Connecting solar generation to the Electricity North West network requires following ENA Engineering Recommendation G98 or G99, depending on system size. ENW serves one of the most geographically varied service territories in England — from dense urban areas in Greater Manchester to rural upland networks in Cumbria — and that variation directly affects how quickly connections can be made and whether export limitation is needed.
This guide covers the full G98 and G99 application process for ENW, the documents you need, ENW’s SSEG connection pathway, export limiting in constrained areas, and the timelines you should plan around.
Electricity North West Service Territory
ENW is the distribution network operator for the North West of England. Its licence area covers:
- Cumbria — includes the Lake District, Barrow-in-Furness, Carlisle, and remote upland areas
- Lancashire — Preston, Blackburn, Burnley, Lancaster, and the Fylde Coast
- Greater Manchester — the ten metropolitan boroughs including Manchester, Salford, Trafford, and Stockport
- Cheshire — Chester, Warrington, Crewe, and Macclesfield
The network topology varies significantly across this area. Greater Manchester is a dense urban network with high load density and generally good capacity on feeder circuits. Cumbria and parts of rural Lancashire have long overhead line circuits serving sparse loads — conditions that create voltage and thermal constraints that can slow or complicate generation connections.
Understanding which part of the ENW network your site sits on is the first step in gauging how straightforward your G99 application will be.
G98 vs G99: Which Applies to Your System?
The dividing line is 3.68 kW per phase at the point of connection.
| System Size | Standard | Process |
|---|---|---|
| Up to 3.68 kW per phase (single-phase: up to 3.68 kW; three-phase: up to 11.04 kW) | G98 | Self-notification to ENW within 28 days of commissioning |
| 3.68 kW per phase and above (single-phase: 3.68+ kW; three-phase: 11.04+ kW) | G99 | Pre-application and formal approval before installation |
| Export-limited systems | G98 or G99 depending on inverter export capacity | G100-compliant active export controller required |
For most residential rooftop systems, G98 applies. For commercial rooftop systems and ground-mount arrays of any meaningful scale, G99 is required.
G98 Notification Deadline
G98 notifications must reach ENW within 28 days of the system being commissioned and connected to the grid. Late notifications can result in the system being treated as non-compliant. Submit through the ENW connections portal or by email to the SSEG team.
For a detailed comparison of the two standards, see the G98 vs G99 guide.
ENW Connections Portal
All G98 notifications and G99 applications are handled through the ENW connections portal at enwl.co.uk/connections. The portal allows you to:
- Create and manage connection applications
- Upload supporting documents
- Track application status
- Receive and accept connection offers
- Submit commissioning test results
Before accessing the portal, you need to register as a contractor or designer. ENW requires a company name, contact details, and confirmation that the applicant is a qualified electrical engineer or is working under one.
Pro Tip
Register on the ENW portal before you have a live project. Account creation and verification can take a few days, and you cannot submit a G99 application until your account is active. Getting this done early avoids delays at the start of the application process.
G98 Notification Process
For systems up to 3.68 kW per phase, the process is notification rather than application. The installer or designer notifies ENW that a compliant system has been connected.
Required information for G98 notification:
- Site address and MPAN (Meter Point Administration Number)
- Installed capacity in kW and kVA
- Inverter make, model, and type test certificate reference
- Date of commissioning
- Installer details and qualification reference (MCS certificate number for domestic systems)
ENW does not issue a formal approval for G98 systems — the notification is a record that the connection has been made in accordance with the standard. However, ENW may carry out spot checks on notified installations, and any system found not to comply with G98 technical requirements will need to be rectified.
G99 Application Process
G99 applies to any generation system at or above 3.68 kW per phase. The process has two stages: a pre-application or feasibility stage, and a full application stage.
Stage 1: Pre-Application / Feasibility
Before submitting a full G99 application, it is good practice — and for larger systems, practically necessary — to request a pre-application feasibility study from ENW. This costs a fee (typically £200–£500 depending on system size) and provides:
- Confirmation of the available network capacity at the connection point
- An early indication of whether reinforcement will be required
- Guidance on whether export limitation would be an acceptable alternative to reinforcement
- An indicative programme for the connection
Register on the ENW Connections Portal
Go to enwl.co.uk/connections and create an account. Select ‘New Connection’ and choose ‘Embedded Generation’ as the connection type. You will need the site address, your installer details, and a basic description of the proposed system before you can start the application.
Stage 2: Full G99 Application
Once you have a design developed to a sufficient level of detail, submit the full G99 application through the portal. ENW requires the following documents:
Mandatory documents:
| Document | Notes |
|---|---|
| Completed G99 application form | ENW’s own form, available on the portal |
| Single-line diagram | Showing generation system, protection, metering, and connection to ENW network |
| Site plan | Showing connection point, cable route, and generation equipment location |
| Equipment schedule | Inverter datasheets, protection relay specifications |
| Protection coordination study | For systems above certain sizes or in constrained network areas |
| Export control confirmation | If export limiting is proposed — confirm G100-compliant controller |
Optional but useful:
- Pre-application correspondence from ENW
- Load flow study results
- Planning permission reference (if applicable)
Submit the G98 notification or G99 application
For systems below 3.68 kW per phase, complete the G98 self-notification form within 28 days of commissioning. For systems at or above 3.68 kW per phase, submit the G99 pre-application or full application form through the portal before any installation work begins. Attach the completed application form, site plan, single-line diagram, and equipment schedule.
ENW Technical Assessment
After submission, ENW’s connections engineers carry out a technical assessment. This involves load flow modelling of the relevant network section to check:
- Thermal ratings of cables and transformers
- Voltage rise at the point of connection and across the feeder
- Fault level contributions
- Protection coordination with existing network protection
For straightforward connections on well-meshed urban networks, this assessment is fast and usually confirms connection without reinforcement. For rural connections or systems in areas where ENW has identified network constraints, the assessment may identify the need for network reinforcement or export limitation.
Connection Offer
ENW issues a connection offer setting out:
- The agreed connection point and voltage level
- Any reinforcement works required and their cost
- Protection settings and requirements
- Export conditions (maximum export level if export-limited)
- Programme for connection works
- Offer validity period (typically 90 days)
You must accept the offer in writing within the validity period and pay any quoted charges before ENW will proceed.
Respond to ENW’s technical assessment and accept the connection offer
ENW will issue a feasibility response or full technical offer outlining any reinforcement requirements, protection settings, and export conditions. Review the offer, confirm acceptance in writing, and pay any quoted connection charges before commissioning. A commissioning test witnessed by ENW or a qualified third party may be required for G99 systems.
ENW-Specific Standard Conditions
ENW applies the ENA G99 standard with the following supplementary requirements specific to its network:
Protection settings: ENW specifies particular under/over voltage and under/over frequency protection settings that must be programmed into inverters or protection relays. These are broadly in line with the G99 defaults but ENW may specify tighter settings for sites in constrained areas.
Power factor: ENW requires generation systems to operate at or near unity power factor or, for larger systems, to operate with reactive power capability as specified in the connection offer.
Metering: For G99 systems, ENW requires a metering point at the point of connection. The meter arrangement must comply with ENW’s metering specifications and be accessible to ENW staff.
Fault ride-through: Systems above certain capacity thresholds must comply with G99 fault ride-through requirements, maintaining connection during specified voltage dip events rather than disconnecting.
Anti-islanding: All G99 systems must have anti-islanding protection that disconnects the generation system if ENW’s network becomes de-energised. ENW requires that this protection meets the response times specified in G99.
Export Limiting in Constrained Areas
Parts of the ENW network — particularly rural feeders in Cumbria and Lancashire — have limited headroom for additional generation export. In these areas, ENW may require export limitation as a condition of connection.
Export limitation means fitting a G100-compliant active export controller (AEC) that monitors the energy flow at the grid connection point and curtails the inverter output to prevent export above an agreed maximum level.
Benefits of export limitation:
- Avoids the cost and time of network reinforcement
- Enables connection in areas that would otherwise be refused
- Faster programme — ENW can often complete an export-limited connection more quickly than a reinforced connection
Drawbacks:
- The system cannot export above the agreed limit, which reduces revenue from export tariffs and Smart Export Guarantee payments
- The export limit is fixed in the connection agreement; increasing it requires a new application
Export Limit Agreement
If ENW offers a connection subject to export limitation, the export limit is a legal condition of your connection agreement. Operating the system above the agreed export limit is a breach of your connection agreement and can result in disconnection. Ensure your AEC is correctly configured and calibrated before commissioning.
For guidance on G99 commissioning requirements once your connection is agreed, see the G99 commissioning test guide.
SSEG Connection Process
ENW operates a dedicated SSEG (Small Scale Embedded Generation) process for generation systems up to around 1 MW connecting at low voltage or at simple 11 kV points. SSEG sits within the broader G98/G99 framework but is handled by a dedicated team with documentation tailored to smaller-scale applicants.
The SSEG process is designed to be more accessible than ENW’s large-scale connections process. Key features:
- Dedicated SSEG application forms (simpler than full industrial forms)
- SSEG team contact for technical queries
- Pre-application meetings available for projects of any size
- Streamlined feasibility assessment for straightforward connections
For solar design software users designing commercial rooftop systems in the ENW area, the SSEG route is the most relevant path. Systems in the range of 50 kW to 1 MW will typically follow G99 via the SSEG process.
Network Reinforcement
Where the ENW network cannot accommodate a generation system without reinforcement, ENW will set out the required works in the connection offer. Reinforcement may involve:
- Uprating or replacing cables or overhead lines
- Installing or uprating transformers
- Installing or modifying network protection
- Installing reactive power compensation
The cost of reinforcement is shared between ENW and the applicant according to Ofgem’s charging arrangements. For generation connections, the applicant typically pays for shallow connection works (the connection from the generator to the network boundary) while ENW recovers reinforcement costs through its use-of-system charges.
For large systems or systems in constrained areas, reinforcement costs can be significant — sometimes exceeding the system installation cost for smaller projects. Running a pre-application feasibility study to understand reinforcement requirements before committing to a site is good practice.
Cost Before Commitment
ENW’s connection offer will include a cost breakdown for any reinforcement required. You are not obligated to proceed after receiving the offer — you can decline without penalty if the reinforcement cost makes the project unviable. Always get the offer before committing significant capital to the project.
Application Timelines
| Stage | ENW Target | Notes |
|---|---|---|
| Pre-application feasibility response | 30 business days | May be shorter for straightforward connections |
| Full G99 offer | 45 business days | From receipt of complete application |
| Complex connection offer | 90+ business days | Where reinforcement studies are required |
| Connection works (ENW side) | Variable | Depends on reinforcement scope; may be 6–18 months for major works |
| G98 notification acknowledgement | No formal target | ENW confirms receipt; no approval issued |
These are ENW targets under the Electricity (Connection Standards of Performance) Regulations. ENW is required to compensate applicants if it misses statutory timescales for certain connection types.
Pro Tip
Use good solar design software to produce accurate single-line diagrams and equipment schedules before submitting to ENW. Incomplete or inaccurate applications are a common cause of delays — ENW will return an application that is missing required documents, and the clock does not start until a complete application is received.
Contact Details
ENW Connections Portal: enwl.co.uk/connections
SSEG Team: connections@enwl.co.uk
Telephone: 0800 048 4080 (connections enquiries)
Postal address:
Electricity North West Limited
Connections Team
Borron Street
Stockport
SK1 2JD
For urgent technical queries during the application process, ENW’s connections engineers are contactable by phone or email during normal business hours.
Design and Document Your ENW Solar Connection
SurgePV generates the single-line diagrams, equipment schedules, and export calculations ENW requires for a G99 application — saving hours of manual documentation on every project.
Book a DemoNo commitment required · 20 minutes · Live project walkthrough
Other UK DNOs
If your project is outside the ENW service area, the following guides cover the other UK distribution network operators:
- UK Power Networks — South East England, East of England, London
- NGED (National Grid Electricity Distribution) — Midlands, South West England, South Wales
- Northern Powergrid — Yorkshire, North East England
- SP Energy Networks — Central and Southern Scotland, Merseyside, North Wales, Cheshire
- SSE Networks — North of Scotland, South of England
See the UK solar compliance hub for the full framework, or read the G99 application guide for a standard-by-standard walkthrough.
Frequently Asked Questions
Does Electricity North West use the ENA G99 standard or its own bespoke process?
ENW implements the ENA Engineering Recommendation G99 for generation systems 3.68 kW per phase and above. For systems below that threshold, G98 self-notification applies. ENW does not operate a separate bespoke standard, but it does have specific technical appendices and supplementary conditions that apply within its network area.
How long does a G99 application take with Electricity North West?
ENW targets a feasibility study response within 30 business days and a full offer within 45 business days for straightforward connections. More complex connections requiring reinforcement can take 90 business days or longer. Export-limited connections generally move faster because they avoid the need for network reinforcement studies.
What is an SSEG connection and how does it differ from a standard G99 application?
SSEG stands for Small Scale Embedded Generation. ENW uses this term to describe generation systems typically up to around 1 MW that connect at low voltage or at simple 11 kV points. The SSEG connection process follows G98 or G99 depending on system size, but ENW provides dedicated guidance documents and a specific SSEG team to handle these applications separately from large-scale industrial connections.
Can I install an export limiter to avoid a full G99 network study?
Yes. ENW accepts export-limited connections in areas where network capacity is constrained. Fitting a G100-compliant active export controller can reduce or eliminate the need for network reinforcement, which lowers both cost and programme time. ENW will confirm whether export limitation is appropriate during the pre-application or feasibility stage.