Quick answer
Active power P (kW) is average energy-transfer rate; reactive power Q (kvar) describes reactive AC exchange. Apparent power S (kVA) relates to equipment voltage-current loading, with waveform and measurement context required.
Answer: Active power P, measured in watts or kW, is the average rate of electrical energy transfer. Reactive power Q, measured in var or kvar, describes the reactive component in AC operation. Apparent power S, measured in VA or kVA, relates to voltage and current loading. Their simple power-triangle relationship applies under sinusoidal conditions; harmonic distortion requires additional measurement context.
Three quantities, three units
Keep the useful distinction between energy transfer, reactive exchange, and equipment loading:
| Quantity | Common symbol and unit | Meaning in an AC review |
|---|---|---|
| Active or real power | P, kW | Average energy-transfer rate, including useful output and real losses |
| Reactive power | Q, kvar | Reactive exchange associated with phase relationships and electric or magnetic fields |
| Apparent power | S, kVA | Voltage-current loading measure; for one phase, RMS voltage times RMS current |
| Active energy | kWh | Active power accumulated over time at a specified boundary |
Active power is not itself an energy quantity. The kilowatt-hour reference explains the time dimension. Reactive power should not be described as equipment converting electricity into useful mechanical work, but it can matter for current, voltage operation, and equipment limits.
For import/export or injection/absorption, declare the meter’s sign convention and connection point. A positive Q reading does not have a universal meaning across every meter or generator convention.
When the power triangle applies
For sinusoidal single-phase operation, or a consistently defined balanced sinusoidal three-phase total:
S² = P² + Q²
|Power factor| = |P| / S = |cos(phase angle)|
For a consuming load with positive P, this reduces to P/S. Under waveform distortion, true power factor includes distortion effects; displacement power factor describes the fundamental voltage-current phase relationship. Do not substitute a displacement reading for total power factor without checking the measurement definition.
Fluke’s power-quality troubleshooting guide, particularly its total-versus-displacement discussion, explains why harmonic currents change that distinction. The familiar right triangle is useful for declared sinusoidal examples, not a universal decomposition of every distorted or unbalanced system. See power factor for the ratio and measurement context.
Hypothetical sinusoidal example, not an inverter specification: For S = 10 kVA and consuming-load PF = 0.90, P = 9 kW and the magnitude of Q is 4.36 kvar. The quantities combine through the square relationship, not ordinary addition.
If 10 kW of active power is required at the same PF, the corresponding apparent power is 11.11 kVA and reactive-power magnitude is 4.84 kvar. This arithmetic does not select an inverter, conductor, transformer, or protection device. Ratings, operating envelopes, voltage, temperature, phase loading, and applicable design rules still need review.
Why PV generation does not automatically improve site power factor
A solar inverter’s own operating point and the site’s grid-meter operating point are different. Reducing imported active power while leaving reactive demand unchanged can reduce the grid-meter power factor.
Hypothetical balanced sinusoidal import case: A facility draws 100 kW and 40 kvar before PV contribution. Assume a PV inverter then supplies 60 kW locally with zero Q contribution, and the load remains unchanged.
| Grid-meter condition | Imported P | Imported Q | Apparent S | P/S |
|---|---|---|---|---|
| Before PV | 100 kW | 40 kvar | 107.70 kVA | 0.9285 |
| With the stated PV contribution | 40 kW | 40 kvar | 56.57 kVA | 0.7071 |
Import power and apparent loading fell, while the ratio also fell. This is an illustrative electrical balance, not a tariff outcome or measured facility result. It shows why an inverter’s unity-PF operation cannot be described as automatic facility PF correction.
Use interval measurements at the applicable connection point. Review both direction and magnitude where import approaches zero or becomes export; a single PF number can obscure the operating situation.
Inverter reactive capability and approved control settings
Some inverter systems can inject or absorb reactive power within their documented operating envelope. Constant PF, constant Q, and voltage-reactive-power control are different functions. A voltage-control curve does not automatically target a facility billing ratio.
The national laboratory IEEE 1547-2018 voltage/reactive-power overview explains that capability utilization and settings require stakeholder decisions. Its technical report discusses operating categories, controls, and reactive-power priority. These documents describe that standard’s context; they do not establish its adoption or the correct settings for every project worldwide.
The simple kVA circle gives a first check for a declared sinusoidal case. Actual available P and Q require the exact equipment curve and operating conditions. Whether active power must be reduced depends on capability, the requested operating point, and the applicable control priority. Do not assume every reactive command always reduces energy, or that unused nameplate capacity establishes all required capability.
Record:
- inverter model, regional certification, firmware, and P-Q capability basis;
- connection point, sign convention, measurement type, and operating period;
- applicable interconnection conditions and approved control mode/setpoints;
- active/reactive priority and operating limits;
- commissioning method, responsible reviewer, and retained results.
Qualified personnel should configure and verify the accepted settings using the manufacturer’s and project’s procedures. This explanation is not a field-setting instruction.
Keep billing claims separate from electrical capability
A bill may contain energy, demand, apparent-demand, reactive-energy, or power-factor provisions according to its tariff and metering rules. Do not infer a penalty or savings from a residential/commercial label, a nominal threshold, or the inverter’s own PF.
Before evaluating compensation, obtain the current tariff, meter definitions, relevant interval records, and approved controls. Review whether the proposed equipment can address the actual measurement and whether other compensation equipment or harmonic conditions affect the result. Financial claims need their own evidenced calculation.
Designers should reconcile P/Q/S boundaries and operating limits. Installers should retain the approved commissioning records. Sales teams should carry those assumptions into the proposal without promising penalty elimination. Bring the requirements to a SurgePV demo and verify which equipment inputs, controls, and reporting outputs the workflow supports.
Frequently asked questions
Is reactive power the same as kWh?
No. Reactive power is expressed in var or kvar. kWh is accumulated active energy. Metering can also include reactive-energy quantities, but those have their own units, definitions, and tariff treatment.
Does a solar inverter always correct the building’s power factor?
No. Its operating point differs from the net site-meter balance. Capability, permitted controls, load behavior, and measurement definitions matter. The illustrative unity-PF PV case above reduces imported active power while lowering the import power-factor ratio.
What power-factor setting should be used?
Use the approved project and manufacturer requirements. There is no universal setting. Confirm the control mode, measurement point, sign convention, capability limits, and applicable interconnection conditions with the responsible reviewer.
Sources reviewed September 30, 2026. Numerical examples assume balanced sinusoidal conditions; they do not establish equipment selection, compliance, or tariff savings.
Related Glossary Terms
About the Contributors

Editorial contributor · SurgePV
Rainer Neumann is credited as an editorial contributor on SurgePV content. This profile does not assert engineering credentials, project totals, software-testing experience, education, speaking engagements, or media citations because independent verification evidence is not retained in the publication record.

CEO & Co-Founder · SurgePV
Keyur Rakholiya is identified by SurgePV as its CEO and a company co-founder. His SurgePV author page lists only role information that can be tied to the public profile below; credentials, project totals, testing claims, media appearances, and speaking engagements are not asserted without retained evidence.