plan includes a monthly solar access charge ($32–50/month) plus time-of-use pricing. For small residential systems, the fixed monthly charge can significantly offset solar savings. Before designing a system in SRP territory, model the full E-27 economics including the solar access charge — the solar economics differ substantially from APS territory even for the same solar resource.
City of Phoenix Permit Process
SolarAPP+ Track (Residential, under 15 kW)
Phoenix participates in SolarAPP+:
- Submit through SolarAPP+-compatible design software
- Automated approval — typically same-day
- Apply for Phoenix permit with SolarAPP+ certificate
- Phoenix issues permit
- Install + inspection
- APS/SRP interconnection activation
Standard Track
- Submit through Phoenix Permits online portal
- Submit electrical one-line, structural plan, equipment specs
- Plan review: 5–15 business days
- Permit issued
- Install
- Schedule Phoenix Building Services inspection
- Utility interconnection
Phoenix Permit Fees
| System | Approximate Fee |
|---|---|
| Residential SolarAPP+ | ~$100–200 |
| Standard residential | ~$150–400 |
| Commercial | Valuation-based |
Maricopa County (Unincorporated)
Maricopa County Building Services serves unincorporated areas of the county:
- Separate from City of Phoenix
- County solar permit process
- SolarAPP+ participation varies — confirm with Maricopa County
- Many suburban Phoenix areas (parts of Scottsdale, Mesa, Chandler, Gilbert) are incorporated cities with their own permits — not County
Phoenix-Ready Solar Permit Packages with Desert Derating
SurgePV applies Phoenix ASHRAE data (43°C max, effective 65°C rooftop) automatically and generates NEC 2020-compliant permit packages formatted for Phoenix Building Services, APS, and SRP interconnection.
Book a DemoNo commitment required · 20 minutes · Live project walkthrough
Frequently Asked Questions
What is the conductor derating for Phoenix solar?
Phoenix has the highest effective rooftop temperature in the US: 43°C air + 22°C adder = 65°C effective. THWN-2 correction factor: 0.65. Required conductor ampacity = (Isc × 1.25) ÷ 0.65. If inverter terminals are 75°C-rated, use the 75°C ampacity column — this often requires the next larger conductor size vs. the 90°C calculation.
What is the difference between APS and SRP for solar?
APS credits excess solar at the Resource Comparison Proxy (RCP) rate (~$0.09–0.12/kWh). SRP places solar customers on the E-27 plan with a monthly solar access charge ($32–50/month) — this monthly fixed charge affects ROI for small systems. Determining which utility serves the project address is the first step in any Phoenix solar project.
Does Phoenix use SolarAPP+?
Yes — City of Phoenix participates in SolarAPP+ for residential systems under 15 kW. Maricopa County (unincorporated) and other Phoenix metro cities (Mesa, Chandler, etc.) have separate permitting processes.