Back to Blog
solar roi22 min read

Commercial Solar ROI Calculator: Payback, IRR, LCOE

Model commercial solar ROI with payback, IRR, NPV and LCOE formulas, a worked 100 kW example and sensitivity tables you can rebuild in Excel.

Akash Hirpara

Written by

Akash Hirpara

Co-Founder · SurgePV

Rainer Neumann

Edited by

Rainer Neumann

Editorial contributor · SurgePV

Published ·Updated

Answer

Commercial solar ROI is measured with payback, IRR, NPV and LCOE, and the result depends mostly on your electricity price, installed cost, self-consumption and incentives. In this guide's illustrative 100 kW model, simple payback is 12.2 years with no incentives and 8.2 years with a 30 percent upfront incentive assumption.

Commercial solar is a capital allocation decision. A CFO does not care about panels, inverters or tilt angles. A CFO cares whether the project beats the hurdle rate, how fast the cash comes back and what could go wrong.

This guide covers the financial modeling stack for commercial solar from 50 kW to 500 kW: payback, internal rate of return (IRR), net present value (NPV) and levelized cost of energy (LCOE). Every formula is shown and every assumption is stated. The worked examples use illustrative inputs that you should replace with your own bids, tariffs and tax advice. They are not market data.

Last updated: November 2026

SurgePV publishes this post and sells solar design software, which is discussed near the end. For a direct software comparison, see Arka 360 vs SurgePV.

TL;DR: Commercial Solar ROI

ROI depends mainly on your electricity price, installed cost, self-consumption rate and incentives. In the illustrative 100 kW model below, a $200,000 system saving $15,600 in year one has a static payback of 12.8 years and a 25-year IRR of 7.9 percent with no incentives. A 30 percent upfront incentive assumption lifts IRR to 12.1 percent. Always state which incentives are included.

Model Payback on Your Own Commercial Roof?

Run production, cost and savings for your own site and see IRR, LCOE and payback update as the design changes.

Book a Demo

Checking cost first? See the SurgePV pricing page · 20 minutes · Live project walkthrough

In this guide:

  • What commercial solar ROI calculators measure
  • How to calculate payback, with a worked example
  • IRR, NPV and LCOE formulas and results
  • System size, financing and incentives
  • Operating costs, escalation and sensitivity
  • Electricity prices by state from EIA
  • A modeled warehouse example (not a real project)
  • Common modeling errors

What Commercial Solar ROI Calculators Measure

A commercial solar ROI calculator is not a single formula. It is a stack of metrics that each answer a different question.

Metric Question it answers Notes
Simple payback How many years until cumulative savings equal the net cost? Easy to explain, ignores time value of money
Discounted payback Same, with each year’s savings discounted Longer than simple payback
IRR What annualized return does the project earn? Depends on cash flow timing and incentives
NPV How much value is created in today’s dollars at your discount rate? Positive means the project beats the rate
LCOE What does each kWh cost over the system’s life? State whether it is gross or net of incentives

These metrics are not interchangeable. A project can have a short payback and a modest IRR if savings are front-loaded, and a longer payback with a higher IRR if savings grow quickly. Report more than one.

What a Good Calculator Models

A serious commercial solar financial model includes four groups of inputs:

  1. Savings side: energy production (kWh per year), self-consumption rate, export rate, electricity price, price escalation, and any REC revenue.
  2. Cost side: installed cost, interconnection fees, permitting, financing cost, O&M, insurance, inverter replacement and end-of-life cost.
  3. Tax side: incentives, depreciation and state or local programs. Tax rules change, so check current IRS guidance and a tax advisor instead of relying on a rule of thumb.
  4. Time side: construction period, analysis period (25 years is common), discount rate and degradation.

Many free calculators cover only the first two groups, so they miss tax effects that can change the result materially.

Pro Tip: Build Your Own Model

Free online calculators are fine for first-pass screening. For a capital decision, build a spreadsheet or use PV design software with integrated financials, and write the assumptions on the first tab. NLR’s System Advisor Model is a free reference for cash-flow modeling.


How to Calculate Commercial Solar Payback Period

Payback is the simplest metric. It is also the easiest to misuse. See our glossary entry on payback period calculation for the basics.

Simple Payback Formula

Simple Payback = Net Project Cost / Annual Net Savings

Illustrative example inputs (assumptions, not market data):

Input Value
System size 100 kW
Installed cost $2.00/W = $200,000
Annual production 140,000 kWh
Self-consumption rate 75%
Electricity price $0.14/kWh
Export rate $0.08/kWh
Annual O&M $1,500
Insurance $400

Annual savings = (140,000 x 0.75 x $0.14) + (140,000 x 0.25 x $0.08) - $1,500 - $400 Annual savings = $14,700 + $2,800 - $1,900 = $15,600

Static payback on gross cost = $200,000 / $15,600 = 12.8 years

That looks weak, which is why incentives matter. The table shows the same system under three scenarios. The “upfront incentive” is a scenario input that reduces net cost. It is not a statement of current tax law.

Scenario Net cost Static payback (year-1 savings) Payback with escalation and degradation
No incentives $200,000 12.8 years 12.2 years
30% upfront incentive $140,000 9.0 years 8.2 years
50% upfront incentive $100,000 6.4 years 6.0 years

The last column uses a model with 3% annual electricity price escalation, 0.5% annual module degradation, O&M growing 2.5% a year and a $20,000 inverter replacement in year 12.

Discounted Payback

Discounted payback recognizes that a dollar saved in year 10 is worth less than a dollar saved in year 1.

Discounted Payback = the year in which cumulative discounted cash flow turns positive

Using an 8% discount rate on the 50% upfront incentive scenario ($100,000 net cost):

Year Net savings Discount factor (8%) Discounted savings Cumulative (net of cost)
1 $15,600 0.926 $14,444 -$85,556
2 $15,987 0.857 $13,707 -$71,849
3 $16,384 0.794 $13,006 -$58,843
4 $16,791 0.735 $12,342 -$46,500
5 $17,208 0.681 $11,712 -$34,789
6 $17,635 0.630 $11,113 -$23,676
7 $18,073 0.583 $10,546 -$13,130
8 $18,522 0.540 $10,007 -$3,123

Cumulative discounted cash flow turns positive early in year 9, so discounted payback is about 8.3 years, against 6.0 years for simple payback in the same scenario. With no incentive, discounted payback is not reached within 25 years at an 8% rate.

Key Takeaway

Report discounted payback alongside simple payback, and show payback at low, base and high escalation. Simple payback can mislead stakeholders who think in terms of the cost of capital.


IRR Calculation for Commercial Solar

IRR is the discount rate at which NPV equals zero. It answers: what annualized return does the project generate?

0 = -Initial Investment + SUM [Annual Cash Flow_t / (1 + IRR)^t] for t = 1 to N

Excel handles this with =IRR() or =XIRR() for irregular cash flows. What matters is building the cash-flow stream correctly: upfront cost, annual savings net of O&M and insurance, the inverter replacement and any incentive cash flows.

Results for the Illustrative 100 kW System

The cash flows use the inputs above, with 25 years of operation. The model is pre-tax apart from the upfront incentive scenarios.

Scenario Net cost 25-year IRR NPV at 8% Simple payback Discounted payback
No incentives $200,000 7.9% -$1,406 12.2 years Not reached in 25 years
30% upfront incentive $140,000 12.1% $58,594 8.2 years 14.1 years
50% upfront incentive $100,000 17.1% $98,594 6.0 years 8.3 years

The no-incentive IRR of 7.9 percent sits just under the 8 percent discount rate, which is why NPV is about zero. The point of the table is the spread. The same roof and the same production give a 7.9 to 17.1 percent IRR depending on what the owner can claim.

Compare Against Your Own Hurdle Rate

Do not compare IRR to a table of “typical” returns from other asset classes. Use your company’s own cost of capital or hurdle rate, and compare the solar project with the alternatives you are actually choosing between: another equipment upgrade, a debt paydown or leaving the cash in the business. Our post on 9 solar ROI mistakes that make savings claims hard to trust covers how to present this to a board.


LCOE for Commercial Solar Systems

LCOE strips away financing and tax appetite. It asks what each kilowatt-hour costs to produce over the system’s life. See the glossary entry on LCOE.

LCOE = (Initial Investment + SUM[O&M_t / (1+r)^t] + PV of replacements - Residual Value) / SUM[Production_t / (1+r)^t]

Worked LCOE Example: 100 kW System

Parameter Value
Initial investment $200,000
Analysis period 25 years
Discount rate 8%
Year 1 production 140,000 kWh
Annual degradation 0.5%
PV of 25 years of production 1,434,885 kWh
PV of O&M and insurance $25,194
PV of inverter replacement (year 12) $7,942
Residual value $0 (assumed)

Gross LCOE = ($200,000 + $25,194 + $7,942) / 1,434,885 kWh = $0.162/kWh

Net of a 30% upfront incentive scenario: ($140,000 + $25,194 + $7,942) / 1,434,885 = $0.121/kWh. Net of a 50% scenario: ($100,000 + $25,194 + $7,942) / 1,434,885 = $0.093/kWh.

The lesson is to say whether an LCOE is gross or net of incentives, and which discount rate was used. LCOE is also sensitive to the discount rate: an 8% rate weights early production far more than the later years.

Pro Tip: Use LCOE for Comparing Energy Sources

LCOE is the right metric for comparing solar with grid supply or other generation. It is less useful for comparing projects with different financing structures. For financing comparisons, use IRR or NPV on equity cash flows.


System Sizing Impact on ROI

Larger systems usually cost less per watt, but they can face different interconnection rules, permitting and space constraints. NLR publishes installed-cost benchmarks for PV systems by sector on its solar installed system cost page. Use that or your own bids for the cost per watt.

The table below uses hypothetical cost-per-watt inputs to show how size changes the result. They are not market prices. The other assumptions are the same as the 100 kW example: 1,400 kWh per kW per year, $0.14 per kWh at 75% self-consumption, $0.08 export, O&M of $15 per kW-year, insurance of $4 per kW-year and an inverter replacement at $0.20 per W in year 12.

Metric 50 kW 100 kW 250 kW 500 kW
Hypothetical cost per W $2.40 $2.00 $1.80 $1.60
Installed cost $120,000 $200,000 $450,000 $800,000
Year 1 net savings $7,800 $15,600 $39,000 $78,000
IRR, no incentives 6.1% 7.9% 9.1% 10.4%
NPV at 8%, no incentives -$20,703 -$1,406 $46,484 $192,969
IRR, 30% upfront incentive 9.8% 12.1% 13.5% 15.3%
NPV at 8%, 30% upfront incentive $15,297 $58,594 $181,484 $432,969

Savings per kW are identical across the columns, so the improvement comes only from the assumed lower cost per watt. Real projects also differ in roof area, interconnection cost and tariff structure. A single roof often limits size before cost does, and ground-mount systems add land and zoning questions. See our ground mount system entry and the solar carport design guide for those cases.


PPA vs. Cash Purchase vs. Loan vs. Lease

Financing structure changes who owns the system and who captures savings and incentives. The qualitative comparison is below. Specific terms vary by provider, so get written quotes.

Dimension Cash purchase Loan PPA Lease
Upfront cost Full cost Down payment Typically none Typically none
Ongoing payments None Loan payments Per-kWh payments Fixed lease payments
Owner Host Host Third party Third party
Incentives claimed by Host Host Third party, priced into the rate Third party, priced into the payment
O&M responsibility Host Host Usually third party Depends on the contract
Residual value Host Host Third party or buyout Third party or buyout

For definitions, see the glossary entries on power purchase agreement and loan, cash and PPA modeling.

Cash vs. Loan in the Illustrative Model

Assumptions: $200,000 installed cost, no incentives, an 80 percent loan at 6.5 percent over 10 years, and the 100 kW cash flows above.

Metric Cash purchase Loan (80% of cost)
Upfront equity $200,000 $40,000
Annual loan payment (years 1 to 10) None $22,257
Equity IRR (25 years) 7.9% 8.8%
NPV at 8% -$1,406 $9,249

Leverage helps only when the project’s return exceeds the cost of debt. Here the project IRR of 7.9 percent is barely above the 6.5 percent loan rate, so the equity IRR improves only slightly, and annual cash flow is negative in the early years because the loan payment ($22,257) exceeds year-one savings ($15,600). A loan makes more sense where incentives or high electricity prices lift project returns well above the interest rate.

Key Takeaway

Do not assume a loan or a PPA is the best structure. Compare equity cash flows under each option using your own rates, and check how each affects the incentive you can claim. Our post on financing comparisons that mislead buyers lists common traps.


Tax Incentives for Commercial Solar

Incentives can be the largest driver of commercial solar economics. They are also the part of a model most likely to be out of date. U.S. federal credits, depreciation rules and state programs have changed several times, and eligibility can depend on when construction begins and when the system is placed in service.

Treat incentives as explicit scenario inputs:

  • Federal credits and deductions: Check current IRS guidance and ask a tax advisor which credit and depreciation rules apply to your project, entity and dates. See also our glossary entry on MACRS depreciation.
  • State and utility programs: Programs differ widely in form (rebates, per-kWh payments, REC markets, property-tax treatment) and change often. The DSIRE database, run by the N.C. Clean Energy Technology Center, lists incentives and policies by state.
  • Tax appetite: An owner needs enough tax liability to use credits and deductions. If not, a third-party owner through a PPA or lease may capture them, with the benefit passed on through the price.

Run the model at several incentive levels, as in the tables above, and show the project with and without them. If a project only works with one specific incentive, say so on the first page.


Operating Expenses

Operating costs are not an afterthought. Over 25 years they can be a meaningful share of project cost, and models that skip them overstate returns.

Category What it covers How to estimate
Monitoring and reporting Data subscriptions, performance reports Vendor quote
Cleaning Soiling removal, site-dependent Local contractor quote
Inspections Visual and electrical checks Maintenance contract
Vegetation management Ground-mount sites Site-specific
Inverter maintenance Routine service Manufacturer or O&M contract
Insurance Rider or base-policy coverage Broker quote
Major capital event Timing Treatment in the model
Inverter replacement Often within the system’s life DOE says inverters are expected to be replaced at least once in the 25-year lifetime of a PV array
Roof membrane work Depends on roof age Check the roof condition report
Module failures Scattered Warranty claims, reserve if needed
Decommissioning End of life Check the lease or contract terms

The DOE statement comes from its PV system design basics page, checked November 2026. For module warranty and degradation, use the manufacturer’s own datasheet and warranty terms, and our glossary entry on degradation rate.

Key Takeaway

Include an inverter replacement in every 25-year model. In the 100 kW example, leaving it out would lift IRR and shorten discounted payback without any change in the system.


Escalation Assumptions and Sensitivity Analysis

The most consequential assumptions are the electricity price escalation and the discount rate. Avoid a single “base case”. Show a range and say where each number came from.

Sensitivity Table: IRR by Installed Cost and Escalation

Base case: 100 kW illustrative model with a 30% upfront incentive scenario.

Installed cost 0% escalation 1% 2% 3% 4%
$1.60/W 11.7% 12.9% 14.1% 15.3% 16.4%
$1.80/W 10.0% 11.2% 12.4% 13.5% 14.7%
$2.00/W 8.6% 9.8% 10.9% 12.1% 13.2%
$2.20/W 7.4% 8.6% 9.7% 10.9% 12.0%
$2.50/W 5.9% 7.1% 8.2% 9.4% 10.5%
$2.80/W 4.7% 5.9% 7.0% 8.1% 9.2%

Each $0.20 per watt change in installed cost moves IRR by roughly 1 to 1.7 percentage points in this model, and each percentage point of escalation moves it by about 1.1 to 1.2 points.

Sensitivity Table: NPV by Discount Rate and Escalation

Same base case, $2.00 per watt.

Discount rate 0% escalation 1% 2% 3% 4%
6% $33,113 $53,317 $76,394 $102,815 $133,128
8% $6,225 $21,520 $38,869 $58,594 $81,074
10% -$14,275 -$2,483 $10,798 $25,796 $42,772
12% -$30,218 -$20,968 -$10,621 $984 $14,031

The sign of NPV changes inside the table. A project that looks fine at a 6 percent discount rate and 3 percent escalation can fail at 10 percent and 1 percent. That is why the escalation assumption is the most argued line in any solar model.

Which Inputs Matter Most

A useful way to rank inputs is a tornado analysis: change one input at a time by the same relative amount and rank the effect on NPV. Do it on your own model rather than relying on a generic ranking. In most commercial models the electricity price, installed cost and self-consumption rate dominate. Document how you chose each range.


Electricity Prices by State

Solar economics vary more by electricity price than by system design. The chart shows the average retail price of electricity in the commercial sector for a few states, from the U.S. Energy Information Administration.

Average commercial electricity price by state, August 2026 (cents per kWh, monthly average, preliminary)
  • Hawaii43.55 c
  • California30.02 c
  • Massachusetts24.11 c
  • New York23.06 c
  • Illinois14.67 c
  • U.S. total14.47 c
  • Arizona13.05 c
  • Ohio12.31 c
  • Florida11.35 c
  • Texas8.96 c

Source: EIA Electric Power Monthly, Table 5.6.A (commercial sector, August 2026 monthly data), checked November 2026.

These are average prices across all commercial customers in a state. A specific building’s avoided cost depends on its tariff, including demand charges, time-of-use periods and fixed charges, so use the actual bill.

What the Price Does to Payback

The table applies each state’s average price to the same illustrative 100 kW system: 140,000 kWh per year, 75% self-consumed at the state price, 25% exported at $0.08, and $1,900 a year in costs. It shows static payback on the $200,000 gross cost. It ignores state differences in production and installed cost, so it isolates the effect of price only.

Region Avg commercial price (Aug 2026) Year 1 net savings Static payback on $200,000
Hawaii 43.55 c/kWh $46,628 4.3 years
California 30.02 c/kWh $32,421 6.2 years
Massachusetts 24.11 c/kWh $26,216 7.6 years
New York 23.06 c/kWh $25,113 8.0 years
U.S. total 14.47 c/kWh $16,094 12.4 years
Illinois 14.67 c/kWh $16,304 12.3 years
Arizona 13.05 c/kWh $14,602 13.7 years
Ohio 12.31 c/kWh $13,826 14.5 years
Florida 11.35 c/kWh $12,818 15.6 years
Texas 8.96 c/kWh $10,308 19.4 years
Static payback on a $200,000 illustrative 100 kW system, by state price (illustrative example, not market data) (years, before incentives)
  • Hawaii4.3 yr
  • California6.2 yr
  • Massachusetts7.6 yr
  • New York8 yr
  • U.S. total12.4 yr
  • Ohio14.5 yr
  • Florida15.6 yr
  • Texas19.4 yr

Source: Author's illustrative model using EIA August 2026 commercial prices and the stated assumptions, checked November 2026.

In low-price states, incentives, demand-charge savings or a lower installed cost are what make the project work. Interconnection timelines and costs also differ by utility, so request them from the utility rather than assuming a range.


Modeled Example: 150 kW Warehouse Rooftop

This is a modeled design example, not a real project. The inputs are assumptions chosen to show the arithmetic.

Illustrative Project Parameters

Parameter Value
Host 80,000 sq ft distribution warehouse (hypothetical)
System size 150 kW DC
Modules 300 x 500 W
Annual production 247,500 kWh (1,650 kWh per kW per year, assumed)
Self-consumption 82% (daytime operations, assumed)
Electricity price $0.24/kWh (assumed)
Export rate $0.08/kWh (assumed)
O&M and insurance $2,250 and $600 a year, growing 2.5%
Inverter replacement $30,000 in year 12 (assumed)

Illustrative Financial Structure

Line item Amount
EPC contract $285,000 ($1.90/W)
Interconnection $12,000
Permitting and fees $8,000
Total project cost $305,000

Year 1 savings: 247,500 x 0.82 = 202,950 kWh self-consumed x $0.24 = $48,708, plus 44,550 kWh exported x $0.08 = $3,564, less $2,250 O&M and $600 insurance, giving $49,422.

Year Net annual cash flow (3% price escalation, 0.5% degradation)
1 $49,422
2 $50,650
3 $51,908
4 $53,197
5 $54,519

Illustrative Results

Metric No incentives 30% upfront incentive scenario
Net project cost $305,000 $213,500
Simple payback 5.8 years 4.2 years
Discounted payback (8%) 7.9 years 5.2 years
25-year IRR 18.0% 25.3%
NPV at 8% $337,466 $428,966
25-year net savings (nominal) $1,654,680 $1,654,680

The strong result comes mainly from the assumed $0.24 per kWh price and 82 percent self-consumption. Change either and the picture moves. The point is to show a method you can rerun with your own tariff.

What Could Go Wrong

Risk What changes Mitigation
Tariff restructuring Value of each self-consumed kWh Model low, base and high price cases
Module underperformance Annual production Independent review of the design and the warranty terms
Inverter failure before replacement Unplanned cost Monitoring and a maintenance contract
Roof leak or membrane work Removal and reinstall cost Pre-install roof inspection, roofer sign-off
Host vacancy or bankruptcy Loss of the savings Credit review and lease terms

What Most Commercial Solar ROI Models Get Wrong

These four errors cause the most distortion in commercial solar models.

Error 1: Using an Unsupported Escalation Rate

The sensitivity tables show how much escalation matters. Do not accept a model built on a single high rate. Check your utility’s recent rate history and any published tariff or rate case filings, and run the model at low, base and high rates, including zero.

Error 2: Ignoring Inverter Replacement

DOE notes that inverters are expected to be replaced at least once in the 25-year life of a PV array. A model that omits this shows a better return than reality. Include the cost from the manufacturer’s or integrator’s quote.

Error 3: Assuming 100% Self-Consumption

No building consumes all of its solar output in real time. Maintenance shutdowns, holidays and seasonal changes all create exports. Take the self-consumption rate from an interval-data analysis, not from a round number, and value exports at the actual export rate in your tariff.

Error 4: Treating Incentives as a Sure Thing

Credit rules, deadlines and depreciation treatment have changed in the past. Model the project with and without incentives, as the tables in this guide do. If it only clears your hurdle rate with a specific incentive, flag the dependency and its dates.

Further Reading

For help explaining payback to a non-technical buyer, read 7 ways to explain solar payback without a finance lecture, and for the CFO view, the commercial solar CFO pitch.


Using SurgePV for Commercial Solar Financial Modeling

A financial model is only as good as the production estimate that feeds it. A 10 percent production error is roughly a 10 percent error in annual savings, so the design stage matters.

PV design software like SurgePV connects production modeling with financial analysis. You design the system, model shading and orientation, and take the results into the solar proposal platform. The shadow analysis workflow identifies shading issues before installation. SurgePV supports energy-yield and financial modeling, and results depend on the source data, assumptions, equipment models and configuration you use.

SurgePV system pricing and financial-modeling workflow

SurgePV pricing configuration showing system size, estimated production, per-watt pricing and financial metrics in one view.

The Workflow

  1. Import satellite imagery and draw the roof or ground area
  2. Place modules and select inverters
  3. Run shading analysis and production simulation
  4. Enter pricing, financing and incentive assumptions
  5. Review LCOE, IRR, NPV and payback outputs
  6. Export to a proposal or a spreadsheet for further analysis

See the inverter sizing guide for the electrical side of step 2. For a production baseline, NLR’s PVWatts calculator is a free starting point; its own page says its predictions include many inherent assumptions and uncertainties.

Price a Commercial System Before You Commit?

Design, simulate and price commercial systems in one workflow, with the financial outputs tied to the layout.

Book a Demo

Want plan details first? Read the SurgePV pricing page · No commitment required


Conclusion

Commercial solar ROI is a spreadsheet problem, and the only question is whether you build it with honest assumptions. What the examples in this guide show:

  • A 100 kW system’s IRR moved from 7.9 to 17.1 percent across incentive scenarios on the same roof.
  • Electricity price drives payback more than almost any design choice.
  • Equity returns from a loan improve only when the project return is well above the interest rate.
  • The biggest modeling errors are optimistic escalation, ignoring inverter replacement and assuming full self-consumption.

Three actions for your next evaluation:

  1. Build your own model. Use the vendor’s production estimate if it is documented, but run your own financials with conservative escalation and full O&M.
  2. Stress-test the incentives. Model the project with the incentive reduced or removed. If it still clears your hurdle rate, the project is robust.
  3. Get production right. Use site-specific modeling with shading analysis, then book a demo to see how a design workflow feeds the financials.

Frequently Asked Questions

What is a commercial solar ROI calculator and what does it measure?

A commercial solar ROI calculator estimates the financial return on a photovoltaic project for a business. It computes payback period, internal rate of return (IRR), net present value (NPV) and levelized cost of energy (LCOE), and a good one also models incentives, financing and operating costs.

How do you calculate commercial solar payback period?

Simple payback equals net project cost divided by annual net savings. For example, a $200,000 system with $15,600 of first-year net savings has a static payback of about 12.8 years. Discounted payback is longer because it applies a discount rate to each year’s savings.

What is a good IRR for commercial solar?

There is no universal figure. A good IRR is one that clears your own hurdle rate after realistic assumptions. In this guide’s illustrative 100 kW model the 25-year IRR is 7.9 percent with no incentives and 12.1 percent with a 30 percent upfront incentive assumption.

How is LCOE calculated for commercial solar?

LCOE equals the present value of lifetime costs divided by the present value of lifetime energy. In the illustrative 100 kW model at an 8 percent discount rate, gross LCOE is about $0.162 per kWh, and it falls as incentives reduce the upfront cost.

What operating costs should a commercial solar ROI model include?

Include operations and maintenance, insurance, monitoring, an inverter replacement, possible roof work and end-of-life costs. Leaving out the inverter replacement is a common modeling error because it makes payback look earlier than it is.

How does system size affect commercial solar ROI?

Larger systems usually have a lower installed cost per watt, which improves payback and IRR if the electricity savings per kWh stay the same. In the illustrative model, IRR with no incentives rises from 6.1 percent at 50 kW to 10.4 percent at 500 kW, but that depends entirely on the assumed costs.

What is the most common mistake in commercial solar ROI analysis?

The most common mistake is optimistic inputs: a high electricity escalation rate, full self-consumption and no inverter replacement. Run the model at low, base and high escalation and ask vendors to show their assumptions.


Sources and Further Reading

Where this fits

This article is part of SurgePV's Solar Business & Operations hub, which works through the topic from first principles to the decisions a project team actually has to make.

About the Contributors

Author
Akash Hirpara
Akash Hirpara

Co-Founder · SurgePV

Akash Hirpara is identified by SurgePV as a company co-founder. His SurgePV author page lists only role information that can be tied to the public profile below; education, certifications, project totals, financial results, speaking engagements, and media appearances are not asserted without retained evidence.

Editor
Rainer Neumann
Rainer Neumann

Editorial contributor · SurgePV

Rainer Neumann is credited as an editorial contributor on SurgePV content. This profile does not assert engineering credentials, project totals, software-testing experience, education, speaking engagements, or media citations because independent verification evidence is not retained in the publication record.

Get Solar Design Tips in Your Inbox

Join 2,000+ solar professionals. One email per week - no spam.

No spam · Unsubscribe anytime

Book Free Demo

Choose which optional technologies SurgePV may use. Essential storage remains active for security and requested features.